Less Ads, More Data, More Tools Register for FREE

Pin to quick picksVOG.L Regulatory News (VOG)

  • There is currently no data for VOG

Continuous Production Operations at Logbaba

9 Jul 2012 07:00

RNS Number : 1587H
Victoria Oil & Gas PLC
09 July 2012
 



9 July 2012

 

Victoria Oil & Gas Plc

('VOG' or 'the Company')

(AIM: VOG)

Commencement of Continuous Gas and Condensate Production

Operations at Logbaba

 

Highlights:

 

·; RDL commences continuous production operations at Logbaba

·; Current production of 0.7 million standard cubic feet per day ('mmscf/d')

·; Production forecasts remains on schedule to increase to 8 mmscf/d by the end of 2012

·; RDL becomes the first gas producer in Cameroon to supply the industrial market

 

Victoria Oil & Gas Plc, the AIM quoted oil and gas exploration and production company with assets in Cameroon and the FSU, is pleased to announce the commencement of continuous production operations at its 95% owned and operated Logbaba gas and condensate project onshore Cameroon managed by its wholly owned subsidiary Rodeo Development Limited, ('RDL').

 

The Company's first three customers are now taking delivery of gas in sufficient volume to allow the production facilities to operate 24 hours a day, delivering gas in full compliance with specification. These customers have a combined average daily demand of approximately 0.7 mmscf/d. The Company is assisting additional customers to convert their factories to take gas.

 

The Company remains on schedule to increase production to 8 mmscf/d by the end of the year. This will be driven by an increase in the number of thermal (heat requirement) customers and the installation of gas powered electrical generation units on customers' sites. The first units are expected to come on line in mid Q4 2012. This will be a major development for Cameroon, making clean and reliable power available to industrial users.

 

Further updates on existing customer volumes will be provided in due course.

 

 

 

For further information, please contact:

Victoria Oil & Gas Plc - Tel: +44 (0) 20 7921 8820

Kevin Foo / Martin Devine

Macquarie Capital (Europe) Limited - Tel: +44 (0) 20 3037 2000

Jeffrey Auld / Steve Baldwin / Nicholas Harland

Fox-Davies Capital - Tel: +44 (0) 20 3463 5010

Daniel Fox-Davies/ Richard Hail

Strand Hanson Limited - Tel: +44 (0) 20 7409 3494

Simon Raggett / Angela Peace

Tavistock Communications - Tel: +44 (0) 20 7920 3150

Ed Portman/ Simon Hudson

 

Background Information on Victoria Oil & Gas Plc:

 

Victoria Oil & Gas Plc is an independent oil and gas exploration and production company with projects in Africa and the FSU. The Company's principal assets are the Logbaba gas and condensate project in Cameroon and the West Medvezhye project in Siberia, Russia. Logbaba is located in Douala, the economic capital of Cameroon. The field was discovered in the 1950s when all four exploration wells drilled at the time encountered gas. The Company drilled two successful development wells in 2009/10 and was awarded an Exploitation Licence in April 2011.

 

The Company's Logbaba proved and probable reserves are sufficient to supply an average of 30 mmscf/d for the next 20 years to industrial customers. Under current management projections, the Company forecasts industrial gas demand to rise to 44 mmscf/d by the end of 2014. In the longer term, as further reserves may be proven, gas may also be supplied to large gas fired power stations connected to the grid, with either VOG investing in an independent power producer joint venture or selling the gas to third parties. The Company has signed a multitude of gas sales agreements with industrial customers to serve their energy requirements and anticipates in excess of 40 customers over the medium term.

 

West Medvezhye is situated in the prolific Yamal-Nenetsk hydrocarbon region in Siberia. An independent audit, carried out by Mineral LLC in 2011, estimated prospective resources for the area of over 1.4 billion barrels of oil equivalent ('boe'). The Company also has a discovery well, 103, with C1 and C2 reserves, independently assessed under the Russian classification convention of 14.4 million boe as approved by the Russian Ministry of Natural Resources.

 

Development studies are in progress to commercialise the Well-103 discovery and prospective resources and a detailed well design study for the upcoming drilling campaign has commenced.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUNVVRUAABRAR
Date   Source Headline
18th Jun 20217:00 amRNSLoan Note Instrument
4th Jun 202111:07 amRNSNotice of Annual General Meeting
4th Jun 20217:00 amRNSCorporate Update
30th Apr 20217:00 amRNSQ1 2021 Operational Update
19th Apr 20212:06 pmRNSSecond Price Monitoring Extn
19th Apr 20212:01 pmRNSPrice Monitoring Extension
19th Apr 20211:44 pmRNSSettlement with Eneo Cameroon S.A. ("Eneo")
8th Apr 20217:00 amRNSLoan Note
6th Apr 20219:06 amRNSSecond Price Monitoring Extn
6th Apr 20219:00 amRNSPrice Monitoring Extension
1st Apr 20217:23 amRNSCorporate and Operational Update
28th Jan 20217:00 amRNSQ4 2020 Operational Update
22nd Jan 20212:06 pmRNSSecond Price Monitoring Extn
22nd Jan 20212:00 pmRNSPrice Monitoring Extension
24th Nov 20207:54 amRNSMinisterial Approval on Matanda Licence Extension
23rd Nov 20204:41 pmRNSSecond Price Monitoring Extn
23rd Nov 20204:36 pmRNSPrice Monitoring Extension
23rd Nov 20202:06 pmRNSSecond Price Monitoring Extn
23rd Nov 20202:00 pmRNSPrice Monitoring Extension
18th Nov 20207:00 amRNSIssue of Shares
16th Nov 20204:42 pmRNSSecond Price Monitoring Extn
16th Nov 20204:36 pmRNSPrice Monitoring Extension
13th Nov 20204:40 pmRNSSecond Price Monitoring Extn
13th Nov 20204:35 pmRNSPrice Monitoring Extension
12th Nov 20207:00 amRNSSettlement of litigation with CHL & La-108 update
11th Nov 20204:41 pmRNSSecond Price Monitoring Extn
11th Nov 20204:36 pmRNSPrice Monitoring Extension
3rd Nov 20204:40 pmRNSSecond Price Monitoring Extn
3rd Nov 20204:35 pmRNSPrice Monitoring Extension
2nd Nov 20204:36 pmRNSPrice Monitoring Extension
30th Oct 20207:00 amRNSHalf-year Report
29th Oct 202011:38 amRNSResult of General Meeting
28th Oct 20204:36 pmRNSPrice Monitoring Extension
27th Oct 20204:40 pmRNSSecond Price Monitoring Extn
27th Oct 20204:35 pmRNSPrice Monitoring Extension
26th Oct 20204:40 pmRNSSecond Price Monitoring Extn
26th Oct 20204:35 pmRNSPrice Monitoring Extension
30th Sep 20207:00 amRNSAudited Results for year ended 31 December 2019
14th Aug 202012:07 pmRNSSecond Price Monitoring Extn
14th Aug 202012:02 pmRNSPrice Monitoring Extension
11th Aug 20207:00 amRNSAppointment of Chief Financial Officer
27th Jul 20207:28 amRNSQ2 2020 Operational Update
7th Jul 20204:40 pmRNSSecond Price Monitoring Extn
7th Jul 20204:35 pmRNSPrice Monitoring Extension
3rd Jul 202012:36 pmRNSTermination of Agreement to Supply Gas to ENEO
29th Jun 20204:41 pmRNSSecond Price Monitoring Extn
29th Jun 20204:37 pmRNSPrice Monitoring Extension
29th Jun 202012:35 pmRNSResult of Annual General Meeting
26th Jun 20204:35 pmRNSPrice Monitoring Extension
25th Jun 20207:00 amRNSAnnual Report and Accounts & Trading update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.