RE: First deadline tomorrow2 Jun 2023 11:33
SYN have never, in recent history, hit any published deadline.
"The jet pump and modified wellhead will be ready for airfreight shipment to India circa June 5th 2023. The surface pump skid will be ready for airfreighting on June 3rd 2023. Other associated equipment such as motor drive, VFD panel, separator and tubing have been ordered locally for delivery early July 2023. Due to workover rig availability, the re-completion operation is scheduled to commence on July 9th 2023"
If the 3rd and 5th June parts don't happen, the 9th July sure as heck ain't gonna happen. So yes the 3rd and 5th June are important.