RE: Interesting16 Apr 2025 14:23
Also interesting
The time it takes to issue a drilling permit in Western Australia can vary. The Department of Energy, Mines, Industry Regulation and Safety (DEMIRS) aims to complete 80% of assessments within 15 business days, according to the Western Australian Government. However, the actual timeframe can depend on factors like the completeness of the application and the need for environmental assessment. It's recommended to submit applications three months before the planned start of drilling to allow for sufficient time for review and approval, according to the Western Australian Government.
Here's a more detailed breakdown:
DEMIRS Assessment Target:
DEMIRS aims to complete 80% of assessments within 15 business days, but this is dependent on the completeness of the application.
End-to-End Timeframe:
The average end-to-end timeframe for drilling permit approvals can range from 26 to 65 business days, according to a report on mining.com.au.
Environmental Assessments:
Environmental assessments can add to the overall timeframe, so it's crucial to address these issues early in the process.
Application Completeness:
Incomplete applications can lead to delays, so ensuring all necessary information is provided from the start is important.
Submission Timeline:
It's recommended to submit applications three months before the planned start of drilling to allow for sufficient time for review and approval.