RE: News flow14 Nov 2022 19:41
Regarding Vele Colliery commissioning, there was this about it in the AR:
"On 24 September 2020, 1,602,393 Performance Rights were issued to senior management as a special incentive. These were granted to certain employees of the Company in the form of MC Mining Limited shares. The Incentive Shares will vest in full on the hot commissioning of the Vele Colliery plant. If the hot commissioning does not take place before 31 December 2022, the Incentive Shares will lapse. As at 31 March 2022, the commissioning of the Vele plant did not occur. A directors resolution was passed on 22 March 2022 to extend the expiry date of the special incentive to 31 December 2022."
No guarantee it will happen by end of December but given the slew of vacancies advertised in recent months, the chamge of plans re. Makhado CPP and the need for cash flow seems like Vele going online would be an important part of the plan to get Makhado into production.