Oman Antimony Roaster - Capital Budget Update

24 Jul 2017 07:00

RNS Number : 8221L
Tri-Star Resources PLC
24 July 2017
 

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No. 596/2014 until the release of this announcement

24 July 2017

Tri-Star Resources plc

("Tri-Star" or the "Company")

Oman Antimony Roaster - Capital Budget Update

Tri-Star announces further progress by Strategic & Precious Metals Processing LLC ("SPMP") in developing the Oman Antimony Roaster project ("OAR"). The OAR is located in Sohar, Sultanate of Oman. Tri-Star has a 40% equity interest in SPMP.

Since the Company's update reported in the circular to shareholders dated 1 June 2017, process test-work has now been largely concluded, with work now focusing primarily on operational readiness. Consequential final plant modifications have moved forecast plant commissioning, as expected, into Q1 2018. Importantly, SPMP's negotiations with Traxys Europe SA ("Traxys") were concluded on schedule and, as announced by Tri-Star on 13 June 2017, SPMP has signed a multi-year feedstock supply contract with Traxys.

Moreover, SPMP has achieved process design freeze for the overall project which has enabled a more definitive appraisal of the costs to complete to be undertaken. As such, and further to the matters described above, SPMP has formally approved an increase in the capital budget for the construction of OAR to $96.0 million, plus a contingency that can be approved by the Board of SPMP on a case by case basis. 

The bulk of the increase in the capital budget results from design changes. Specifically:

- increasing the capability of the plant to accept a wider range of feedstock such as direct shipping ores, of which there is a large global network of small scale operators currently poorly served with sustainable off-taker demand; 

- expansion of the downstream gold treatment and associated gas handling which will allow the OAR to bring in non-conventional feed sources of high gold content directly for gold recovery, thereby increasing gold output viability without compromising the antimony concentrate process route; and 

- thirdly, subsequent to test-work, altering the design and materials for construction of the gold furnaces to protect the equipment from the highly corrosive behaviour of antimony on linings, therefore improving plant life, equipment performance and most importantly the quality of the gold to be produced.

SPMP's existing committed financing facilities amount to $70 million, comprising senior debt of $40 million from Bank Nizwa and shareholder loans and equity of a further $30 million. As a result of the now confirmed revised capital budget, SPMP is working closely with its stakeholders (both prospective lenders and existing shareholders) to increase the size of these facilities to accommodate the increased capital cost, the associated contingency, and SPMP's working capital requirements through to cash flow positive operations. Tri-Star expects SPMP to be in a position to start paying dividends to shareholders within three years of commencement of commercial operations in Q1 2018.

As already advised in the circular to shareholders dated 1 June 2017, the Tri-Star expects to be invited to participate in this further round of financing in order to maintain its 40% interest in the project. Further announcements regarding the financing will be made by the Company in due course.

References in this announcement to $ mean United States Dollars.

 

Enquiries:

Tri-Star Resources plc Tel: +44 (0) 20 3470 0470

Guy Eastaugh, Chief Executive Officer

SP Angel Corporate Finance (Nomad and Broker) Tel: +44 (0) 20 3470 0470

Robert Wooldridge / Jeff Keating

Yellow Jersey PR Limited (Media Relations) Tel: +44 (0) 776 932 5254

Felicity Winkles / Joe Burgess

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEUESDFWSELW
Date   Source Headline
16th Jan 20141:40 pmRNSIssue of Equity and TVR
20th Dec 20137:00 amRNSPreliminary Report and Antimony Roaster Update
1st Nov 20137:00 amRNSQuarterly Results to 30 September 2013
31st Oct 201311:06 amRNSTotal Voting Rights
17th Oct 20137:00 amRNSHolding in Company
15th Oct 201312:46 pmRNSHolding in Company
9th Oct 20133:01 pmRNSMOU signed re. Roaster Project
7th Oct 20137:00 amRNSCompletion of Acquisition
2nd Oct 20137:00 amRNSChange of Adviser
1st Oct 20137:00 amRNSUpdate re Acquisition of Portage Minerals Inc.
27th Sep 201311:24 amRNSDrawdown of Convertible Bonds
13th Sep 20137:00 amRNSPortage Shareholder Approval
6th Sep 20137:00 amRNSProposed Acquisition of Portage Minerals Inc.
2nd Sep 20137:00 amRNSH1 2013 Interim Results
20th Aug 20134:45 pmRNSProposed Acquisition of Portage Minerals Inc.
6th Aug 20137:00 amRNSProposed Acquisition of Portage Minerals Inc
23rd Jul 20131:45 pmRNSResult of AGM
26th Jun 20137:00 amRNSNotice of AGM
20th Jun 20137:01 amRNSFinal Results for the year ended 31 December 2012
20th Jun 20137:00 amRNSIssue of Convertible Bonds
18th Jun 20132:30 pmRNSResult of General Meeting
31st May 20137:00 amRNSNotice of General Meeting
31st May 20137:00 amRNSTotal Voting Rights
21st May 20131:45 pmRNSHolding(s) in Company
20th May 20134:35 pmRNSHolding(s) in Company
2nd May 20137:00 amRNSPlacing, Proposed Acquisition & Roaster JV Update
5th Apr 20138:42 amRNSLaunch of Antimony World Website
4th Mar 20137:05 amRNSChange of Registered Office
26th Sep 20127:00 amRNSHalf Yearly Report
8th Aug 20127:00 amRNSAntimony Technical Collaboration in Myanmar
25th Jul 201211:49 amRNSResult of AGM
17th Jul 20127:00 amRNSSubscription
29th Jun 20127:00 amRNSFinal Results
20th Jun 20127:00 amRNSOperational update
28th Feb 20122:35 pmRNSUAE Antimony Roaster - Update
14th Feb 20127:00 amRNSDrilling Report - Göynük Project, Turkey
4th Jan 20121:00 pmRNSDirectorate Changes and Address Change
6th Dec 20117:00 amRNSInterim Sampling Results - Canada
26th Oct 20118:02 amRNSInterim assay results - 2011 drilling programme
17th Oct 20117:00 amRNSEnvironmental Clearance for UAE Antimony Roaster
7th Oct 20118:00 amRNSInterim assay results for 2011 drilling programme
30th Sep 20117:00 amRNSHalf Yearly Report
1st Sep 20116:00 pmRNSFurther re Proposed Joint Venture
26th Jul 20112:30 pmRNSMemorandum of Understanding
1st Jul 20117:00 amRNSAcquisition of Licence
28th Jun 20117:00 amRNSProposed Joint Venture
20th Jun 20112:15 pmRNSAppointment of Drilling Contractor
2nd Jun 20117:00 amRNSResult of AGM
26th May 20111:00 pmRNSExploration target extended
11th May 20117:00 amRNSGrant of Options

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.