Guinea Project Update

4 Mar 2009 07:00

RNS Number : 2638O
West African Diamonds PLC
04 March 2009
 

WEST AFRICAN DIAMONDS PLC

GUINEA UPDATE

Highlights:

 Mine commissioning to commence at Bomboko in March, production April

 A plant to allow bulk sampling of the Droujba kimberlites has been set up and is being commissioned

 A drill rig is on site at Droujba. Drilling to define the size of the kimberlites will commence in March

The board of West African Diamonds plc, the AIM listed diamonds and precious metals explorer and developer (AIM: WAD), is pleased to provide an update on its activities in Guinea. 

Engineering work is completed on our Bomboko alluvial mine located near the Aredor diamond mine. Pre-production testing will commence towards the end of March followed by production in April. The mine will commence operations with a 10 foot Pan Plant capable of treating 7,000 tonnes a month. Initial production will be from a stockpile adjacent to the plant. A 16 foot Pan Plant supported by a 46 tonne excavator will be installed during April. This will enable an increase in production to 18,000 tonnes a month.

A mobile Dense Media Separation (DMS) unit has been installed and commissioned on the Droujba kimberlite licence. A drill rig has arrived and is being commissioned. A drill programme to bulk sample the kimberlites and the geophysical targets identified on the surrounding ground will start within weeks.

James Campbell, Deputy Chairman of West African Diamonds, commented:

"Despite the turmoil in the diamond industry, it is good news that we have been able to build our Bomboko mine on time and within budget - we have taken the asset to the brink of production and look forward to collating our first package of diamonds for sale.

Diamonds are scarce and remain highly desirable in both consumer and industrial markets. Whilst the current lack of credit may reduce prices or even cause a postponement of sales due to the hits taken by the sightholders, we are confident that the long term future for the quality of diamonds from Guinea is bright.

Droujba is a fine prospect. We eagerly await the results of the bulk sampling. With production from Bomboko and a number of attractive development and exploration projects, significant value has been uncovered in a short period. We believe WAD remains an attractive overall package."

Enquiries:

West African Diamonds

www.westafdiamonds.com

John Teeling, Chairman

James Campbell, Deputy Chairman

 

+ 353 1 833 2833

+27 83 457 3724

Blue Oar

Nick Lovering

Toby Gibbs

 

+44 (0)20 7448 4400

College Hill

Paddy Blewer

Nick Elwes

+44 (0) 20 7457 2020

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUOOBRKBRORAR
Date   Source Headline
20th Oct 20105:12 pmRNSHolding(s) in Company
20th Oct 20105:12 pmRNSHolding(s) in Company
18th Oct 20107:00 amRNSBomboko Diamond Mine Progress Report
14th Oct 20104:29 pmRNSHolding(s) in Company
14th Oct 20101:49 pmRNSHolding(s) in Company
14th Oct 20101:45 pmRNSHolding(s) in Company
14th Oct 20107:00 amRNSMandala Diamond Mine Quarterly Progress Update
12th Oct 201011:00 amRNSHolding(s) in Company
12th Oct 20107:00 amRNSDealings by Directors and Significant Shareholders
11th Oct 20101:08 pmRNSResult of General Meeting
22nd Sep 20107:00 amRNSProposed Placing to Raise ?1.9 Million
10th Aug 20107:00 amRNSGRANT OF OPTIONS & ISSUE OF EQUITY
15th Jul 20107:00 amRNSMine Capacity Increased at Guinea Operations
30th Jun 20107:00 amRNSBulk Sampling to Commence on Tongo Kimberlite
25th Jun 20107:00 amRNSInterim Results
24th May 20107:00 amRNSCompletion of Acquisition of Kono Diamond Project
4th May 20107:00 amRNSAcquisition of Kono Diamond Project
20th Apr 20107:00 amRNSChange of registered address
16th Apr 20102:09 pmRNSDirector's Dealing
15th Mar 20107:00 amRNSProgress Update
2nd Mar 20103:42 pmRNSHolding(s) in Company
23rd Feb 20104:31 pmRNSDirector's Dealing
22nd Feb 20107:00 amRNSAIM Admission - First Day of Dealings
19th Feb 201012:36 pmRNSResult of General Meeting
4th Feb 20107:00 amRNSSchedule 1 - Stellar Diamonds plc
27th Jan 20107:30 amRNSRestoration - West African Diamonds plc
27th Jan 20107:30 amRNSProposed Acquisition of Stellar Diamonds
7th Jan 201011:26 amRNSHalf Yearly Report
23rd Nov 200912:00 pmRNSAGM Statement
27th Oct 20093:42 pmRNSHolding(s) in Company
26th Oct 20094:00 pmRNSSuspension - West African Diamonds plc
26th Oct 20094:00 pmRNSMerger between WAD and Stellar Diamonds Ltd
21st Oct 20097:00 amRNSPreliminary Results
16th Oct 20093:50 pmRNSPlant 11 Koidu SL to reopen under new management
16th Sep 20097:00 amRNSDevelopments in Sierra Leone
14th Aug 20099:23 amRNSHolding(s) in Company
12th Aug 200911:18 amRNSHolding(s) in Company
12th Aug 20099:27 amRNSHolding(s) in Company
7th Aug 20092:42 pmRNSDirectorate Change
23rd Jul 20094:00 pmRNSGrant of options
23rd Jul 20097:00 amRNSDirectors and Institutional placing
21st Jul 20097:00 amRNSGuinea Production Update
15th Jun 20097:00 amRNSChange of Name of Nominated Adviser and Broker
8th Jun 20097:00 amRNSGuinea Production & Exploration Update
4th Mar 200911:18 amRNSHolding(s) in Company
4th Mar 20097:00 amRNSGuinea Project Update
24th Feb 200911:13 amRNSIssue of Equity
20th Feb 20094:21 pmRNSDirectorate Change
4th Feb 20092:56 pmRNSDirectorate Change
29th Jan 200911:34 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.