focusIR May 2024 Investor Webinar: Blue Whale, Kavango, Taseko Mines & CQS Natural Resources. Catch up with the webinar here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksThor Energy Regulatory News (THR)

Share Price Information for Thor Energy (THR)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.90
Bid: 0.80
Ask: 1.00
Change: 0.00 (0.00%)
Spread: 0.20 (25.00%)
Open: 0.90
High: 0.90
Low: 0.90
Prev. Close: 0.90
THR Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Upgraded Ore Reserve For Molyhil Tungsten Mine

29 Jul 2014 07:00

RNS Number : 5489N
Thor Mining PLC
29 July 2014
 

 

29 July 2014

 

 

THOR MINING PLC

 

UPGRADED ORE RESERVE DELIVERS LONGER 6 YEAR LIFE FOR MOLYHIL TUNGSTEN MINE

 

An updated Ore Reserve Statement of 3.0 million tonnes @ 0.31% WO (tungsten tri-oxide) and 0.12% Mo (molybdenum) has been announced by Thor Mining Plc ("Thor") (AIM, ASX: THR) for its wholly-owned proposed Molyhil tungsten mine in Australia's Northern Territory ("Molyhil").

The revised reserve is likely to support a six year mine life at Molyhil, a two year extension from the previous study as announced on 30 May 2012.

This new reserve, with improvements largely attributable to the benefits of adopting ore sorting technology, has boosted mineable reserves of contained tungsten in WO by 33.3% to 9,200 tonnes, and contained molybdenum by 63.6% to 3,600 tonnes.

Highlights

· Reserve statement of 3.0 million tonnes @ 0.31% WO and 0.12% Mo.

· Ore sorting increases grade of material processed by 15% to 0.35% WOand 0.14% Mo.

· Post ore sort tungsten equivalent grade of 0.46% WO using a 15% upgrade.

· Very high grade near-surface tungsten provides opportunity for early payback of project capital.

 

Next steps

· Update capital and operating cost estimates

· Completion of upgraded financial feasibility study

 

 

Mr Mick Billing, Executive Chairman of Thor Mining:

"This is a major step forward for the Molyhil project. The Open Cut Ore Reserve Statement provides for significant additional production from Molyhil, whilst the process improvements demonstrate that production costs will be very low, particularly in the initial couple of years. Indeed, the tungsten grade of the mineralisation, in the top 40 metres of the resource, before molybdenum credits, is 0.53% WO3, substantially above the project's average grade, suggesting very low operating costs in the first two years of operation, and subsequent early capital payback.

 

The next step is to update the bankable feasibility study for the project, including a review of capital and operating costs. This is anticipated to be completed before the end of the quarter ended September 2014, enabling the finance of the project to be concluded. The Directors believe that the enhanced project economics shown by this updated Reserve statement will significantly boost the prospects of securing project finance."

 

Molyhil Open Cut Ore Reserve Statement

Based upon the Resources Estimate reported to the ASX & AIM on 30 January 2014, and following a re-estimate of costs and metallurgical recovery factors, mining consultancy, AVCS Pty Ltd, has issued a statement of Open Cut Ore Reserve for the Molyhil deposit of 3.0 million tonnes averaging 0.31% WO3 & 0.12% Mo, classified as Probable. See Table 1 and Attachment 1. The improved outcome is largely driven by successful test results of pre-concentration of ore using ore sorting technology.

Table 1: Molyhil Open Cut Ore Reserve Statement

Classification

Reserve

WO3

Mo

'000 Tonnes

Grade %

Tonnes

Grade %

Tonnes

Probable

3,000

0.31

9,200

0.12

3,600

Total

3,000

0.31

9,200

0.12

3,600

Notes:

· Thor Mining PLC holds 100% equity interest in this reserve.

· Estimate has been rounded to reflect accuracy.

· All estimates are on a dry tonne basis.

· The reserve estimate extends to a maximum depth below surface of 150 metres.

· The statement is derived from the Indicated portion of the resource estimate only, and the Inferred portion is excluded from the calculations. The long-term prices used were US$408/mtu for WO3 concentrate and US$12.76/lb for Mo concentrate at an exchange rate of US$0.83 to A$1.00. The WO3 and Mo Processing Recovery post ore sorting used was 85% and 77.8% respectively.

 

Much of the improvement in outcomes is derived from the innovation of ore sorting technology where Thor has successfully demonstrated a 15% to 25% mass rejection with minimal loss of payable metal. Other savings have been achieved compared with previous studies, via electing to owner-operate mining activities rather than use contract miners, and to purchase some infrastructure items in lieu of leasing. Some further process improvements are also in progress with scheelite flotation testwork continuing.

 

Next steps

Using this open cut reserve statement, AVCS has prepared a detailed mining plan to provide Thor with a monthly mining schedule for the currently estimated life of the proposed operation, including tonnes of ore and waste removed and the grade of the material mined. This will then be incorporated into the financial model, along with revised capital and operating cost estimates, to prepare economic return estimates.

It is expected that this process will be completed during the quarter ending 30 September 2014.

About Tungsten

Tungsten is used in the manufacture of hard metals, steels, alloys and mill products. Its unique physical properties (melting point/hardness/tensile strength) and lack of substitutes, make tungsten critical in industrial, oil & gas, mining and agricultural applications. It is classified as a strategic metal in the US, EU and China. Production and consumption of tungsten is dominated by China, with western world demand growing. Tungsten prices increased strongly during 2011 & have largely held those gains.

Demand is estimated by the International Tungsten Industry Association to grow at 4%pa til 2018.

While Molyhil is principally a tungsten project, the contribution from the contained molybdenum is significant. The grade of material reporting to the processing plant adjusted for molybdenum credits, and after ore sorting, will be equivalent to 0.46% WO, well above the grade of most Western World operating or proposed tungsten mining operations.

 

Enquiries:

 

Mick Billing

+61 (8) 7324 1935

 

Thor Mining PLC

Executive Chairman

Ray Ridge

+61 (8) 7324 1935

 

Thor Mining PLC

CFO/Company Secretary

 

Colin Aaronson/ David Hignell/ Jamie Barklem

+44 (0) 207 383 5100

 

Grant Thornton UK LLP

 

Nominated Adviser

Andrew Monk/

Bhavesh Patel

+44 (0)20 3005 5000

 VSA Capital Limited

Broker

Alex Walters

 

+44 (0) 7771 713608

+44 (0) 207 839 9260

Cadogan PR

Financial PR

Competent Persons Report

The information in this report that relates to the Ore Reserves is prepared by Andrew Vidale who is a Member of The Australasian Institute of Mining and Metallurgy. Andrew Vidale is a full time employee of AVCS and has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" ("The JORC Code 2012 Edition"). Andrew Vidale consents to the inclusion of material within this report by Thor.

 

Molyhil - Table 1

Criteria

Commentary

Mineral Resource estimate for conversion to Ore Reserves

The Ore Reserve estimate is based on the Mineral Resource estimate prepared by

Runge Pincock Minarco (RPM) reported in the October to December 2013 quarterly report. The Mineral Resources are reported inclusive of Ore Reserves.

 

Site visits

A site visit has not been conducted by the Competent Person.

 

The Competent Person is satisfied that the 3D topographic data supplied and descriptions of the site environment and expected operating conditions are adequate for the completion of appropriate mine designs and schedules and for the estimation of Ore Reserves.

 

Study status

Thor completed and published a Definitive Feasibility Study (DFS) in June 2012.  A JORC 2004 compliant Ore Reserve was published in May 2012.

 

This Ore Reserve is an update based on planned changes to ore processing and revised operating and capital cost estimates leading to updated pit optimisation, pit design and mine schedules.

 

Cut-off parameters

 

An NSR cut-off has been determined taking into consideration:

o WO3 price

o Mo price

o Processing cost

o Metallurgical recoveries

o Transport cost

o G&A costs

 

Royalty to Northern Territory government and private entities were not included in the calculation of the NSR

 

Mining factors or assumptions

 

 

The Ore Reserve has been estimated from detailed pit designs which were based on a preferred shell chosen from a range of pit optimisation shells.  The pit optimisation incorporated sensitivity analyses on mining cost, processing cost, revenue, slope angle and geo-metallurgical recovery.

 

The Ore Reserve estimate assumes conventional truck and shovel open pit mining practices, X-Ray ore sorting and conventional flotation and gravity processing practices.

 

Pit design slope parameters were sourced from a report by Pells Sullivan Meynik; "Molyhil, Geotechnical Open Pit Slope Design Aug 2012.  Overall slope angles for pit optimisation were adjusted for the likely impact of ramps - these overall angles aligned well with final pit designs.

 

The resource block model provided by Thor has block dimensions of 1.25m in the east-west direction x 2.5m in the north-south direction x 2.5m in elevation.

 

A mining block model was prepared from the resource block model, the mining model incorporates estimates for mining loss and dilution, geo-metallurgical stage recoveries, costs and revenue.

 

The mining model was regularised to a 5m bench height and a block edge dilution of

0.5m was applied.  Value based ore selectivity analysis assuming a 5m x 5m SMU

was carried out to determine ore boundaries.

The net impact of regularisation, mining dilution and SMU is 103% mass recovery of 1mineralised material, 98% mass recovery of WO3 and Mo, head grade of 96% of in- situ.

 

 

 

 

 

 

 

The proposed pit is developed in two stages.  Minimum dimension of the first stage pit floor is 170m x 65m.  The second stage mining width is typically 60m to 100m with a minimum width of 30m.  The final pit is approximately 150m deep with the final 45m utilising a single lane ramp.  Final pit floor design includes a "goodbye" cut which narrows to between 25m and 35m in width.

 

Metallurgical factors or assumptions

 

Ore processing will consist of crushing, X-Ray sorting for pre-concentration, grinding, flotation and gravity separation.  These technologies are industry standards for the type of deposit.

 

Drilling, bulk sampling and metallurgical test work by Thor has been ongoing since

2005.

 

Metallurgical recoveries were estimated in the block model based on the test work and trial data provided by Thor.  These indicate:

o 15% of ROM mass rejected by ore sorting with a loss of 0.4% WO3 mass and 1.1% Mo mass

o 85.0% recovery of WO3 in mill feed (84.6% of ROM feed)

o 77.8% recovery of Mo in mill feed (77.0% of ROM feed)

 

Copper is a potential penalty element in the Molybdenum concentrate.  Test work indicates the copper grade will not exceed the allowable limit in previous off-take agreements hence no price penalty has been applied.

 

Molybdenum is a potential penalty element in the Scheelite concentrate.  Test work indicates the molybdenum grade is likely to be above the penalty threshold.  Price penalties are applied in; the calculation of NSR, the pit optimisation and the financial model based on estimates from off-take partners.

 

Environmental

Approval for the Mining Management Plan was granted by the Northern Territory Director of Mining and Petroleum Authorisations and Evaluations in 2008 but was let lapse by Thor.

 

The Mining Management Plan was re-submitted in June 2012, Thor are currently awaiting a response.

 

Geological data indicates the waste rock is not likely to be acid consuming, consequently no further studies have been undertaken on waste rock characterisation or selective placement.

 

Infrastructure

Infrastructure for all activities will need to be installed/constructed before the commencement of mining.

 

Site access from the Plenty Highway will require upgrading of an existing road for both transport of construction materials and concentrate shipment.  Agreements are in place with the landholder for use of this road.

 

A community assessment of stakeholders was conducted in 2007.  Stakeholders consulted in identifying opportunities and risks were:

o Central Land Council (CLC)

o Indigenous Coordination Venture

o Indigenous Business and Industry Services

o Alice Springs Town Council

o Mining, Petroleum and Defence Support Group

o Desert Knowledge Australia

o Centre for Appropriate Technology

o Arltarlpilta Community Government Council

o Jinka/Jervois station

An agreement is in place with the CLC to provide indigenous employment opportunities

 

Costs

Full project valuation has been conducted by Thor.  The Competent Person understands that Capital costs have been sourced from suppliers and contractors during the DFS process and since updated by Thor.

 

Operating costs have been based on supplier quotes and extrapolation from Thor and Competent Person experience elsewhere.

 

Project valuation costs include tailings retention.  The DFS included designs for a tailings storage facility (TSF) near the eastern side of ML24429.  The subsequent increase in Ore Reserve and pit size necessitates the placement of waste rock dumps in that area, and it is planned to relocate the TSF immediately to the north of the existing MLs.  The proposed location lies within Thor's exploration lease EL22349.

 

An exchange rate of 0.83 USD/AUD has been used in the pit optimisation and calculation of the NSR.

Royalty to Northern Territory government and Central Land Council have been calculated in the financial model.

 

Revenue factors

 

NSR calculation and pit optimisation used:

o US$408/mtu for WO3

o US$12.76/lb for Mo

 

The WO3 price was determined by discounting the average market prediction of US$458/mtu for 2APT for 2014~2018 sourced from an independent report by Tungsten Market Research Ltd (Jan 2014.  The Mo price was determined by discounting the LME long term prices estimate of 3$16.47/lb.

 

Market assessment

 

Neither tungsten nor molybdenum have potential substitutes for their main application and consumption for both is expected to continue to grow.  Molybdenum is often a secondary product from Cu or Cu/Au mines and production can be readily turned on or off as demand and price dictates.

 

Market predictions for tungsten beyond 2014 are for demand to exceed supply and price to increase.

 

Market predictions for molybdenum beyond 2013 are for demand to increase with global GDP and prices increase beyond 2015

 

Economic

Economic inputs such as foreign exchange rates, royalties, costs, discount rate etc are set by Thor and have been tested in the project valuation model.

 

Project assessment by Thor indicates a very attractive positive net present value and

IRR.

 

Social

Consultation has occurred with the relevant stakeholders, including aboriginal peoples who claim affinity with the land upon which the plant will be located.

 

Tripartite Deed of Agreement has been executed in 2008 between the NT

government, Thor, the Central Land Council and the Arrapere Group.

 

Thor obtained the Aboriginal Areas protection Authority Certificate in March 2012.

 

Classification

The entire Ore Reserve is classified as Probable.

 

Only Indicated Mineral Resources were considered in the calculation of the NSR for the purposes of pit optimisation and Reserves estimation.

 

The Ore Reserve estimate does include minor quantities of Inferred Resources and unclassified mineralisation that have resulted from the formation of an SMU and/or inclusion of edge dilution across the Indicated Resource block boundary.  

 

 

 

 

 

 

 

 

This additional material is <3% of the estimated Reserve mass and contains approximately 1% of the WO3 and Mo.

 

No portion of the Probable Ore Reserves have been derived from Measured

Resources - there are no Mineral Resources of Measured classification.

 

Audits or reviews

 

The Ore Reserves has not been externally audited.

Discussion of relative accuracy/ confidence

 

The pit designs and mine schedule on which the Ore Reserve is based have been prepared to Feasibility Study level with a corresponding level of confidence.

 

The mineralisation at Molyhil comprises two near vertically dipping iron rich skarn lobes in granite host rock.  The defined ore boundaries are, within each lobe, continuous and in the order of 50m wide (east to west) by 100m long (north to south) for the western lobe and 40m wide (east to west) by 80 m long (north to south) for the eastern lobe overall.

 

Minimum mining width across the ore zones rarely approaches the assumed SMU

limit of 5m and is more typically greater than 20m.

 

The external ore boundary is typically at the contact between the skarn and the host granites and thus easily visually identified.  The internal waste boundaries and external boundaries that are within the skarn will require blast hole sampling and/or a field XRF for grade control.

 

Mining modifying factors, pit designs and schedule reflect the scale of the intended equipment and planned operation.

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUWRBRSRABUAR
Date   Source Headline
16th May 20247:00 amRNSDirectorate Change
13th May 20247:00 amRNSEquity Placing & Lifting of ASX Trading Halt
9th May 20247:00 amRNSASX Trading Halt
8th May 202410:32 amRNSRIU Sydney Conference Presentation
30th Apr 20247:00 amRNSQuarterly Activities and Cash Flow Report
24th Apr 20247:00 amRNSCompletion of Stage 1 Earn-In Commitment - Molyhil
6th Mar 20247:00 amRNS3D Model Shows Alford East Copper Mineralisation
5th Mar 20247:00 amRNSHalf-year Report
29th Feb 20247:00 amRNSHigh Grade Uranium and Vanadium Assays Results
30th Jan 20247:00 amRNSQuarterly Activities and Cash Flow Report
25th Jan 20247:00 amRNSAlligator completes Initial Investment in ECL
18th Jan 20247:00 amRNSUranium Update
18th Dec 20237:30 amRNSAlligator Energy Invests into ISR Copper
18th Dec 20237:00 amRNSEnviroCopper Ltd to Acquire Alford West Tenement
11th Dec 20237:00 amRNSCopper Recoveries Advance ISR Assessment
4th Dec 20237:00 amRNSHigh-Grade Uranium Intercepts at Groundhog
30th Nov 202312:00 pmRNSConference Attendance
29th Nov 202310:50 amRNSResult of AGM
22nd Nov 20237:00 amRNSDrilling Program Completed
15th Nov 20237:00 amRNSSignificant Uranium Mineralisation Intercepted
8th Nov 20231:30 pmRNSDrilling starts at Molyhil Tungsten Project
7th Nov 20237:00 amRNSCopper Hosting Troughs Defined by ANT Surveys
3rd Nov 20237:05 amRNSIncreases interest in Alford East Project to 80%
3rd Nov 20237:05 amRNSNotice of AGM
31st Oct 20237:00 amRNSQuarterly Activities and Cash Flow Report
26th Oct 20237:00 amRNSCorporate Presentation
23rd Oct 20237:00 amRNSDirector/PDMR Shareholding
18th Oct 20237:30 amRNSUranium Drilling Commences
3rd Oct 20237:00 amRNSANT Geophysical Surveys Commence
20th Sep 20237:00 amRNSEquity Placing to Accelerate Uranium Drilling
18th Sep 20237:30 amRNSASX Trading Halt
13th Sep 20237:00 amRNSKey Environmental Approvals Granted
4th Sep 20237:00 amRNSFleet Space Technologies Collaboration
23rd Aug 202310:56 amRNSResult of GM & Share Capital Consolidation
17th Aug 20237:00 amRNSUranium Drilling Approvals Granted
4th Aug 20237:00 amRNSProposed Share Consolidation and Notice of GM
31st Jul 20237:00 amRNSQuarterly Activities and Cash Flow Report
27th Jul 20237:00 amRNSUranium Targets Identified
31st May 20237:00 amRNSAirborne Magnetic & Radiometric Surveys Commence
22nd May 20237:00 amRNSShareholder and Investor Event
3rd May 20237:00 amRNSRIU Sydney Conference Attendance
28th Apr 20237:33 amRNSQuarterly Activities and Cash Flow Report
26th Apr 20237:00 amRNSAlford East: High-grade Rare Earth Discovery
24th Apr 20237:00 amRNSPositive Vanadium Assay Results
17th Apr 20237:00 amRNSAlford West Project Survey Results
28th Mar 20237:00 amRNSHolding(s) in Company
20th Mar 20237:31 amRNSDirector/PDMR Shareholding
14th Mar 20237:00 amRNSHalf-year Report
8th Mar 20237:00 amRNSCorporate Presentation
2nd Mar 20237:00 amRNSGeophysics Commences at Alford West Project

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.