La Parrilla Tungsten & Tin Mine Update

7 Aug 2019 07:00

RNS Number : 1626I
W Resources PLC
07 August 2019
 

 

 

 

 

 

 

7 August 2019

 

W Resources Plc

("W" or the "Company")

 

La Parrilla Tungsten & Tin Mine Commissioning Advances

W Resources Plc (AIM:WRES), the tungsten, tin and gold mining company announces an update on its flagship project La Parrilla in Spain and further detail on its projects in Portugal.

At La Parrilla, the mine is in the final stages of construction and following delivery of the Motor Control Centre (MCC) the team is completing the final electrical connections in the lead up to full commissioning of the large-scale Concentrator Plant.

As previously reported, the Mine, Crusher Plant and Jig and Mill Plant are already in operation and are geared up and ready to feed upgraded ore to the new Concentrator Plant. allmineral Aufbereitungstechnik GmbH & Co. KG of Germany ("allmineral") is advancing towards final acceptance testing and signoff of the design capacity of the new 350 tonnes per hour Jig and Mill Plant. allmineral is upgrading the thickener underflow pump capacity and has made a number of changes, which are a usual part of the commissioning and ramp-up process to enhance the Jig and Mill Plant operational capacity. Ore fed to the Jig and Mill Plant is being upgraded to higher grades in line with expectations and plant throughput has been tested at design capacity.

Upgraded pre-concentrate from the new Jig and Mill Plant has been trucked to the existing ('old') La Parrilla Concentrator Plant and processed through to final tungsten and tin concentrate. Tungsten and tin concentrate stock has reached 19.8 tonnes (16t Tungsten and 3.8t Tin) in July, which is slightly lower than earlier guidance of 20t WO3 concentrate, reflecting the constraints on efficient pre-concentrate movement between plants and, in particular, due to the limitations of the old Concentrator Plant which was designed for tailings and not ore feed. Importantly, the operation of the old Concentrator Plant has provided critical information to enhance and fine-tune the performance of the new large-scale Concentrator Plant. These enhancements are being incorporated in real time in the new Concentrator Plant, an example of which is that W has purchased 72 spirals from the Wolf Minerals Limited ("Wolf Minerals") liquidator and expanded the spirals' processing capacity at La Parrilla at very limited cost. The T2 remains within budget, including contingency.

The Company has also signed an amendment agreement with BlackRock Financial Management Inc. ("BlackRock") to capitalise the last two interest payments of the BlackRock term loan, which equates to US$1.29m, which will be added to the final loan balance, further freeing up liquidity. The next quarterly interest payment will fall due in November 2019.

In Portugal at Régua, development work continues to advance with road access construction underway and mining set to commence in the December quarter. Spirals purchased from the Wolf Minerals liquidator and equipment from the existing La Parrilla Concentrator Plant will be used in the Régua plant. Golder Associates Pty Ltd ("Golder") has advised it expects to complete a JORC update of Régua's Reserves and Resource estimate in the December quarter.

As previously reported, there has been a substantial delay in SRK Consulting (UK) Ltd completing the Australasian Joint Ore Reserves Committee resource estimate for São Martinho and the final evaluation is still being reviewed. Once a satisfactory outcome has been agreed, the Company will provide a further update.

Michael Masterman, Chairman of W Resources commented: "We are getting to the closing stages of construction at La Parrilla, with the mine, Crusher and Jig and Mill Plants commissioned and processing ore and the new large-scale Concentrator Plant set to start-up by September, following the completion of the important final commissioning stage. Production from the old Concentrator Plant was below expectations in July, but importantly is greatly assisting with the enhancement of the new large-scale Concentrator Plant, which has been designed for full scale operation. We are close to finalising this process and the priority is that the commissioning is completed thoroughly. The team has delivered a fantastic mine, at low-cost and we very much look forward to first production from the new Concentrator Plant in the September quarter."

Enquiries:

W Resources Plc

Michael Masterman

T: +44 (0) 20 7193 7463

www.wresources.com

 

Grant Thornton UK LLP

Colin Aaronson / Seamus Fricker

T: +44 (0) 20 7383 5100

 

 

Joint Broker

Turner Pope Investments (TPI) Ltd

Andy Thacker

T: +44 (0) 203 621 4120

www.turnerpope.com

 

Gable Communications

Justine James

T: +44 (0) 20 7193 7463

M: +44 (0) 7525 324431

Joint Broker

Alternative Resource Capital / Shard Capital

Alex Wood

T:+44 (0) 207 186 9004

www.altrescap.com

Damon Heath

T:+44 (0) 207 186 9952

www.shardcapital.com

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLLFFIITTIRIIA
Date   Source Headline
20th May 20082:48 pmRNSPreliminary Results
8th May 20082:18 pmRNSUSA Lease Update
16th Apr 200811:30 amRNSCaspian Expands into the USA
5th Mar 20089:42 amRNSCredit Facility Agreement
20th Feb 200811:42 amRNSZhengeldy - Temp. Suspension
28th Jan 20087:00 amRNSUpdate - Zhengeldy Field
10th Jan 200811:59 amRNSShare Price Increase
21st Dec 200710:42 amRNSExport update
25th Oct 20072:31 pmRNSDirector/PDMR Shareholding
23rd Oct 20077:00 amRNSBoard and Management Changes
23rd Oct 20077:00 amRNSHolding(s) in Company
15th Oct 20077:01 amRNSZhengeldy Production Update
28th Sep 20077:04 amRNSInterim Results
13th Sep 20075:11 pmRNSAim Rule 26 Information
17th Jul 200710:14 amRNSResult of AGM
22nd Jun 20079:13 amRNSAnnual Report and Accounts
1st Jun 20075:51 pmRNSPreliminary Results
24th Apr 20079:50 amRNSCredit Facility Agreement
4th Apr 200710:58 amRNSTemporary export delay
14th Mar 20079:52 amRNSHolding in Company
14th Feb 20079:00 amRNSProduction Update
7th Feb 200711:22 amRNSHolding in Company
8th Jan 200711:23 amRNSPositive levels of oil flow
19th Dec 200612:13 pmRNSTotal Voting Rights
6th Dec 20069:25 amRNSDrilling Results
24th Oct 200611:24 amRNSWell 119 - Positive Results
27th Sep 200611:05 amRNSInterim Results
18th Sep 200611:04 amRNSCaspian continues finding oil
18th Jul 200612:14 pmRNSAGM Statement
18th Jul 200610:58 amRNSOil Shipments Increased
14th Jul 20068:56 amRNSSignificant Shareholder
3rd Jul 200610:42 amRNSAppmt of Ops Manager and CFO
26th Jun 200610:42 amRNSNotice of AGM - Replace
26th Jun 20067:01 amRNSNotice of AGM
12th Jun 20063:09 pmRNSPreliminary Results
7th Jun 20061:20 pmRNSSubstantial Shareholder
1st Jun 200610:26 amRNSDrilling Success
18th May 20069:16 amRNSAppointment
4th May 20062:33 pmRNSDrilling Report
5th Apr 200610:04 amRNSDrilling Campaign Update
4th Apr 200610:56 amRNSSignificant Shareholder
21st Mar 200611:03 amRNSIssue of Equity/Placing
14th Mar 200610:32 amRNSCasing and Testing Well 101
3rd Mar 20069:38 amRNSHolding(s) in Company
24th Feb 20068:08 amRNSHolding in Company
16th Feb 200610:59 amRNSProduction up by 35%
14th Feb 20066:28 pmRNSHoldings in Company-Amendment
13th Feb 20063:18 pmRNSHolding in Company
10th Feb 20063:27 pmRNSHoldings in Company
31st Jan 200610:33 amRNSExport Deliveries Commence

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.