BP eyes ‘start-up’ of challenging LNG project within weeks5 Nov 2024 07:15
Start-up of BP’s challenging Greater Tortue Ahmeyim liquefied natural gas project offshore Senegal and Mauritania is due this quarter.
The development has been bedevilled by delays and cost overruns but now appears to be closing in rapidly of first production.
According to partner Kosmos Energy, ”cool down and commissioning” of the project’s floating LNG vessel has started, with first LNG “expected around the end of the fourth quarter of 2024.”
It is unclear, however, if this is the date when the first LNG export cargo will be sent to market or whether this is when LNG production starts.
In addition, the first batch of four development wells has been completed, said Kosmos, with expected production capacity significantly higher than is required for first gas.
Work on a hub terminal — which comprises the 2.5 million tonnes per annum FLNG vessel and various utility structures situated behind a concrete breakwater — has been handed over to operations, while the subsea workscope for first gas is mechanically complete.
In addition, said Kosmos, the project's floating production, storage and offloading vessel is ready for startup shortly.
The FPSO will separate produced gas from liquids, before exporting this gas to the FLNG vessel.