What we can expect and when...6 Nov 2020 09:38
From the last RNS, it took the guys 31 working days to complete 23 RC holes, equiv to 1.35 days per hole... A Barns they have already drilled 2 holes and therefore had 16 remaining at the RNS date, so I guess we can guess that these will be completed in 22 days, so by 20th November... CM said that he expect first samples to be received in 2 weeks so I presume we use 2-3 weeks as turnaround time as opposed to 3-5 weeks... so between 4-11th December...
Baggy Green/Baggy Green North/Clarke - Results expected by end of next week (by the 13th November)
Barns - Results expected by the end of 11th December
We also have the warrants accelerator by end of the month (30th November), use them or lose them etc...
And we are waiting for the final confirmation of 50% of asset, lovely jubbly… Anyway good luck guys and girls, would be surprised to see us lower than 6p by end of year, my initial target in 6-8p...