Operations Update & Non-Grid Business Developments

22 Oct 2018 07:00

RNS Number : 6837E
Victoria Oil & Gas PLC
22 October 2018
 

 

 

22 October 2018

Victoria Oil & Gas Plc

("VOG" or "the Company" or "the Group")

 

Q3 2018 Operations Update and Non-Grid Business Developments

 

Victoria Oil & Gas Plc, the Cameroon based gas and condensate producer and distributor, provides an update on the Group's operations for the three months ended 30 September 2018 ("Q3 18" or "the Quarter").

 

Highlights:

 

· Gross gas sales increased by 11% on Q2 to 356mmscf

· Average gas production increased by 12% on Q2 to 3.72mmscf/d

· 4 additional thermal customers consumed gas during Q3 2018 and an additional customer was connected for industrial power just after quarter end

· GDC signed GSA's with 4 new customers for Industrial Power during the quarter

· W/E 19 October 2018 average gross gas sales of 4.6mmscf/d

· Focus on non-grid customer build out via three new business units

 

 

The Board is pleased to provide more details of its "Non-Grid" business which is focused on increasing gas sales and revenue via increased thermal sales, the roll out of its Industrial Power Unit and establishment and growth of the compressed natural gas (CNG) Unit with partners Naturelgaz of Turkey. The Company is also pleased to introduce its "Energy Well" concept which aims to provide power to people in Cameroon that have no access to grid power.

 

 

Logbaba - Quarterly Production Update

The Q3 18 gross and net gas and condensate sales for Logbaba and Gaz du Cameroun S a, ("GDC"), are as follows.

Amounts in bold are gas and condensate sales attributable to GDC (57%):

 

 

Q3 2018

Q2 2018

Q1 2018

Q4 2017

Q3 2017

Gas sales (mmscf)

 

 

 

 

 

Thermal

194

341

174

305

179

313

177

312

157

276

Industrial power

9

15

9

15

10

17

10

18

12

20

Grid power

0

0

0

0

0

0

226

396

180

317

Total (mmscf)

203

356

183

320

189

330

413

726

349

613

Average gas production (mmscf/d)

3.72

3.30

3.50

7.94

6.96

Condensate sold (bbl.)

2,298

4,032

1,657

2,907

1,654

2,900

3,951

6,931

2,538

4,452

 

 

 

 

Grid Power Update

The Government of Cameroon, ENEO Cameroon SA ("ENEO"), Altaaqa Global ("Altaaqa"), the genset providers to ENEO which consume GDC's gas, and GDC continue negotiations to end the suspension of sales to the ENEO owned Logbaba and Bassa power stations in Douala.

GDC remains confident that a solution with ENEO will be found, but a resolution has been further delayed because of the recent Presidential elections in Cameroon.

 

The shortfalls in power supply in Cameroon continue, with hydroelectric schemes not meeting the current demand. VOG will make further announcements when appropriate.

 

Consumption Increased

 

During the quarter, GDC increased consumption through the commissioning of two new thermal customers, in addition to the resumption of two former thermal customers who had not consumed since August 2017. The Company also connected an existing thermal customer for industrial power during the quarter and post quarter end has commissioned their generator. Peak consumption during the quarter was 4.98mmscf/d and average gas sales through week ending 19 October 2018 were 4.6mmscf/d with and peak of 5.6mmscf/d.

 

Overall, gross gas sales have increased 11% since Q2 to 356mmscf or an average of 3.72mmscf/d for the quarter and are expected by the Board to grow to 5 mmscf/d by year end.

 

Non-Grid Business Development

 

The Board has carefully assessed the future Cameroon business model and it is clear that whilst gas supply for grid power, to ENEO and to others, will always be a key strategy of the Group, the Board believes that it is important to diversify the customer base to reduce dependence on any single customer.

 

Rebalancing of Group customer consumption with an emphasis on non-grid has been a major driver. As a result of the considerable reserves upgrade announced in June 2018, the Company can seek long term sales contracts, both grid and non-grid. Accordingly, key focuses of management have been to:

 

· Increase thermal consumption by actively marketing the benefits of natural gas over liquid fuels

· Accelerate the Groups gas to power programme for Industrial Power (formerly called retail) customers

· Leverage VOG's relationship with Naturelgaz, aimed at bringing first CNG customers online in 2019; and

· Examine potential rural energy needs using CNG as a key fuel that allows integrated and distributed power solutions for communities with no grid power access. The Group's "Energy Well" solution is set out in more detail below.

 

Industrial Power Unit

 

With recurrent power shortages in Douala, over 30 existing and new customers have expressed interest in an industrial power solution; the GDC Industrial Power Unit. As most of these proposed power customers are already connected to GDC's gas pipeline, adding a gas fired generator would increase gas consumption with minimal downstream costs for GDC.

 

GDC are aggressively targeting industries within Douala to supply consistent, reliable and clean energy solutions in a turnkey package, with an all-inclusive capital and gas price. Previously, customers found it difficult to switch to their own power generation because of the capital cost required.

 

Working with international and local banks, GDC has developed a bespoke solution to finance the gas fired generators and have them installed at client premises with limited upfront cost to the customer. In return for a 10-year commitment, and minimum guaranteed volumes customers will pay an all-inclusive gas price which captures:

 

· Financing of the generators

· Installation and commissioning costs

· The gas consumed, and

· Operation and maintenance costs of the generator

 

This will ensure 24/7 availability for the generator and provide power utilisation times that match customer requirements and removes grid reliance. The customer will receive a single integrated monthly gas invoice.

 

Industrial Power is expected to yield substantial revenues over the next 10 years for GDC. GDC has completed negotiations with and issued GSA's to 11 customers and signed GSA's with 4 customers. We expect a further 7 customers to sign in the near term. GDC is working with Altaaqa and other equipment suppliers to fast track 6 generators for customers who wish to have power online this year and the Board believes that these customers will initially consume over 1mmscf/d of gas at a price of $13 per MMBtu.

As customer roll out continues, the target is to have over 18 gas to power customers online by end of 2019, consuming over 4.5mmscf/d of gas with no seasonality, in addition to the thermal demand.

 

 

CNG Development

 

On 26 June 2018 the Company announced an agreement to partner with Naturelgaz Sanayi ve Ticaret A.S.("Naturelgaz") on CNG projects. Naturelgaz is Europe's largest CNG supplier and distributor and brings valuable expertise within this field to support GDC. The project will allow GDC to reach to reach larger customers beyond the pipeline infrastructure and aims to replace diesel and heavy fuel oils in a variety of applications. In 2017, Naturelgaz produced and sold over 5.2bcf of CNG in Turkey.

 

GDC and Naturelgaz have completed positive feasibility and marketing studies on the CNG project in Cameroon. CNG, which is a cleaner fuel at a competitive price competes with liquid fuels such as fuel oil, LPG or diesel. Marketing studies by GDC/Naturelgaz have concluded that five types of customers would use CNG in Cameroon; thermal, off-grid power generation, commercial trucking, public transportation, and domestic transportation. The studies indicate the near-term potential of the CNG market, within a 60 km radius of the Logbaba facilities, is 2mmscf/d thermal and 2mmscf/d industrial power. The pricing of CNG will be benchmarked against competing liquid fuels. To date, 20 customers have expressed interest in CNG within a 60 km radius of Douala.

 

The partnership will provide CNG infrastructure for customers in and around Douala, with the intention of rolling the concept out further in the longer term. GDC will supply natural gas, land space and support services to the CNG production facilities, whilst Naturelgaz will design, build and operate the CNG production, distribution and offloading facilities. Negotiations on the commercial structure of this initiative are ongoing and expected to be concluded during Q4 2018.

 

 A new business concept: The Energy Well

 

The term Energy Well is derived from the timeless tradition of villagers drawing from local water wells. VOG has taken this tradition and adapted it for the purposes of energy supply.

 

 Seventy four percent of the Cameroon population has access to the National Grid and 86% of the population lives within 15km of the power network. However, household electrification stands at only 23%. There are approximately 8 million rural Cameroonians who have no access to grid electricity. This situation is replicated in many African nations where less than 10% of the rural population has access to reliable grid electricity.

 

The average rural household in Cameroon requires about 1kWh of energy per day.

 

VOG believes CNG is the bridge between renewable energy and traditional hydrocarbons and that its Energy Well system can provide a seamless, clean and reliable energy solution to regions that are currently poorly served.

 

CNG produced by GDC would be trucked to cell towers, or other locations where electricity is generated, to power the cell tower and create energy to store in large onsite batteries or for distribution to local mini or micro grids. Villagers can collect or have delivered smaller rechargeable batteries to use them in their homes as standalone energy banks or to augment solar or wind power if available, to meet their domestic power consumption needs. Consumers would pay upon receipt for battery rental or CNG bottles via mobile phone Apps.

 

Underpinning the Energy Well concept is VOG's ability to monitor, manage and immediately monetise energy, be it in the form of compressed natural gas in transit or the electricity stored in batteries throughout the supply chain. GDC has teamed up with leading edge US company Blocksyte Inc on development of the Blockchain elements of Energy Wells. The Company is working with Blocksyte, Altaaqa and others to start limited field tests this year on the key components of the business.

 

Upstream Resource Development

 

VOG is working on several activities to enhance the asset value of the Company. In Cameroon these are focused on securing the resources necessary to grow production and gas sales in the medium to long term.

 

Logbaba

 

The Logbaba exploitation license covers 20 km2 from the original 64 km2 exploration license. Negotiations have commenced to secure the remaining 44 km2 of the license of the Logbaba area.

 

Matanda

 

The PSC amendments necessary to complete the assignment of the Matanda PSC to VOG have been agreed with National Hydrocarbons Corporation, Cameroon (SNH). We have been informed that application has been made for the Presidential Decree and should be issued shortly.

 

 

West Medvezhye

 

Discussions are continuing with several interested parties in respect of the developing the West Medvezhye oil discovery in Russia. The Company's preferred option remains an outright sale.

 

This announcement contains inside information.

 

For further information, please visit www.victoriaoilandgas.com or contact: 

 

Victoria Oil & Gas Plc

Kevin Foo / Ahmet Dik Tel: +44 (0) 20 7921 8820

 

Strand Hanson Limited (Nominated and Financial Adviser)

Rory Murphy / Stuart Faulkner / Ritchie Balmer Tel: +44 (0) 20 7409 3494

 

Shore Capital Stockbrokers Limited (Joint Broker)

Mark Percy / Toby Gibbs (corporate finance) Tel: +44 (0) 207 408 4090

Jerry Keen (corporate broking)

 

FirstEnergy Capital LLP (Joint Broker)

Jonathan Wright / David van Erp Tel: +44 (0) 207 448 0200

 

Camarco (Financial PR)

Billy Clegg Tel: +44 (0) 203 757 4983

Nick Hennis Tel: +44 (0) 203 781 8330

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
STRPGGUUUUPRGRG
Date   Source Headline
11th Jun 20204:41 pmRNSSecond Price Monitoring Extn
11th Jun 20204:35 pmRNSPrice Monitoring Extension
8th Jun 202012:07 pmRNSSecond Price Monitoring Extn
8th Jun 202012:02 pmRNSPrice Monitoring Extension
8th Jun 20207:00 amRNSNotice of Annual General Meeting
18th May 20207:00 amRNSResignation of Director
20th Apr 202012:07 pmRNSSecond Price Monitoring Extn
20th Apr 202012:02 pmRNSPrice Monitoring Extension
17th Apr 20201:45 pmRNSReplacement: Q1 2020 Operational Update
17th Apr 20207:00 amRNSQ1 2020 Operational Update
25th Mar 202010:00 amRNSBusiness Update and Chairman Interview
16th Mar 20204:42 pmRNSSecond Price Monitoring Extn
16th Mar 20204:38 pmRNSPrice Monitoring Extension
11th Mar 20207:00 amRNSRoy Kelly Appointed as New CEO and Board Change
10th Mar 20204:41 pmRNSSecond Price Monitoring Extn
10th Mar 20204:35 pmRNSPrice Monitoring Extension
9th Mar 202012:07 pmRNSSecond Price Monitoring Extn
9th Mar 202012:02 pmRNSPrice Monitoring Extension
21st Feb 20207:00 amRNSRSM and VOG Arbitration
10th Feb 20207:00 amRNSAppointment of Non-Executive Director
5th Feb 20207:00 amRNSOperations Update
8th Jan 20207:00 amRNSTermination of Broker Services
14th Nov 20192:33 pmRNSDirectorate Change
7th Oct 201910:00 amRNSHolding(s) in Company
30th Sep 20197:00 amRNSHalf-year Report
2nd Sep 201911:53 amRNSHolding(s) in Company
27th Aug 20192:05 pmRNSHolding(s) in Company
5th Aug 20197:00 amRNSGrant of Options to Directors and employees
29th Jul 20197:00 amRNSTerm Sheet signed with Aksa Energy
8th Jul 20197:00 amRNSDirectorate Change
5th Jul 201912:30 pmRNSPost-AGM Q2 2019 Operations Update
5th Jul 201910:59 amRNSHolding(s) in Company
27th Jun 20194:15 pmRNSResult of AGM
27th Jun 20191:10 pmRNSPre-AGM Trading Update
5th Jun 20197:00 amRNSIssue of Shares
4th Jun 20197:55 amRNSCREDITOR SETTLEMENT AGREEMENT
28th May 20197:00 amRNSAnnual Report & Accounts to 31 December 2018
24th May 20197:00 amRNSPreliminary Results
15th May 20194:00 pmRNSHolding(s) in Company
9th May 20197:00 amRNSQ1 2019 Operations Update
15th Apr 201912:00 pmRNSHolding(s) in Company
5th Apr 201910:30 amRNSHolding(s) in Company
4th Apr 20197:00 amRNSAppointment of Independent Non-Executive Directors
3rd Apr 201912:30 pmRNSResult of General Meeting and Board Changes
11th Mar 20191:15 pmRNSPosting of Circular & Notice of General Meeting
7th Mar 20197:00 amRNSResult of Placing
6th Mar 20197:30 amRNSSubscription & Placing & Proposed Board Changes
5th Mar 20193:30 pmRNSHolding(s) in Company
19th Feb 201912:30 pmRNSHolding(s) in Company
29th Jan 20197:00 amRNSProduction Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.