Operational Update

14 Dec 2015 07:00

RNS Number : 8861I
Volga Gas PLC
14 December 2015
 

 

 

14 December 2015

Volga Gas plc

("Volga Gas", the "Company" or the "Group")

 

OPERATIONAL UPDATE

 

Volga Gas plc, the oil and gas exploration and production group operating in the Volga Region of Russia, is pleased to provide the following update on its operations.

 

Vostochny Makarovskoye ("VM") field

 

As of 11 December 2015, the VM#4 well, in which the Group drilled a successful sidetrack earlier in 2015, has been hooked up and is ready to be put on production. With the inclusion of this well to the existing stock of producing wells on the VM and Dobrinskoye fields, there is sufficient capacity for full utilization of the current planned operational capacity of 750,000 m3 per day of gas processing at the Dobrinskoye Gas Plant. This production rate, with the associated condensate equates to production of over 5,700 barrels of oil equivalent per day ("boepd"). Combined with the Company's currently modest oil output, total Group production is estimated to be approximately 6,000 boepd.

 

Yuzhno Mironovskaya exploration well

 

The exploratory well on the Yuzhno Mironovskaya prospect, as announced on 7 December 2015, was drilled to a total vertical depth of 940 metres within a time of 21 days, a record drilling rate for the Group. After running logs, the principal and secondary target zones in the Cretaceous post salt Albian and Aptian formations were found to be water bearing and the well is being plugged and abandoned. With the efficient well drilling, the total cost of this well was limited to approximately US$800,000.

 

Sobolevskaya-11 and Uzen-8 sidetracks

 

As stated in the 2015 Interim Report, sidetracks were being drilled on both of these currently non-producing oil wells with the aim of recovering production. Unfortunately significant mechanical difficulties were encountered in both of these wells and the operations on both have been temporarily suspended.

 

At Sobolevskaya-11, there is an ongoing contractual dispute with the drilling contractor. Subject to satisfactory resolution of this, the Group plans to complete the drilling of this well which requires a further 250 metres to reach the potential target reservoir at a total vertical depth of approximately 2,600 metres, expected to be in Q1 2016.

 

At Uzen-8, which at 1,000 metres has a shallower reservoir, it is believed that a re-drill would be required. For the time being this operation is to be deferred.

 

Export channels for condensate sales

 

During November and December 2015, the Group exported its first two cargoes of 500 tonnes each of condensate from its gas plant. The cargoes were delivered to a rail loading terminal and shipped on to customers in Lithuania. While this is still a trial operation, export channels are being developed to offset the risk of disruption to the regional domestic market which impacted production and sales of gas and condensate earlier in 2015.

 

Andrey Zozulya, Chief Executive of Volga Gas, commented:

"It is pleasing to achieve the important production target with the new well on the VM field. With the completion of the VM#3 well, which is already drilled but awaiting tie-back, the Group is well placed to reach an eventual plateau of 1 million cubic metres of daily gas production from the VM and Dobrinskoye fields.

"The results from the exploration well and delays to the sidetracks are disappointing. However, recent changes in the management of drilling contractors are expected to improve efficiency, as we have seen at Yuzhno Mironovskaya, and we will update the market once we have clarity on the timing for completion of these wells."

 

For further information, please contact:

 

Volga Gas plc

Andrey Zozulya, Chief Executive Officer

Tony Alves, Chief Financial Officer

+7 903 385 9889

+44 (0)20 8622 4451

Stifel Nicolaus Europe Limited (Nominated Adviser and Broker)

+44 (0)20 7710 7600

Michael Shaw, Ashton Clanfield

FTI Consulting

+44 (0)20 3727 1000

Edward Westropp, Alex Beagley

 

 

Editors' notes:

 

Volga Gas is an independent oil and gas exploration and production company operating in the Volga region of Russia. The company has 100% interests in its four licence areas.

 

The information contained in this announcement has been reviewed and verified by Mr. Andrey Zozulya, Director and Chief Executive Officer of Volga Gas plc, for the purposes of the Guidance Note for Mining, Oil and Gas companies issued by the London Stock Exchange in June 2009. Mr. Andrey Zozulya holds a degree in Geophysics and Engineering from the Groznensky Oil & Gas Institute and is a member of the Society of Petroleum Engineers.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLUOSBRVAAUAAA
Date   Source Headline
29th Apr 20107:00 amRNSKarpenskiy Licence Area: new supra salt prospect
30th Mar 20107:00 amRNSFull year results
4th Mar 201010:00 amRNSOperational Update - Vostochny Makarovskoye
23rd Nov 20097:00 amRNSOperational Update
26th Oct 20097:00 amRNSDrilling Update
16th Sep 20097:00 amRNSInterim Results
28th Aug 20097:00 amRNSDrilling commences on sub-salt Grafovskaya
25th Aug 20097:00 amRNSKarpenskiy supra-salt operational update
14th Aug 20094:40 pmRNSSecond Price Monitoring Extn
14th Aug 20094:35 pmRNSPrice Monitoring Extension
30th Jul 20097:00 amRNSDevelopment Drilling Update
10th Jul 200911:31 amRNSHolding(s) in Company
10th Jul 20099:21 amRNSHolding(s) in Company
7th Jul 20098:01 amRNSDealings by Directors and Significant Shareholders
6th Jul 20094:40 pmRNSSecond Price Monitoring Extn
6th Jul 20094:35 pmRNSPrice Monitoring Extension
6th Jul 200911:44 amRNSResult of General Meeting
22nd Jun 20091:59 pmRNSDirector/PDMR Shareholding
22nd Jun 20097:00 amRNSResult of Bookbuilding
19th Jun 20094:21 pmRNSPosting of Circular to Shareholders
18th Jun 20099:48 amRNSResult of AGM
18th Jun 20099:14 amRNSReplacement: Placing
18th Jun 20097:00 amRNSPlacing
17th Jun 20094:41 pmRNSSecond Price Monitoring Extn
17th Jun 20094:35 pmRNSPrice Monitoring Extension
10th Jun 20097:00 amRNSDrilling Update
14th May 20093:37 pmRNSDirector dealing
8th May 20094:35 pmRNSPrice Monitoring Extension
7th May 20093:27 pmRNSHolding(s) in Company
30th Apr 20098:55 amRNSChange of Adviser
31st Mar 20097:00 amRNSFinal Results
30th Mar 20097:00 amRNSReserve Report and Drilling Update
17th Mar 20098:47 amRNSReplacement: Issue of Equity
17th Mar 20098:45 amRNSReplacement: Total Voting Rights
10th Mar 200911:14 amRNSChange of Registered Address
2nd Mar 20094:40 pmRNSSecond Price Monitoring Extn
2nd Mar 20094:36 pmRNSPrice Monitoring Extension
27th Feb 20094:41 pmRNSSecond Price Monitoring Extn
27th Feb 20094:36 pmRNSPrice Monitoring Extension
3rd Feb 20093:28 pmRNSOperational update
15th Jan 20095:22 pmRNSHolding(s) in Company
14th Jan 20098:44 amRNSRe Management Share Options
7th Jan 200911:43 amRNSResult of EGM
19th Dec 20084:40 pmRNSSecond Price Monitoring Extn
19th Dec 20084:36 pmRNSPrice Monitoring Extension
18th Dec 20084:41 pmRNSSecond Price Monitoring Extn
18th Dec 20084:36 pmRNSPrice Monitoring Extension
17th Dec 20084:40 pmRNSSecond Price Monitoring Extn
17th Dec 20084:35 pmRNSPrice Monitoring Extension
16th Dec 20084:40 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.