The next focusIR Investor Webinar takes places on 14th May with guest speakers from WS Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksZanaga Iron Regulatory News (ZIOC)

Share Price Information for Zanaga Iron (ZIOC)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 7.20
Bid: 7.10
Ask: 7.30
Change: -0.14 (-1.91%)
Spread: 0.20 (2.817%)
Open: 7.20
High: 7.20
Low: 7.20
Prev. Close: 7.34
ZIOC Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Zanaga Project Update

31 Oct 2011 07:00

RNS Number : 1087R
Zanaga Iron Ore Company Ltd
31 October 2011
 



31 October 2011

 

 

 

ZANAGA IRON ORE COMPANY LIMITED

("ZIOC" or the "Company")

Zanaga Project Update

 

 

Zanaga Iron Ore Company Limited (AIM:ZIOC) is pleased to announce the following update on the Zanaga Iron Ore Project (the "Zanaga Project") in the Republic of Congo (Congo Brazzaville)

 

Highlights

·; Value Engineering Exercise ("VEE") completed

o results confirm the economic viability of the Zanaga Project

o post VEE the projected cost of the 45 Mtpa railway option remains in line with IPO estimates

o    an alternative 30Mtpa slurry pipeline transportation option identified with potential to further enhance project economics

·; Xstrata intends to commit to a Pipeline Study shortly to refine the pipeline option and its economics

·; Feasibility Study ("FS") drilling and Environmental and Social Impact Assessment (ESIA) work continues on schedule

o FS expected to conclude in Q1 2014

·; Joint search initiated with Xstrata for a strategic partner for the Zanaga Project

 

Clifford Elphick, Non-Executive Chairman of ZIOC, commented:

"Following the completion of the Value Engineering Exercise, ZIOC is pleased to provide an update on the Zanaga Project. It is extremely pleasing that the PFS and VEE work streams have confirmed the economic viability of the 45 Mtpa railway option. In addition, significant potential incremental value has been identified based on modifying the mode of transport to a slurry pipeline, producing a high grade pellet feed product. Xstrata intends to commit to a Pipeline Study shortly to refine this option and its costing, which will assist in determining which option to take through to final Feasibility Study. ZIOC and Xstrata have in addition begun to investigate strategic partner options"

Value Engineering Exercise

 

The VEE represents an important initial stage of the FS. Following ZIOC's announcement on 8 February 2011 a team of internal and external experts was assembled to conduct the VEE, based on the capital and operating cost reduction opportunities recognised in the draft PFS report. With Xstrata managing the Zanaga Project, the VEE focused on investigating a broad range of development opportunities for the Project to identify the most attractive final development option. During the VEE phase, the project team continued its resource, geotechnical and hydro-geological drilling, metallurgical test work and all other associated port and mine site engineering and ESIA FS work programs.

 

As part of the VEE the pipeline option was revisited to investigate several capex and opex optimisation possibilities as well as the fit with changing global iron ore market dynamics. The outcome of this review confirmed two viable transport options for the development of the Zanaga Project:

 

1) Railway Option:

The original railway option assumes that on average 118 Mtpa of ore will be treated through two processing plants to produce 30 Mtpa of magnetite concentrate and 15 Mtpa of Hematite sinter feed which will be transported to the port at Pointe Noire via a 350 km railway and exported from a new port facility 9 km north of Pointe Noire. Life of Mine (LOM) will be in the region of 30 years, although the resource base and its upside potential will support either increased production or a longer LOM. The design, development plan and costs for the railway option have not changed materially since IPO.

 

45 Mtpa Railway Option - Capital Cost Estimate (US$m)

 

Area

IPO(Nov 2010)

Pre VEE

(Feb 2011)

VEE savings

(Mar-Sep 2011)

Post VEE(Oct 2011)

Minesite

2,644

3,170

-406

2,764

Transport Corridor

2,074

2,472

-462

2,010

Port

896

681

-108

573

Power

214

500

50

550

Total Direct

5,828

6,822

-926

5,896

Indirect costs1

634

915

0

915

Contingency2

986

734

0

734

TOTAL

7,448

8,471

-926

7,545

 

Notes: The Post VEE figures above include potential savings identified by the Xstrata managed VEE and have not been the subject of a formal capital re-estimate. . Figures exclude FS costs (funded by Xstrata) of an estimated US$249m and are in 2011 US$.

1Indirect costs include Head Office costs, EPCM & other indirect costs

2 Contingency provision of US$734m (10% of total direct plus indirect costs) for the 45 Mtpa railway option was the result of a thorough quantitative risk analysis (QRA) performed by the project team on the pre VEE case

 

FOB operating cost for the 45 Mtpa rail option as estimated by the PFS workstreams is US$25 per dry metric tonne including a US$2/tonne contingency. In addition, approximately US$3/tonne of potential savings were then identified by the VEE. This represents a significant saving compared with the blended FOB operating cost presented at IPO of US$27/tonne.

2) Pipeline Option:

 

The pipeline option assumes that initially 30 Mtpa of pellet feed will be produced from an average 75 Mtpa of combined hematite/magnetite ore. Treatment of ore will be through a single integrated processing plant. The pellet feed product will be transported via a slurry pipeline to the port site to the north of Pointe Noire. LOM will be in excess of 30 years and significant potential exists to expand production.

 

The Pipeline Option has the potential to enhance the Zanaga Project's value by significantly reducing both capital expenditure and operating costs.

 

30 Mtpa Pipeline Option - Capital Cost Estimate (US$m)

 

Area

30 Mtpa Pipeline Option

Mine

1,203

Beneficiation plant

1,071

Transport Corridor

1,096

Port

484

Power

564

Total Direct

4,418

Head Office

273

Indirects

441

On-costs (EPCM)

502

Contingency

1,627

Total per Xstrata managed VEE

7,260

FS costs (funded by Xstrata)

(249)

ZIOC identified savings:

Indirects1

(322)

Contingency2

(629)

TOTAL- ZIOC guidance

6,060

Notes: ZIOC's technical team has identified potential savings to certain indirect costs and contingency provisions outlined below. Figures shown in 2011 US$.

1Comprises additional indirect costs included by Xstrata in the pipeline option but not included in the railway option

2Comprises additional contingency included by Xstrata consisting primarily of engineering rework and full costs associated with an assumed one year project delay

 

FOB operating cost for the 30 Mtpa slurry pipeline as estimated by the VEE is US$21 per dry metric tonne including a US$5/tonne contingency.

 

Pipeline Study

 

Xstrata intends to commit to a Pipeline Study shortly to refine this option and its costing, which will assist in determining which option to take through to final Feasibility Study.

 

Strategic Partner Process

 

Xstrata and ZIOC wish to explore whether there is a suitable strategic partner who can further enhance the long-term value of the Zanaga Project, including off-take on commercial terms, access to construction financing and construction expertise. Accordingly Xstrata and ZIOC have embarked on a joint process, which is at an early stage, to identify a party to become a strategic partner in the development of this world class project. Xstrata intends to fully retain its interest in the Zanaga Project. There can be no certainty that this process will result in any transaction being completed.

 

 

For further information please contact:

Zanaga UK Services Limited

Corporate Development and Andrew TraharInvestor Relations Manager +44 20 7399 1105

 

Liberum Capital Limited

Nominated Adviser, Financial Chris Bowman, Christopher BrittonAdviser and Joint Corporate Broker and Christopher Kololian

+44 20 3100 2000

 

Citigroup Global Markets Limited

Joint Corporate Broker Alex Carter

+44 20 7986 4000

 

Pelham Bell Pottinger

Financial PR James MacFarlane and Philippe Polman

+44 20 7861 3232

About us:

Zanaga Iron Ore Company Limited (AIM:ZIOC) is a BVI registered Company and the owner of 50% less one share interest in the Zanaga Iron Ore Project based in the Republic of Congo (Congo Brazzaville) through its joint venture partnership with Xstrata. The Zanaga Project is focused on the management, development and construction of a world-class iron ore mine and related, processing, transportationand port infrastructure

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDXBDGGDXBGBG
Date   Source Headline
30th Apr 20247:00 amRNSFeasibility Study Update
28th Mar 20244:06 pmRNSCorporate and Project Update
2nd Jan 20247:00 amRNSGlencore Loan Update
28th Dec 20237:00 amRNSMoU signed with CMEC and FS Process Update
19th Dec 20233:38 pmRNSResults of AGM
14th Dec 20237:00 amRNSCEO Appointment
14th Dec 20237:00 amRNSFunding Update - Subscription Facility
27th Nov 20235:00 pmRNSPosting of Annual Report and Notice of AGM
7th Nov 20237:00 amRNSInvestor Presentation
2nd Oct 20235:33 pmRNSIssue of Equity
29th Sep 20237:00 amRNSInterim Results
3rd Jul 20237:00 amRNSFunding update - subscription facility
3rd Jul 20237:00 amRNSAnnual Results
28th Feb 20234:35 pmRNSPrice Monitoring Extension
30th Jan 20234:40 pmRNSSecond Price Monitoring Extn
30th Jan 20234:35 pmRNSPrice Monitoring Extension
16th Dec 20224:37 pmRNSNotification of Major Holdings
16th Dec 202210:31 amRNSAcquisition, Admission & Board Appointments
13th Dec 202211:45 amRNSResults of General Meeting and Board Appointments
25th Nov 20224:36 pmRNSNotice of GM
25th Nov 20227:00 amRNSResults of AGM
23rd Nov 20227:00 amRNSAcquisition of 100% of Zanaga Iron Ore Project
4th Nov 20225:41 pmRNSNotice of Annual General Meeting
30th Sep 20221:00 pmRNSInterim Results
5th Sep 20224:40 pmRNSSecond Price Monitoring Extn
5th Sep 20224:35 pmRNSPrice Monitoring Extension
1st Jul 20227:00 amRNSAnnual Results
29th Apr 20224:40 pmRNSSecond Price Monitoring Extn
29th Apr 20224:35 pmRNSPrice Monitoring Extension
3rd Mar 20224:40 pmRNSSecond Price Monitoring Extn
3rd Mar 20224:36 pmRNSPrice Monitoring Extension
7th Jan 20224:41 pmRNSSecond Price Monitoring Extn
7th Jan 20224:35 pmRNSPrice Monitoring Extension
20th Dec 20213:13 pmRNSResult of AGM
8th Dec 20214:36 pmRNSPrice Monitoring Extension
25th Nov 20217:00 amRNSPosting of Annual Report and Notice of AGM
21st Oct 20214:40 pmRNSSecond Price Monitoring Extn
21st Oct 20214:36 pmRNSPrice Monitoring Extension
28th Sep 20217:00 amRNSINTERIM RESULTS
27th Sep 20214:41 pmRNSSecond Price Monitoring Extn
27th Sep 20214:35 pmRNSPrice Monitoring Extension
16th Sep 202112:11 pmRNSSecond Price Monitoring Extn
16th Sep 202112:10 pmRNSPrice Monitoring Extension
15th Sep 20214:41 pmRNSSecond Price Monitoring Extn
15th Sep 20214:36 pmRNSPrice Monitoring Extension
11th Aug 20214:40 pmRNSSecond Price Monitoring Extn
11th Aug 20214:35 pmRNSPrice Monitoring Extension
7th Jul 20214:40 pmRNSSecond Price Monitoring Extn
7th Jul 20214:35 pmRNSPrice Monitoring Extension
30th Jun 20217:00 amRNSAnnual Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.