Aureus Mining Hopes To Restart New Liberty Plant Within Two Weeks

Mon, 23rd May 2016 07:05

LONDON (Alliance News) - Aureus Mining Inc Monday said it has still not managed to restart the gold plant at the New Liberty project in Liberia but said good progress has been made which should allow processing operations to recommence "within the next two weeks".

Aureus was forced to suspend plant operations at its New Liberty gold mine earlier this month after problems with a circuit and heavy rainfall caused a "small overflow" from its tailings facility. Operations will not restart until authorities have approved the remediation work and rectified the issue.

"The company is working closely with both the Ministry of Lands, Mines and Energy and the Environmental Protection Agency of Liberia to oversee the restart of processing operations and to ensure that this process is undertaken in accordance with the International Cyanide Management Code," said the miner.

"The company is working towards a recommencement of processing operations at New Liberty within the next two weeks, subject to final approval of the Ministry of Lands, Mines and Energy," the company added.

Aureus said the Environmental Protection Agencyu has given its approval for Aureus to construct holding zones within the wetlands area downstream of the tailings storage facility, which should enable better aeration of surface waters and improved retention times. The leak from the facility mostly impacted the surrounding wetland areas and has so far not caused any injuries of fatalities to any individuals.

The miner said it has engaged technical experts to help with various modifications within the process plant and detoxification circuit to ensure that discharges onto the facility comply with the environmental and operating permits that regulate the project.

"A number of technical studies by international consultants are underway, to review the company's environmental and social action plans and ensure compliance with International Finance Corporation's performance standards and the Equator Principles," said Aureus.

International Finance Corp is the company's lender and the World Bank's private sector lender whilst the Equator Principles are a risk-management framework adopted by financial institutions for determining, assessing and managing environmental and social risk in projects.

Aureus said it is holding discussions with its lenders and suppliers and reiterated that mining activities are ongoing, with ore being stockpiled rather than treated. Aureus said it has stockpiled 73,431 tonnes of ore graded at 3.78 grammes of gold per tonne.

Total gold production since the start of 2016 stands at 30,000 ounces of gold, which can be compared to the 22,706 ounces that were produced during the first three months of the year.

Aureus shares were up 10% to 3.71 pence per share on Monday morning.

By Joshua Warner; joshuawarner@alliancenews.com; @JoshAlliance

Copyright 2016 Alliance News Limited. All Rights Reserved.

More News
7 Sep 2015 08:26

Aureus Mining Says Gold Sales And Processing Start At New Liberty

Read more
20 Aug 2015 07:48

Aureus Mining Pours First Gold From New Liberty At Ceremonial Opening

Read more
11 Aug 2015 14:53

Aureus Mining rises despite posting wider first-half loss

(ShareCast News) - Canadian based Aureus Mining widened its first half loss in the six months to June 30, down to $5.15m from $2.08m. However shares in the AIM listed company were up by 1.84% to 20.75p at 1451 BST. In the past quarter Aureus Mining took a $1.036m loss on warrant derivative liabilit

Read more
11 Aug 2015 08:08

Aureus Mining Reports Widened Loss For First Half Of 2015

Read more
6 Aug 2015 05:18

AGM, EGM Calendar - Week Ahead

Read more
5 Aug 2015 15:06

AGM, EGM Calendar - Week Ahead

Read more
5 Aug 2015 05:13

AGM, EGM Calendar - Week Ahead

Read more
4 Aug 2015 15:16

AGM, EGM Calendar - Week Ahead

Read more
4 Aug 2015 05:18

AGM, EGM Calendar - Week Ahead

Read more
3 Aug 2015 15:24

AGM, EGM Calendar - Week Ahead

Read more
3 Aug 2015 05:19

AGM, EGM Calendar - Week Ahead

Read more
31 Jul 2015 15:24

AGM, EGM Calendar - Week Ahead

Read more
31 Jul 2015 05:18

AGM, EGM Calendar - Week Ahead

Read more
30 Jul 2015 15:23

AGM, EGM Calendar - Week Ahead

Read more
20 Jul 2015 08:03

Aureus Mining Says New Liberty Process Plant Hits Nameplate Capacity