Timetable4 Jan 2023 15:54
Completion of the Transaction is subject to, inter alia:
• Certain regulatory consents and confirmations;
• Approval by Tulip's shareholders at a general meeting;
• Finalisation of the Placing;
• Publication of an AIM Admission Document; and
• Approval by Beacon Energy's shareholders at a general meeting, including the passing of the Rule 9 Waiver
resolution
Indicative timetable
• Sale and Purchase Agreement signed 15 December 2022
• Publication of AIM Admission Document anticipated late January 2023
• General Meeting of Beacon Energy shareholders anticipated mid February 2023
• Completion targeted mid February 2023