'The further preparatory work aims to ensure the borehole is in optimum condition for testing, and to give the best possible communication between the well and the fracture system in the formation. Once this has been completed then, subject to agreement of partners, well testing can commence to ascertain whether commercial hydrocarbon flows can be achieved from the BRX4Z well as envisaged per our timetable of 3 April.'
Stage 1
Rig Acceptance and Mobilisation -3 Days
Isolation of water, reperforation and recompletion - 19 Days
Rig Demobilisation - 6 Days
Stage 2
Discussions etc
Stage 2 (now stage 3)
Lead Time for Arrival of Well Test Kit - 14 Days ? Has this happened ie order it
Installation, Testing & Commission of Equipment - 10 Days (completed by end of june ????)
Flow Test & Production Results - 1 month (completed by end of july) ?????
Stage 1 Rig Acceptance and Mobilisation -3 DaysIsolation of water, reperforation and recompletion - 19 DaysRig Demobilisation - 6 DaysStage 2 Discussions etcStage 2 (now stage 3) Lead Time for Arrival of Well Test Kit - 14 Days ? Has this happened ie order it Installation, Testing & Commission of Equipment - 10 Days (completed by end of june ????)Flow Test & Production Results - 1 month (completed by end of july) ?????
they will then no doubt have another load and another and another to continue the process and add even more total shares indefinetly
If I had know they had this amount so far sold off and who knows how many left . Iwould not have not bothered buying in the 1st place
Why are not told the entire figure of warrants and shares they have etc