RE: Galactica-Pegasus project29 Aug 2024 07:24
Just for you Corkscrew
US$1.5 million in respect of past costs incurred by Blue Star on the Galactica Project;
· 100% of the costs in respect of six wells capped at US$450,000 per well;
· up to US$2.55 million in in respect of the Company's 50% participating interest share of the tie-back, installation andprocessing expenditures required for the development of the Galactica Project;
· the balance of US$1.18 million in respect of associated fees, legal costs and working capital and development contingencies.
The initial wells are expected to be on stream and producing in H1 2025 and an independent third-party competent person's report indicates that an average of approximately US$2 million per annum