RE: RNS4 Sep 2019 15:34
Colin Bird, Executive Chairman said: "Our partners, MMP, have approached the Manica Hard Rock Project in very positive and professional manner. Their investigations and planning have led them to a point where they have identified critical items which have the longer lead delivery times. To this end they have letters of intent agreed and deposits paid thereby ensuring no delays are expected to the contractual planned start date.
We are very encouraged by MMP's commitment and look forward to primary mining and processing commencing with a well designed and built plant together with an optimal mine plan. We share a common belief in the further exploration potential of the concession and the district and will be developing a plan to pursue mutually agreed targets once all of the operational decisions have been made and execution is in progress."