Given the shallow water depths and nearby infrastructure, the partners in the DEWA PSC are targeting a low-cost development plan utilising existing technology, which could support a potential production plateau of up to 100 mmscfd (17 kboped). DEWA has a low-cost initial work commitment of approximately US$0.6 million net to Seascape, to conduct a detailed resource estimate and deliver a Field Development and Abandonment Plan ("FDP") within two years, currently targeting first gas in 2027.
The farm-out of Block 2A marks an important milestone in the transformation of Seascape into a fully funded, Southeast Asian focused E&P business with a combination of firm value in discovered resources on the DEWA PSC and significant upside associated with its retained interest in the world-class Kertang prospect.