RE: Deliveries at Brockham5 Apr 2019 13:53
The 14 days refers to the well testing which is due after the water isolation. The full test for Stage 1 is here:
Stage 1
Rig acceptance & mobilisation:The delivery of the work-over rig, rigging up and testing rig systems and finally rig acceptance.
Isolation of Water: Full logging program over perforated section to identify water zone. The isolation of the water zone using hydraulically set plug.
Reperforation of Well:Wireline deployed guns to re-shoot the oil section and enable effective communication with the fracture system. Relogging of well to confirm water isolation successful and perforation intervals.
Re-completion of Well:Running of new completion to allow flexibility whilst well in long term production
I expect water isoltion to start immediately followed in 2-3 by the well testing. We will probably know how successful it is in the next 2 weeks.