RE: Okay guys...10 Sep 2018 10:14
From 18th January 2018 update they have mine costs at $6.2 per ton and give these notes to go along with that figure.
On mine costs include all mining and processing costs excluding depreciation. This does not include head office or other administrative or financing costs. Exchange rate used is USD1=ZAR13.7 equal to the average for the 3 months ended 30 November 2017.
The cost per tonne of production will vary depending on, inter alia, volumes produced and waste levels (the strip ratio), which are expected to increase over the next 12 months, offset by increases in volumes. In addition, the cost per tonne expressed in USD will vary according to the prevailing exchange rate, which is currently approximately USD1 = ZAR 12.3.Â