So notes taken by one of the Tgm group members at tonight's zoom call with Adam, CEO of Bens Creek Group:
? Railway signed off. NS involvement required for train deliveries, multiple rail deliveries to commence through May. Each train carries 10-15k tonnes.
? Underground mining due to commence imminently.
? Marshal Miller report expected to uplift resource/reserve base significantly. 45 days to produce and on day 27, BEN management meeting MM this Thursday.
? Demand for product is exceptionally high, constant enquiries to produce and deliver above current offtake.
? Awaiting permit for 2nd HWM and to conduct minor works on it before operational
? Anticipate fully ramped up production to 70/80k by July/early Aug onwards.
? Accounts to Mar 22 to be released in June
? Large team of about 100 (BEN/contractors) on site.
80k is @$16m profit…possibly more