Drill 2 progress3 Jul 2025 16:20
As of 19 June 2025, drill hole KWDD002 at Tertiary Minerals' Konkola West project had reached a depth of 1,343.7 metres.
Drilling started on 26 March 2025. By 19 June, 85 dayshad elapsed. thats 15.8 metres per day. At that rate, without encountering issues, you're looking at
1565m. Target depth 2000m, so you're looking at late July 2025 for target depth. thing is we got prelims on drill 1 in - from memory - upper roan, which is where we had reached in the last update.
And, let's all remember the following key pieces of information. This is not a blind drill. We KNOW there is a commercial deposit in the neighbouring area. We KNOW the geology extends (and dips) into our area. In Drill 1 we drilled through all the expected strat groups, but due to fold and depth couldn't reach ore shale where we/Kobold's AI expects to find the same copper-bearing rock. We are now drilling at a point closer to the neighbouring area. We have once again gone through all the expected strat groups and reached the upper roan. 100m of Kitwe, 100m of Mindola clastics and we are into the Ore Shale. Without knowing any results or having any insider information, the Directors have just bought in knowing all the above. I think they've timed it perfectly. Kobold are in touch with TYM Board periodically and board/Kobold are bound to release market-moving news immediately we're about to see the cards laid out on the table. SEISNAV, correct me if I'm wrong on any of the above please. thanks.