Lesedi Drilling and Project Update

11 Sep 2023 07:00

RNS Number : 9340L
Tlou Energy Ltd
11 September 2023
 

 

11 September 2023

 

Tlou Energy Limited

("Tlou" or "the Company")

 

Lesedi 4 and 6 drilling successfully completed

 

 

Ø Lateral wells of the Lesedi 4 production pod have been successfully redrilled

Ø Drilling of Lesedi 6 production pod was completed earlier

Ø Dewatering leading to gas production can now commence on Lesedi 4 and Lesedi 6

 

Production Wells

The successful redrill of both lateral wells of the Lesedi 4 production pod has been completed. As reported previously, drilling has also been completed at the new Lesedi 6 pod with both lateral wells (Lesedi 6A and Lesedi 6B) successfully intersecting the target vertical well (Lesedi 6P).

 

The aim of redrilling the Lesedi 4 wells is to provide straighter lateral sections compared to the original wells. The Lesedi 4 pod has flowed gas for a number of years and these straighter laterals are expected to assist with removing water from the reservoir to more efficiently dewater and flow gas.

 

Following completion of the redrill, both Lesedi 4 and Lesedi 6 pods will be flushed to clear the wells and then have production equipment installed to commence dewatering ahead of gas production.

 

Transmission Lines and Substations

Construction of the transmission lines to connect the Lesedi power project to the existing power grid is progressing. Overall progress to date is approximately 90%. Key items outstanding include a road crossing and further stringing of the line. Transmission line work is on track to be completed later this year and well in advance of planned first power into the grid.

 

Separately, work on the substations which are required at either end of the transmission line is also continuing. The contractors are onsite at Lesedi carrying out initial work including site clearing and further updates will be provided in due course.

 

Some recent short videos from the Lesedi site have also been uploaded online at:

https://youtube.com/@TlouEnergy?si=o1HwLoXvGF8G7NrD

 

By Authority of the Board of Directors

Mr. Anthony Gilby

Managing Director

****

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3040 9084

Tony Gilby, Managing Director

 

Solomon Rowland, General Manager

 

 

 

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Harrison Clarke, Colin Aaronson, Ciara Donnelly

 

 

 

Zeus Capital (UK Broker)

+44 (0)20 3829 5000

Simon Johnson

Investor Relations

Ashley Seller (Australia)

+61 418 556 875

FlowComms Ltd - Sasha Sethi (UK)

+44 (0) 7891 677 441

 

About Tlou

Tlou is developing energy solutions in Sub-Saharan Africa through gas-fired power and ancillary projects. The Company is listed on the ASX (Australia), AIM (UK) and the BSE (Botswana). The Lesedi Gas-to-Power Project ("Lesedi") is 100% owned and is the Company's most advanced project. Tlou's competitive advantages include the ability to drill cost effectively for gas, operational experience and Lesedi's strategic location in relation to energy customers. All major government approvals have been achieved.

 

Forward-Looking Statements

This announcement may contain certain forward-looking statements. Actual results may differ materially from those projected or implied in any forward-looking statements. Such forward-looking information involves risks and uncertainties that could significantly affect expected results. No representation is made that any of those statements or forecasts will come to pass or that any forecast results will be achieved. You are cautioned not to place any reliance on such statements or forecasts. Those forward-looking and other statements speak only as at the date of this announcement. Save as required by any applicable law or regulation, Tlou Energy Limited undertakes no obligation to update any forward-looking statements.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
DRLEAXNEFFADEFA
Date   Source Headline
12th Apr 20197:00 amRNSAllotment of Placement shares
8th Apr 20197:00 amRNSAUD$1.2 million equity raising at premium
1st Apr 20197:08 amRNSNew Prospecting Licence Area
18th Mar 20197:00 amRNSField Operations Update
13th Mar 20197:00 amRNSTender Technical Stage Decision Approved
26th Feb 20197:00 amRNSInterim Results
25th Feb 20197:00 amRNSProduction testing underway at Lesedi
12th Feb 20197:00 amRNSFirst development pod successfully completed
6th Feb 20194:30 pmRNSASX query and response
23rd Jan 20197:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 31 DEC 2018
15th Jan 20197:00 amRNSRecommencement of Drilling and Operational Update
4th Dec 20187:00 amRNSTop-hole drilling successfully completed at Lesedi
20th Nov 20187:00 amRNSOperations Update - Excellent Progress at Lesedi
6th Nov 20187:00 amRNSOperations Update
30th Oct 20187:00 amRNSOPERATIONAL REPORT - QUARTER ENDED 30 SEPT 2018
22nd Oct 20187:00 amRNSOperations Update
19th Oct 201812:42 pmRNSIssue of Performance Rights
17th Oct 20187:00 amRNSResults of AGM and Chairman's Address
10th Oct 20182:26 pmRNSTender Submitted
17th Sep 20187:10 amRNSOperations Update
17th Sep 20187:00 amRNSNotice of Annual General Meeting
6th Sep 20181:56 pmRNSChange to RFP submission date
30th Aug 20187:00 amRNSFinal Results
28th Aug 20187:00 amRNSConference Presentation
13th Aug 20181:26 pmRNSOperations Update and RFP bidders meeting
31st Jul 20187:00 amRNSHoldings in Company
31st Jul 20187:00 amRNSSouthern African Power Market Study
27th Jul 20187:05 amRNSGovernment Releases Re-tender of 100MW RFP
25th Jul 201811:43 amRNSOPERATIONAL REPORT - QUARTER ENDING 30 JUNE 2018
18th Jul 20182:18 pmRNSOperations Update
13th Jul 20187:00 amRNSDirectors participation in the Entitlement Offer
11th Jul 20187:00 amRNSEntitlement Offer Closes
28th Jun 20187:00 amRNSOperations Update
20th Jun 20187:38 amRNSEntitlement Offer - Dispatch of Booklet
8th Jun 20187:49 amRNSEntitlement Offer - Letters to Shareholders
6th Jun 20189:47 amRNSEquity Placement and Entitlement Offer
17th May 20187:00 amRNSCorporate Presentation
23rd Apr 20187:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 31 MARCH 2018
22nd Feb 20188:02 amRNSInterim Results
20th Feb 20189:45 amRNSFurther material increase in Gas Reserves
15th Feb 201811:22 amRNS100 MW Request for tender debrief meeting
12th Feb 20184:18 pmRNSGovernment Request for Re-tender of 100MW RFP
23rd Jan 20187:00 amRNSOPERATIONAL REPORT - QUARTER ENDING 31 DECEMBER
22nd Dec 201711:53 amRNSHolding(s) in Company
20th Dec 201712:33 pmRNSHolding(s) in Company
19th Dec 20177:00 amRNSCore-hole Drilling Operations Update
18th Dec 20177:00 amRNSIssue of Shares - Performance Rights Plan
12th Dec 20177:00 amRNSListing on BSE approved and issue of share capital
4th Dec 201712:51 pmRNSExercise of Options
28th Nov 20177:00 amRNSSeismic Survey and Core-hold Operations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.