Why do people repeat the same points when they have already been dealt with numerous times.
1. There is material stockpiled at the site that will take a while to process
2. These concentrators only process 1.5 tph/6 tph depending on the clay content.
3. Lets suppose 10 concentrators at 3 tph for 10 hours a day. That is 300 tpd. 300 tpd at 2 g/t is 600 g
which is 21.16 oz per day.
4. Lets suppose there is only enough material stockpiled for 5 days. That 1 500 t and 105.8 oz of gold. At
$2,300 that is $243k,
5. If they have to stop for a couple of days am I bovvered?
6. For the stockpiled material, wd don't need excavators and heavy trucks. We need one or two of those
small front loader dump trucks.
7. Lets suppose the above is true. A it proves the gold is there B. it proves the grade C. it proves that Fasc
can process successfully and the kit works D. it proves the gold can be sold locally.
Now you might think that is negative but I don't.
_astly, why do you think we need circa 70 Burkinabes; a big chunk of this will be manual labour.
This cannot be a heavily mechanised operation until we have the production licence permitting fully
mechanised production. To get that we need an EIA and EISA and so on. I can't see that we get the
production licence before October/November unless we can do a deal with the Govt. It could be that we
can persuade the Govt that the rules are aimed at hard rock mining and not alluvial mining f that
happens (the Govt wants as much revenue as possible) then we are seriously rocking and rolling.
DYOR