Timings18 Oct 2018 12:11
Back of the fag packet calculations for timings:
Assuming 85m / day drill rate (based on TD 2980 in 35days), first casing point at 450m will be in 5 days from start of drill. Then a further 21 days to get to TOL @2240m (I'm assuming that's the Tagi), then Paleozoic 9 days after that depending upon how long it takes to secure casing points.
with the 45 day schedule i.e 66m/day, 7 days for first casing point, then TOL day 34 and TD 11 days later.
Obviously, just my rough calls, more than happy to be corrected from anybody more in the know.
Such an amazing opportunity and incredibly exciting.