Operations Update & Phase 1A Work Programme

19 Apr 2012 07:00

RNS Number : 6346B
Xcite Energy Limited
19 April 2012
 



 

 

 

NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION IN WHOLE OR IN PART DIRECTLY OR INDIRECTLY IN, INTO OR FROM ANY JURISDICTION WHERE TO DO SO WOULD CONSTITUTE A VIOLATION OF THE RELEVANT LAWS OR REGULATIONS OF SUCH JURISDICTION

 

TSX-V, LSE-AIM: XEL

 

 

 

 

19 April 2012

 

Xcite Energy Limited

("Xcite Energy" or the "Company")

 

Operations Update and Bentley Phase 1A Work Programme

 

 

The Company is pleased to provide an update to the market in respect of the current drilling operations and the Bentley Phase 1A work programme.

 

Current Operations Update

 

As previously announced, the well was spudded on 18 March 2012, with 20 inch casing now having been set down to approximately 2000ft below the rotary table. Preparations are being made to set the blow out preventer and to continue the drilling of the 17.5 inch hole.

 

Summary of Bentley Phase 1A Work Programme

 

Following the successful completion of the 9/03b-6 and 6Z wells (as announced in December 2010), the Company has invested significant resources designing and engineering the next phases in the development of the Bentley field, the Phase 1A and Phase 1B work programmes.

 

The Bentley Phase 1A Work Programme has two principal objectives:

 

1. The 9/03b-7 and 7Z wells are planned to demonstrate the mechanical and operational aspects of the drilling, completion and flowing of the proposed well design for Phase 1B. The 9/03b-7Z well is planned to be used in Phase 1B as the first full production wellbore.

 

2. To collect additional reservoir and production data to improve the calibration of the reservoir model, including data with respect to enhanced oil recovery techniques. This data with be used to further increase the certainty with respect to the longer term oil, gas and water production profiles and recoverable reserves from the Bentley field.

 

The Phase 1A work programme on the Bentley field has been planned to achieve the two principal objectives set out above and comprises the following key operations:

 

v Drilling of a horizontal motherbore well in the geological formation immediately overlying the reservoir. This motherbore is planned to be approximately 2,000ft in length.

v Drilling of the toe extension well (9/03b-7 well), being a horizontal wellbore from the toe of the motherbore, with a reservoir section of up to 2,400ft in length. This well is planned to be positioned approximately at mid-height in the reservoir at an elevation above the oil-water contact such that, when produced at an oil rate of at least 1,500 barrels of oil per day ("bopd"), it should initiate water breakthrough at the well and subsequently develop sufficient water cut (to approximately 50%) within the flow test period. This well will be plugged and abandoned at the end of the production test.

v The 9/03b-7 wellbore is planned to recover a minimum cumulative volume of 45,000 barrels of oil during the flow test period to help ensure that the data gathering will be as effective as possible. This flow test is planned to be up to 90 days in length and to be conducted at a range of different flow rates (specifically not 500 barrels per day for 90 days), again to assist in the data gathering programme. This flow test is expected to commence in the second quarter of 2012 and, for the sake of clarity, it is not a headline flow rate test, it is a data gathering exercise.

v Drilling of a lateral well (9/03b-7Z well) from the side of the motherbore, being a horizontal wellbore with a reservoir section of approximately 2,450ft in length. This well is planned to be positioned as high in the reservoir as possible, being similar in design and completion to the successful 9/03b-6Z well. This wellbore will be drilled after the toe extension well, but not flowed until after the toe extension well has been flowed to achieve sufficient water cut. This lateral wellbore will be cleaned up and then flowed at a rate of at least 1,500 bopd for a minimum period of one day, prior to being suspended as the first full production well on the field in Phase 1B. This flow test is expected to be completed in the fourth quarter of 2012.

 

v Crude oil produced from the 9/03b-7 and 7Z wells will be marketed by BP Oil International Limited, the Company's marketing and offtake partner.

 

v The results and data gathered from the 9/03b-7 well will be used to calibrate the existing reservoir model and update the Reserves Assessment Report. This update is likely to take a number of weeks to finalise after the Phase 1A work programme has been completed.

 

v In parallel to the update of the Reserves Assessment Report, the Field Development Plan for the Bentley field is expected to be updated for re-submission to the Department of Energy & Climate Change as soon as practicable.

 

 

The Company will continue to keep shareholders fully informed during the coming months, which will include the filing of its NI51-101 "Statement of Reserves Data and other Oil and Gas Information" as required in Canada by the end of April 2012.

 

 

 

 

ENQUIRIES:

 

Xcite Energy Limited

 

 

 

+44 (0) 1483 549 063

Richard Smith

Chief Executive Officer

 

Rupert Cole

Chief Financial Officer

 

 

 

 

Oriel Securities (Joint Broker and Nomad)

 

+44 (0) 207 710 7600

Emma Griffin

Partner

 

Michael Shaw

Partner

 

 

 

 

Morgan Stanley (Joint Broker)

 

+44 (0) 207 425 8000

Andrew Foster

Managing Director

 

 

 

 

Pelham Bell Pottinger

 

+44 (0) 207 861 3232

Mark Antelme

Henry Lerwill

 

Director

Account Director

 

 

Paradox Public Relations

 

+1 514 341 0408

Jean-Francois Meilleur

Consultant

 

 

 

 

 

 

Oriel Securities Limited, which is authorised and regulated in the United Kingdom by the Financial Services Authority, is acting exclusively for Xcite Energy and for no one else in connection with the subject matter of this announcement and will not be responsible to anyone other than Xcite Energy for providing the protections afforded to its clients or for providing advice in connection with the subject matter of this announcement.

 

Morgan Stanley, which is authorised and regulated in the United Kingdom by the Financial Services Authority, is acting exclusively for Xcite Energy and for no one else in connection with the subject matter of this announcement and will not be responsible to anyone other than Xcite Energy for providing the protections afforded to its clients or for providing advice in connection with the subject matter of this announcement.

 

 

 

 

Forward-Looking Statements

 

Certain statements contained in this announcement constitute forward-looking information within the meaning of securities laws. Forward-looking information may relate to the Company's future outlook and anticipated events or results and, in some cases, can be identified by terminology such as "may", "will", "should", "expect", "plan", "anticipate", "believe", "intend", "estimate", "predict", "target", "potential", "continue" or other similar expressions concerning matters that are not historical facts. These statements are based on certain factors and assumptions including expected growth, results of operations, performance and business prospects and opportunities. While the Company considers these assumptions to be reasonable based on information currently available to us, they may prove to be incorrect. Forward-looking information is also subject to certain factors, including risks and uncertainties that could cause actual results to differ materially from what we currently expect. These factors include risks associated with the oil and gas industry (including operational risks in exploration and development and uncertainties of estimates oil and gas potential properties), the risk of commodity price and foreign exchange rate fluctuations and the ability of Xcite Energy to secure financing. Additional information identifying risks and uncertainties are contained in the Company's annual information form dated 26 October 2010 and in the annual Management's Discussion and Analysis for Xcite Energy dated 22 March 2012 filed with the Canadian securities regulatory authorities and available at www.sedar.com. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required under applicable securities regulations.

 

 

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) acceptsresponsibility for the adequacy or accuracy of this release.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSFFEFAFESEIL
Date   Source Headline
2nd Jul 20107:00 amRNSRig Contract - Ocean Nomad
17th Jun 20107:00 amRNSTransfer of shareholdings
27th May 20107:00 amRNSResult of AGM
27th May 20107:00 amRNS1st Quarter Results
12th May 20107:00 amRNSExercise of Share Warrants
29th Apr 20109:25 amRNSNotification of Major Interests in Shares
21st Apr 20107:00 amRNSAppointment of Nominated Adviser
29th Mar 201010:29 amRNSAward of Options to Directors and Management Team
26th Mar 20107:00 amRNSHolding(s) in Company
26th Mar 20107:00 amRNSHolding(s) in Company
26th Mar 20107:00 amRNSHolding(s) in Company
25th Mar 20107:00 amRNSAnnual Results
18th Mar 20101:29 pmRNSXcite Energy Closes Placing
10th Mar 20107:00 amRNSPricing of Offering of Ordinary Shares
5th Mar 20107:00 amRNSChallenger Minerals farm-in to Bentley field
10th Feb 20107:00 amRNSLetter of Intent for Deep Water Jack-Up Rig
10th Feb 20107:00 amRNSKey Role for AMEC in Bentley Field Development
8th Feb 20107:00 amRNSPlacing of Ordinary Shares
28th Jan 20107:00 amRNSSupply & Offtake Agreement with BP Oil
3rd Dec 20092:18 pmRNSHoldings in Company
1st Dec 20097:00 amRNSAward of Options to Directors and Management Team
19th Nov 20092:00 pmRNS3rd Quarter Results
28th Oct 20097:00 amRNSChange of Broker
23rd Oct 20094:42 pmRNSHoldings in Company
23rd Oct 20094:41 pmRNSChange of Name of Nominated Adviser
22nd Oct 20097:00 amRNSFugro Well Participation
12th Oct 20098:13 amRNSAppointment of IR adviser in Canada
7th Oct 20092:00 pmRNSXcite Closes Placing
2nd Oct 20097:00 amRNSPlacing
18th Aug 20092:00 pmRNSInterim Results
6th Jul 20092:16 pmRNSOperational Update
22nd Jun 20093:24 pmRNSResults of Interpretation of 3D Seismic Data
29th May 20092:00 pmRNSResult of AGM
7th May 20097:00 amRNSDirector/PDMR Shareholding
29th Apr 20097:00 amRNS2009 Budget and Appointment of Divestment Advisor
24th Apr 20097:00 amRNSAward of Share Options
23rd Apr 20092:00 pmRNSQ1 Financial Results
27th Mar 20092:00 pmRNSFinancial Results
19th Mar 20092:00 pmRNSAppointment of Director
6th Mar 20092:00 pmRNSPricing of Share Options
20th Feb 20092:00 pmRNSCompetent Person's Report
9th Jan 20097:00 amRNSDirector/PDMR Shareholding
3rd Dec 20082:04 pmRNS3rd Quarter Results
4th Nov 20089:29 amRNSDirector Resignation
21st Aug 20082:00 pmRNS2nd Quarter Results
23rd Jun 20082:00 pmRNSAIM Rule 20
19th Jun 20082:00 pmRNSManagement Appointments
28th May 20082:03 pmRNSResult of AGM
22nd May 20082:00 pmRNS1st Quarter Results
21st May 200812:00 pmRNSStatoilHydro Well Data Trade

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.