RE: Great RNS! Read the facts!!27 Jun 2018 11:26
Thanks to free I've been pointed towards a post by elegance:-.
You posted this am:
@ penguins “All key equipment necessary to carry out a 150-day long-term extended flow test campaign at HH-1 is now on site.” And there you were yesterday saying it’ll be middle of July minimum, what an idiot you look now as well as many others. Existing and new investors should read the facts, extended well tests now to start, don’t be swayed by those that are shorting Ukog or those that give you misinformation.
Actually I said:-
'I don't think the actual ewt will be that soon.
From the planning application:
Workover and Portland EWT – workover 12 days, EWT 6 weeks.
If a workover rig is being used that has to arrive (2 days) and if not then the crane has to be sited over the well, not unloading lorries.
So if they are operating t the planning application schedule then there's a minimum of 12 working days from now before the ewt could start so mid July?'
So from the planning permission (not a number I made up) there were 12 days of workover once the site was set up before well testing actually started, and this was 'if' they are operating to the planning application'.
So being quite clear where my information was coming from and from information on twitter seeing that the site wasn't fully set up as they were still unloading equipment.
But what is actually happening next according to the RNS:-
'Following final equipment set-up and the subsequent removal of three temporary suspension plugs in the wellbore, flow will first be re-established from the Portland sandstone oil pool.'
So not (as you said) 'extended well tests now to start,' but actually setting up the equipment was not complete and then removing plugs from the wellbore.
So who is giving misinformation?