RE: Iran war23 Apr 2026 19:28
Sumo,
At the Molefe Copper Mine, the following applies:
• Pits 2 and 3 are being merged into a single, larger open-pit operation. This follows Phase 1 drilling and trenching results that confirmed the continuity of shallow, high-grade copper oxide mineralisation. The integration includes ~4 months of development work (stripping ~400,000 tonnes of overburden) to improve efficiency, lower the stripping ratio (target ~6:1), and ramp up copper reef mining from ~15,000 t/quarter to ~60,000 t/quarter at an average grade of ~1.4% total copper.l at surface.
• Pit 5 is the main active mining area (the only fully developed pit so far). It has been the primary source of ore (mining rate around 80,000 tpm total material, with high-grade ROM delivered to the Sable refinery). The other pits started as satellite/test pits, and expansion focuses on connecting them for better scale.