RE: Value of Mokopane24 Aug 2018 11:47
SOTRR - we should remember that the large majority of the plant cost at Mokopane would have been down the salt roast plant - thus we need to consider the possibility that only crushing and concentration is undertaken at Mokopane and that the salt roast process is undertaken by (a perhaps slightly enlarged) process at Vametco.
This would take a big chunk out of the plant and setup costs as envisaged by the 2016 Mokopane PFS, which of course was undertaken before Vametco was purchased. The 9,525 tonnes of V2O5 envisaged in that PFS of course contains 5,334 Tonnes of Vanadium.
To see if this is practical we simply need to establish if we could transport something like 250-300,000 tonnes of 2% Vanadium concentrate from Mokopane to Vametco, some 150 miles to the south west. Ore have in the past transported almost 100,000 tonnes in one trip. We might need something 1/10th the size of this to permit deliveries every 2 weeks.