RE: MATD27 Jun 2024 17:56
Update May 29
If possible, it is hoped to have the crew at site before Mongolia's parliamentary elections on 28th June, although campaigning tends to have a disruptive influence on logistics in the country. If not possible before, mobilisation shortly after the election will be targeted.
Petro Matad will prioritise getting the Heron 1 well ready to produce as soon as possible since we are aware that DQE expects to be busy with PetroChina and "other operators" from early Q3 2024.
Update June 25
Preparations are being finalised for completion of the Heron 1 well and the contractor, DQE, has indicated that it should be ready to mobilise in July.
May 29, DQE sound fully booked, June 25th contradicts ....
Already pulled one with the funding