RE: Big Rock Energy Storage Optimization1 Mar 2025 07:19
Spot on Simonm.
This what hot commissioning is.
Every component, procedure, control tested under power and documented.
Any bugs rectified and re-test.
They have allowed 3 month, March to June. (presumably from past experience).
May take a bit more or a bit less depending on many factors.
Lastly but importantly, operator training!
jr