Watch the latest episode of focusIR Fireside Chats: Why Edinburgh Investment Trust Is Backing Turnaround Stocks for 2026 Growth. View here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksZanaga Iron Ore Company Limited Regulatory News (ZIOC)

Share Price Information for Zanaga Iron Ore Company Limited (ZIOC)

Share Price is delayed by 15 minutes
Get Live Data
4.10    -0.025 (-0.61%)
Bid:
4.05
Ask:
4.10
Spread: 0.05 (1.235%)
Market Cap: £40.64m
ZIOC Live PriceLast checked at - London Stock Exchange

Intraday Zanaga Iron Ore Company Limited Share Chart

Zanaga Project Update

31 Oct 2011 07:00

RNS Number : 1087R
Zanaga Iron Ore Company Ltd
31 October 2011
 



31 October 2011

 

 

 

ZANAGA IRON ORE COMPANY LIMITED

("ZIOC" or the "Company")

Zanaga Project Update

 

 

Zanaga Iron Ore Company Limited (AIM:ZIOC) is pleased to announce the following update on the Zanaga Iron Ore Project (the "Zanaga Project") in the Republic of Congo (Congo Brazzaville)

 

Highlights

·; Value Engineering Exercise ("VEE") completed

o results confirm the economic viability of the Zanaga Project

o post VEE the projected cost of the 45 Mtpa railway option remains in line with IPO estimates

o    an alternative 30Mtpa slurry pipeline transportation option identified with potential to further enhance project economics

·; Xstrata intends to commit to a Pipeline Study shortly to refine the pipeline option and its economics

·; Feasibility Study ("FS") drilling and Environmental and Social Impact Assessment (ESIA) work continues on schedule

o FS expected to conclude in Q1 2014

·; Joint search initiated with Xstrata for a strategic partner for the Zanaga Project

 

Clifford Elphick, Non-Executive Chairman of ZIOC, commented:

"Following the completion of the Value Engineering Exercise, ZIOC is pleased to provide an update on the Zanaga Project. It is extremely pleasing that the PFS and VEE work streams have confirmed the economic viability of the 45 Mtpa railway option. In addition, significant potential incremental value has been identified based on modifying the mode of transport to a slurry pipeline, producing a high grade pellet feed product. Xstrata intends to commit to a Pipeline Study shortly to refine this option and its costing, which will assist in determining which option to take through to final Feasibility Study. ZIOC and Xstrata have in addition begun to investigate strategic partner options"

Value Engineering Exercise

 

The VEE represents an important initial stage of the FS. Following ZIOC's announcement on 8 February 2011 a team of internal and external experts was assembled to conduct the VEE, based on the capital and operating cost reduction opportunities recognised in the draft PFS report. With Xstrata managing the Zanaga Project, the VEE focused on investigating a broad range of development opportunities for the Project to identify the most attractive final development option. During the VEE phase, the project team continued its resource, geotechnical and hydro-geological drilling, metallurgical test work and all other associated port and mine site engineering and ESIA FS work programs.

 

As part of the VEE the pipeline option was revisited to investigate several capex and opex optimisation possibilities as well as the fit with changing global iron ore market dynamics. The outcome of this review confirmed two viable transport options for the development of the Zanaga Project:

 

1) Railway Option:

The original railway option assumes that on average 118 Mtpa of ore will be treated through two processing plants to produce 30 Mtpa of magnetite concentrate and 15 Mtpa of Hematite sinter feed which will be transported to the port at Pointe Noire via a 350 km railway and exported from a new port facility 9 km north of Pointe Noire. Life of Mine (LOM) will be in the region of 30 years, although the resource base and its upside potential will support either increased production or a longer LOM. The design, development plan and costs for the railway option have not changed materially since IPO.

 

45 Mtpa Railway Option - Capital Cost Estimate (US$m)

 

Area

IPO(Nov 2010)

Pre VEE

(Feb 2011)

VEE savings

(Mar-Sep 2011)

Post VEE(Oct 2011)

Minesite

2,644

3,170

-406

2,764

Transport Corridor

2,074

2,472

-462

2,010

Port

896

681

-108

573

Power

214

500

50

550

Total Direct

5,828

6,822

-926

5,896

Indirect costs1

634

915

0

915

Contingency2

986

734

0

734

TOTAL

7,448

8,471

-926

7,545

 

Notes: The Post VEE figures above include potential savings identified by the Xstrata managed VEE and have not been the subject of a formal capital re-estimate. . Figures exclude FS costs (funded by Xstrata) of an estimated US$249m and are in 2011 US$.

1Indirect costs include Head Office costs, EPCM & other indirect costs

2 Contingency provision of US$734m (10% of total direct plus indirect costs) for the 45 Mtpa railway option was the result of a thorough quantitative risk analysis (QRA) performed by the project team on the pre VEE case

 

FOB operating cost for the 45 Mtpa rail option as estimated by the PFS workstreams is US$25 per dry metric tonne including a US$2/tonne contingency. In addition, approximately US$3/tonne of potential savings were then identified by the VEE. This represents a significant saving compared with the blended FOB operating cost presented at IPO of US$27/tonne.

2) Pipeline Option:

 

The pipeline option assumes that initially 30 Mtpa of pellet feed will be produced from an average 75 Mtpa of combined hematite/magnetite ore. Treatment of ore will be through a single integrated processing plant. The pellet feed product will be transported via a slurry pipeline to the port site to the north of Pointe Noire. LOM will be in excess of 30 years and significant potential exists to expand production.

 

The Pipeline Option has the potential to enhance the Zanaga Project's value by significantly reducing both capital expenditure and operating costs.

 

30 Mtpa Pipeline Option - Capital Cost Estimate (US$m)

 

Area

30 Mtpa Pipeline Option

Mine

1,203

Beneficiation plant

1,071

Transport Corridor

1,096

Port

484

Power

564

Total Direct

4,418

Head Office

273

Indirects

441

On-costs (EPCM)

502

Contingency

1,627

Total per Xstrata managed VEE

7,260

FS costs (funded by Xstrata)

(249)

ZIOC identified savings:

Indirects1

(322)

Contingency2

(629)

TOTAL- ZIOC guidance

6,060

Notes: ZIOC's technical team has identified potential savings to certain indirect costs and contingency provisions outlined below. Figures shown in 2011 US$.

1Comprises additional indirect costs included by Xstrata in the pipeline option but not included in the railway option

2Comprises additional contingency included by Xstrata consisting primarily of engineering rework and full costs associated with an assumed one year project delay

 

FOB operating cost for the 30 Mtpa slurry pipeline as estimated by the VEE is US$21 per dry metric tonne including a US$5/tonne contingency.

 

Pipeline Study

 

Xstrata intends to commit to a Pipeline Study shortly to refine this option and its costing, which will assist in determining which option to take through to final Feasibility Study.

 

Strategic Partner Process

 

Xstrata and ZIOC wish to explore whether there is a suitable strategic partner who can further enhance the long-term value of the Zanaga Project, including off-take on commercial terms, access to construction financing and construction expertise. Accordingly Xstrata and ZIOC have embarked on a joint process, which is at an early stage, to identify a party to become a strategic partner in the development of this world class project. Xstrata intends to fully retain its interest in the Zanaga Project. There can be no certainty that this process will result in any transaction being completed.

 

 

For further information please contact:

Zanaga UK Services Limited

Corporate Development and Andrew TraharInvestor Relations Manager +44 20 7399 1105

 

Liberum Capital Limited

Nominated Adviser, Financial Chris Bowman, Christopher BrittonAdviser and Joint Corporate Broker and Christopher Kololian

+44 20 3100 2000

 

Citigroup Global Markets Limited

Joint Corporate Broker Alex Carter

+44 20 7986 4000

 

Pelham Bell Pottinger

Financial PR James MacFarlane and Philippe Polman

+44 20 7861 3232

About us:

Zanaga Iron Ore Company Limited (AIM:ZIOC) is a BVI registered Company and the owner of 50% less one share interest in the Zanaga Iron Ore Project based in the Republic of Congo (Congo Brazzaville) through its joint venture partnership with Xstrata. The Zanaga Project is focused on the management, development and construction of a world-class iron ore mine and related, processing, transportationand port infrastructure

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDXBDGGDXBGBG
Date   Source Headline
21st May 20263:21 pmRNSAdmission to Trading and Total Voting Rights
15th May 20267:00 amRNSResult of Placing, Subscription and Retail Offer
14th May 20264:44 pmRNSRetail Offer
14th May 20264:41 pmRNSLaunch of Placing, Subscription and Retail Offer
6th May 20267:00 amRNSCompletion of DRI Process Plant Costing
13th Mar 202610:27 amRNS-RRecording of Strategic Investment Presentation
13th Mar 202610:27 amRNS-RRecording of Strategic Investment Presentation
9th Mar 20267:00 amRNS-RInvestor Presentation and Q&A
20th Feb 20269:58 amRNS-RRecording of Investor Presentation
19th Feb 20267:00 amRNSTR-1: Notification of major holdings
10th Feb 20267:00 amRNSProposed Strategic Investment in Zanaga Project
9th Feb 202612:30 pmRNSSignificant shareholding clarification and update
12th Jan 20267:00 amRNSInvestor Event and Planned Corporate Update
6th Jan 20267:00 amRNSCompletion of Project Workstreams
30th Dec 20257:00 amRNSCorporate and Project Workstreams Update
30th Dec 20257:00 amRNSCorporate and Project Workstreams Update
19th Dec 202512:15 pmRNSResults of AGM
19th Dec 202512:15 pmRNSResults of AGM
9th Dec 20257:00 amRNSAppointment of Joint Broker
3rd Dec 20257:00 amRNS-RNew Website, Branding & Corporate Presentation
25th Nov 20255:42 pmRNSPosting of Notice of AGM
17th Nov 202510:06 amRNSTR-1: Notification of major holdings
1st Oct 20257:00 amRNSINTERIM RESULTS FOR SIX MONTHS ENDED 30 JUNE 2025
29th Sep 20257:00 amRNSExecution of Share Lock-in Agreements
5th Sep 20255:00 pmRNSNotification of Transactions of PDMR
11th Aug 20257:00 amRNSUpdate on Improved Project Economics
1st Jul 20257:00 amRNSAudited Results for the Year to 31 December 2024
25th Jun 20257:00 amRNSPositive Test Results Confirm DRI Product Quality
23rd May 20256:29 pmRNSOption Exercise and Issue of Shares
9th Apr 20257:00 amRNSBoard Appointments
26th Mar 20257:00 amRNSTranche 2 Private Placement Completion & Upsizing
18th Mar 20254:45 pmRNSProject Development Strategy Update
13th Mar 20259:25 amRNSBuyback of Glencore Shares and Board Change
3rd Mar 20257:00 amRNSUS$21.5m Private Placement & Proposed Buyback
7th Feb 20258:41 amRNSInvestor Event
3rd Feb 20257:00 amRNSPower Solutions MoU
2nd Jan 20252:55 pmRNSCorporate Update and Investor Event
11th Dec 20247:00 amRNSPort development MOU signed with Arise
5th Dec 202410:16 amRNSResult of AGM
15th Nov 202411:33 amRNSAnnual Report and Notice of AGM
30th Sep 20244:51 pmRNSInterim Results
29th Aug 20247:00 amRNSOptions issue and exercise
22nd Jul 20247:00 amRNSNominated Adviser and Broker
18th Jul 20247:00 amRNSRepayment of Glencore loan
9th Jul 20242:58 pmRNSNotification of Major Holdings
1st Jul 20248:00 amRNSCompletion of Subscription and Shard Facility
1st Jul 20247:31 amRNSAnnouncement re Shard waiver and GC purchase
1st Jul 20247:00 amRNSZIOC 2023 Annual Results announcement
1st Jul 20247:00 amRNS2024 Shard Facility execution announcement
28th Jun 20245:54 pmRNSShard Facility Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.