The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksWeatherly International Plc Regulatory News (WTI)

Share Price Information for Weatherly International Plc (WTI)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 16.1725
Bid: 0.00
Ask: 0.00
Change: 0.00 (0.00%)
Spread: 0.085 (0.527%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 16.1725
WTI Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Quarterly Operations and Production Update

19 Jan 2018 07:00

RNS Number : 2614C
Weatherly International PLC
19 January 2018
 

19 January 2018

 

This Announcement includes release of insider information

 

Weatherly International plc

("Weatherly" or "the Company")

Quarterly Operations and Production Update

 

Weatherly International plc (AIM: WTI) announces its update for the quarter ended 31 December 2017.

 

Summary

 

· Tschudi cathode production improved by 15% quarter on quarter to 4,739 tonnes, which is 11.5% above nameplate over the quarter

· Tschudi C1 costs reduced by 16% to US$4,551 per tonne

 

Tschudi Production Performance

 

Production results for the quarter ended 31 December 2017

 

Quarter ended Mar-17

Quarter ended Jun-17

Quarter ended Sep-17

Quarter ended Dec-17

Total (Ore + Waste) Mined (000 tonnes)

5,117

6,051

6,314

5,869

Ore Tonnes stacked (000 tonnes)

563

726

666

733

Ore Stacked grade (per cent)

0.86

0.99

0.78

0.65

Copper Cathode Produced (tonnes)

3,236

3,386

4,105

4,739

C1 Cost (US$/t)

5,907

6,344

5,402

4,551

 

Tschudi production for the December quarter was 4,739 tonnes of copper cathode, or 11.5% above nameplate. This brings year to date production to 8,843 tonnes or 4% ahead of nameplate half way through the financial year. This outcome was assisted by some short-term benefits from relatively-fast leaching of additional oxide ore mined from an interim pit pushback bringing forward some leaching output. The grade of this additional oxide ore was lower, reducing the tonnage of contained copper metal stacked in the quarter. Some early seasonal rains were received on site but they have had minimal impact upon the operation thus far.

 

Mining and stacking of slower-leaching mixed ore has resumed, and the main wet season is now approaching.  

 

Construction of the heap leach pad extension is complete. Some operational delays are expected during a typical local rainy season, but the expected impacts are reduced due to stacking of ore on new leach pads rather than upon previously leached ore, and because healthy stockpile levels of ore have been placed on the ROM pad near the crusher in anticipation of rain delays impacting mining. Forced aeration of some panels has commenced as part of ongoing testing of how leach rates for mixed and sulphide ore may be improved under modified operating conditions designed to increase bacterial activity in the heap.

 

Open pit groundwater inflows, and the costs of dealing with them, continue to increase as pit mining proceeds to greater depths, but the flow rates are being managed adequately to ensure a reliable supply of ore for stacking.

 

While the strong December quarter demonstrates the capacity of the Tschudi SXEW plant to operate at well above nameplate levels when leaching rates provide sufficient copper into solution, full year production is not expected to exceed nameplate.

 

As a result of the improved production levels, Tschudi C1 unit costs have fallen to US$4,551 per tonne. The Namibia Dollar strengthened notably in December, and this will impact US$ costs going forward if it is sustained.

Loan draw downs and hedges

Weatherly advises it has made no further drawdowns on the US$10 million uncommitted loan from Orion Mine Finance announced on 28 July 2017 to accelerate the building of the leach pads and to fund working capital requirements at Tschudi. The Company has only drawn down US$3m on the loan. To seek to ensure the loan would be sufficient to meet the necessary funding requirements the Company has hedged both copper and currency out to July 2018. In addition to hedges previously announced, Weatherly has 990 tonnes fixed in July at an average copper price of US$7,171 per tonne

As previously advised on 28 April 2017 as a loan rescheduling fee, Orion has the right (but not the obligation) to buy, if available, up to 700 tonnes of unhedged cathode each month from Weatherly until 30 April 2018 at a price of US$6,000 per tonne. Orion can only exercise its option to the extent of unhedged tonnes produced in the month and so far this financial year Orion has not elected to do so.

The Company and its subsidiaries are unlikely to generate sufficient surplus cash to meet all loan repayments when due, particularly in the near term. The Company continues to positively engage with Orion on the subject.

 

For further information please contact:

 

Weatherly International plc +44 (0) 1707 800 774

Craig Thomas, Chief Executive Officer

Kevin Ellis, CFO and Company Secretary

 

RFC Ambrian Limited +44 (0) 20 3440 6800

(Nominated Adviser & Broker)

Nominated adviser contact: Stephen Allen / Bhavesh Patel

Broker contact: Charlie Cryer

 

About Weatherly

 

Weatherly is an AIM listed copper mining company operating in Namibia in southern Africa. Its principal assets are the Tschudi Mine and the Otjihase Project. The Tschudi Mine is an operating open pit mine producing refined copper cathode on site. The key assets of the Otjihase Project are the Otjihase underground copper mine and concentrator and the Matchless West underground copper mine. The Otjihase Project assets are currently under care & maintenance while in the Project Development stage. Weatherly also owns 25% of China Africa Resources Namibia (CARN), a private Namibian company which owns the high-grade Berg Aukas underground zinc-lead-vanadium project. On 12 December 2017, Weatherly announced that it had entered into an agreement to purchase the Kitumba copper development project in Zambia, subject to regulator and vendor shareholder approvals.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBGGDBDDBBGII
Date   Source Headline
7th Aug 20187:00 amRNSResignation of Nominated Adviser
1st Aug 20185:30 pmRNSWeatherly International
31st Jul 20187:00 amRNSAdministrators' Statement of Proposals
3rd Jul 20187:00 amRNSSenior Management Appointment
13th Jun 20187:00 amRNSBerg Aukas Update
4th Jun 20187:00 amRNSWEATHERLY INTERNATIONAL PLC - INVESTMENT UPDATE
1st Jun 20184:00 pmRNSAppointment of Administrators
1st Jun 20187:30 amRNSSuspension - Weatherly International Plc
1st Jun 20187:00 amRNSSuspension & operational & financial update
22nd May 20181:10 pmRNSForm 8.3 - Weatherly International PLC
21st May 20184:55 pmRNSTschudi Operational Update and Kitumba Update
18th May 20187:00 amRNSForm 8.3 - Weatherly International PLC
18th May 20187:00 amRNSForm 8.3 - Weatherly International PLC
16th May 20187:46 amRNSForm 8.3 - Weatherly Intl PLC
16th May 20187:45 amRNSForm 8.3 - Weatherly Intl PLC
11th May 201811:10 amRNSForm 8.3 - Weatherly International
11th May 201811:08 amRNSForm 8.3 - Weatherly International
11th May 20188:49 amRNSForm 8.3 - Weatherly International PLC
10th May 20183:29 pmRNSForm 8.3 - Weatherly International Plc
10th May 201812:46 pmRNSForm 8.3 - Weatherly International plc
10th May 201810:20 amRNSForm 8.3 - Weatherly International
8th May 20181:34 pmRNSForm 8.3 - WEATHERLY INTERNATIONAL
4th May 20187:00 amRNSForm 8.3 - Weatherly International Plc
2nd May 20187:00 amRNSForm 8 (OPD) - Weatherly International plc
30th Apr 20183:18 pmRNSForm 8.3 - Weatherly Intl PLC
27th Apr 201811:49 amRNSForm 8.3 - Weatherly International
26th Apr 20189:05 amRNSSecond Price Monitoring Extn
26th Apr 20189:00 amRNSPrice Monitoring Extension
26th Apr 20187:00 amRNSStrategic Review and Formal Sale Process
26th Apr 20187:00 amRNSQuarterly Operations and Production Update
26th Apr 20187:00 amRNSUpdate on Berg Aukas and Kitumba Acquisitions
24th Apr 20182:05 pmRNSSecond Price Monitoring Extn
24th Apr 20182:00 pmRNSPrice Monitoring Extension
24th Apr 201812:15 pmRNSKitumba Purchase Update
5th Apr 20187:00 amRNSDirectorate Change
4th Apr 20185:45 pmRNSKitumba Purchase Update & Long-Term Restructuring
3rd Apr 20182:05 pmRNSSecond Price Monitoring Extn
3rd Apr 20182:00 pmRNSPrice Monitoring Extension
3rd Apr 20187:00 amRNSRescheduling of repayment
19th Mar 20189:00 amRNSPrice Monitoring Extension
19th Mar 20187:00 amRNSInterim Results
7th Mar 20187:00 amRNSChange of Adviser
6th Feb 20181:51 pmRNSBoard change
5th Feb 20188:53 amRNSAgreement to purchase additional 65% of Berg Aukas
2nd Feb 20187:00 amRNSKitumba Purchase Update and Development Plan
19th Jan 20187:00 amRNSQuarterly Operations and Production Update
9th Jan 20187:00 amRNSAGM Update
27th Dec 20177:00 amRNSLoan repayment update
15th Dec 20171:03 pmRNSNotice of AGM
12th Dec 20177:00 amRNSWeatherly to acquire Zambian copper project

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.