Sierra Rutile Provides Q3 2012 Operational Update
London, UK, 8 October 2012: Sierra Rutile Limited (AIM: SRX) ("SRL" or "the Company") is pleased to provide an operational update on developments during the third quarter of 2012 ("Q3" or "the Period").
Highlights:
· Record quarterly production of both rutile and ilmenite:
- Rutile production of 26,381 tonnes, 4% greater than highest previous quarter in Q4 2006
- Ilmenite production of 5,315 tonnes
·Year-to-date production of 68,991 tonnes of rutile and 15,630 tonnes of ilmenite, 52% and 49% respective increase on Q3YTD 2011 (45,346 tonnes and 10,470 tonnes respectively)
· Full-year 2012 rutile production guidance increased to 85,000 to 90,000 tonnes of rutile
· Dry mining construction nearing completion. Plant commissioning expected to commence in November
· Extremely positive new dredge feasibility study completed, yielding
o US$472 million project pre-tax NPV10
o 68% pre-tax IRR
o 12-month project payback
o 27-year modelled project life, with significant scope for further extensions to the project life
Production
Q3 2012 production of 26,381 tonnes of rutile was a Company record for a quarter, 4% higher than the highest previous quarter in Q4 2006. Rutile production was also significantly above budget and 45% above the 18,197 tonnes produced in Q3 2011. Q3 ilmenite production was above budget and 23% above the 4,306 tonnes produced in Q3 2011.
SRL's production rates have been steadily increasing for some time due to the renewed investment in existing production assets. Q3 has seen a step change in production rates due to this cumulative investment, as well as the planned one-week shutdown completed in Q2 2012, where critical components on the existing dredge (D1) were overhauled or replaced.
Year-to-date production is now 68,991 tonnes of rutile and 15,630 tonnes of ilmenite, respectively 52% and 49% greater than at the end of Q3 2011. Production guidance for the full year has now been increased to 85,000 to 90,000 tonnes of rutile and corresponding ilmenite.
Expansion projects
The construction of the dry mining plant is expected to be completed during October, with plant commissioning from ore previously stockpiled at the new plant commencing in November. Commissioning is scheduled to continue during the remainder of Q4, and SRL remains confident that production will commence during 2012, thus ensuring that the project will be delivered ahead of schedule and on budget.
A significant proportion of the earth moving fleet has now arrived on site and is ready for use in production and mine preparation after the completion of plant commissioning.