Bernard's Friday subjects of discussion12 Nov 2024 14:21
What are your key goals in 3 months, 6 months, 12 months?
3 Months:
Complete construction and commissioning of the Bougouni Lithium Project in Mali.
6 Months:
Start production of lithium concentrate at the Bougouni Mine and generate revenue.
12 Months:
From start of production in 1Q25, produce over 125,000 tonnes of lithium concentrate.
What do you see as the key risks and challenges facing your company at the moment and how are you overcoming these?
Execution risk relating to the development and startup of the Bougouni Lithium Project in Mali.
What do you think makes your company such a compelling investment?
β Top 10 lithium hard rock spodumene resource in the world.
β Mining licence granted over the project providing the foundation for becoming the first lithium concentrate producer in West Africa.
β Fully funded to production of lithium by first quarter 2025 from Bougouni with a fast-track low capex phase 1 DMS operation.
β Massive exploration potential with target established to increase mineral resource by 50%.
β Phase 2 flotation operation to increase production by a factor of three by 2026/7, funded from cash flow and additional capital injection from project partner Hainan Mining.
β Kodal holds a positive outlook on EV demand and energy storage systems is set to continue and out perform.
What are the top 3 key investor takeaways?
Fully permitted, fully funded and progressing towards lithium production in Mali