RE: RNS: Kouroussa Mine All Systems go!2 May 2023 16:43
Oh nice update too!
Kouroussa Gold Mine processing plant has reached the practical completion stage, and has entered the commissioning phase towards achieving first gold pour this quarter, Q2 2023.
· Practical completion on priority systems at the Kouroussa processing plant has now been achieved, allowing the commissioning phase to begin.
· Pre-operational and cold commissioning is currently underway and, once completed, will move to the hot commissioning phase, followed by the first gold pour this quarter, Q2 2023.
· Sufficient ore feed tonnes are on the ROM pad for commissioning, with mining activities accelerating to provide increased ore feed tonnes on the ROM pad for first gold pour followed by name plate production.
Dan Betts, CEO of Hummingbird, commented:
"Kouroussa is on track to pour first gold within the current quarter, and the start of commissioning of the processing plant is a significant step forward in achieving this objective. As we begin the commissioning phase to bring Kouroussa online, we remain heavily focussed on safety at this busy time. Additionally, operational readiness and the transition to daily operations is a key part of this phase as we look not just to first gold, but to ramping up production to name plate capacity, moving the Company to being a +200,000-ounce, multi-asset, multi-jurisdiction gold producer."