The purpose of flaring, during well testing is to monitor the pressure build up.(PBU)
A well is flowed for a well test period anything up to 24 hrs then shut in. The PBU is then monitored for a period, then the well can be flowed again and the sequence repeated if need be. The boffins then do the calc's to find out the specifics of the resevior.