RE: I Am Always Amused How 'Centamin' Shareholders22 May 2023 21:25
Cowichan
When I have provided an on site contract the costs of things like accommodation, food, fuel, lube and any other expenses such as workshops, parts storage etc are all agreed at the time of tendering and or final negotiation.
At the end of each given period contractors are billed for such costs, believe me there's no such thing as a free lunch, although not sure why it worries you so much because added costs inflicted on the contractor encourage higher costs plus a margin to the customer.
The question as to why Centamin didn't do the waste removal inhouse was asked at the last retail shareholder presentation and phone in and the simple answer was the write down over 4 years was too expensive.
Explosives will have to be imported by the license holder and I would suggest that would be Centamin but the experts will likely be whoever is awarded the Drill and blast contract and in this instance it will be Capital. So not sure I understand the question, why charge for the explosives when the contractor is carrying out contract on your behalf only to be charged back with a margin?
The underground contract or inhouse decision would have been different because the underground contract was at an end so renew or go it alone? Length or life of mine says there are long term savings, if there was only 4 years to run doubt that owner mining would have been considered.
I have never said that Capital aren't making a profit of course they are making a profit BUT at $2 per tonne there is no way they can possibly be making what you claim is over $100 million on approximately $240 million contract.
The advantage Capital had over all other contractors is that they actually have the majority of the infrastructure and management/supervisors already in place given the length of time that they have been on site.
For the well known mining contractors to start afresh in what would to each of them be a new market puts them all at a disadvantage from the standpoint of set up costs and timelines. Also wouldn't surprise me if the larger contractors declined to bid given the short duration of the contract.
Do I personally need to see the detailed costs to justify $2 per tonne well no I don't because I know this isn't a rip off number and it will need to be worked at to make a good return.