RE: cornishknocker15 Dec 2020 21:20
Its hard to say, without knowing exactly what stage they are at present. My calculations were based on already achieved production rates as opposed to forecast improvements, with annual sales of approx 9000t of copper in concentrate and 9000oz of gold. The main key to improvement at the moment is improving the head grade, which will be achieved by developing Higher grade ore blocks - and it looks like this has been achieved, so there should be no wait for that. In time as the Footwall vein system opens up, the primary crushing and grinding circuits are going to need uprating (as that us where the production bottleneck is at present) - if there is suitable used plant available, the upgrade could be achieved in 6 months, if new equipment is required you are probably looking at closer to 18 months. I see on their website they are looking to appoint a projects director (if it wasn't for family I would probably apply), so it looks like there is a lot of project work planned.