Trading Statement

9 Jan 2013 07:00

RNS Number : 1192V
Rurelec PLC
09 January 2013
 



9th January 2013

Rurelec PLC

("Rurelec" or "the Company")

 

Trading Update

 

The Directors of Rurelec PLC (AIM: RUR), the electricity utility focused on power generation in Latin America, are pleased to announce that the Company's projects are progressing well and provide the following update:

 

Chile

As announced on 4th October 2012, Rurelec's Termonor subsidiary has received the final government land zoning authorisations in Arica. These are the final precursor to construction, which is expected to commence in February 2013. Termonor has signed an Engineering, Procurement and Construction ("EPC") contract with Energy Contact of Canada, its prime contractor, for the refurbishment and installation of a General Electric 6B gas turbine. The capital cost of the plant is US$16.5 million, with an initial commitment of US$6 million pending initiation of the civil works. The current timetable calls for the turbine to be delivered to the Port of Arica in February, at which time the instruction to commence construction is expected to be issued, with a view to commercial operation by the end of 2013. Agrosonda Chile is the principal sub-contractor.

 

In order to maintain the momentum of the project, in December 2012 Rurelec acquired the remaining 50 per cent of Termonor. It therefore currently holds 100 per cent of the issued share capital of the project company and will continue to do so until its original project partners, Invener, complete their own recapitalisation arrangements with local investors.

 

It remains Rurelec's intention to own, in partnership with Chilean investors, an eventual fifty per cent interest in Termonor. Northern Chile is regarded by the Rurelec Board as the most attractive power market in Latin America, and the Arica project's economics have improved considerably over the last year. As a result of a sharp increase in forecast electricity demand in the very north of Chile, the Arica power plant capacity is expected to be increased in due course from the initial configuration of 40 MW, rising to between 80 and 120 MW in a design similar to Rurelec's Comodoro Rivadavia plant in Argentina which uses the same 6B gas turbine as Arica.

 

The Directors are also delighted to announce that the Company has agreed terms with Independent Power Corporation PLC ("IPC") to acquire its 50 per cent interest of Central Illapa SA, a Chilean project company developing a 250 MW open cycle gas fired peaking plant in Mejillones, one of the key power hubs on the SING system of the Chilean power grid. Central Illapa has also been shortlisted by an international mining group in a tender to supply 500 MW of power to their operations in northern Chile. If awarded the power purchase agreement ("PPA"), Rurelec would work with substantial industry partners to construct, own and operate this high efficiency liquefied natural gas ("LNG") fired combined cycle gas turbine ("CCGT") plant operating in tandem with the 250 MW Illapa peaking plant. Rurelec and IPC have together been short-listed for a further 500 MW CCGT project to be constructed in northern Chile also to run on LNG with capacity to be contracted to another mining group. The PPA proposals are scheduled to be adjudicated in the second or third quarters of 2013.

 

Rurelec is acquiring the shares in Central Illapa for zero premium and refunding a portion of its third party project costs to date. IPC will continue to provide services to augment Rurelec's development efforts for which it will be reimbursed at cost. In addition, at financial close of each project, Rurelec will pay IPC development fees. The level of fee for each of the projects has been agreed following an external appraisal of relevant fee scales commissioned by the Independent Directors of Rurelec.

 

It remains Rurelec's target to own 50 per cent of over 1,250 MW of new Clean Tech generation capacity in Chile in the coming years and to obtain a quotation on the Santiago Stock Exchange.

 

 

Peru

 

In 2012 Rurelec acquired its first projects in hydro-electric power generation in Peru with the acquisition of the 255 MW run-of-river Santa Rita project and the portfolio of small hydro projects which is owned by Rurelec's subsidiary, Cascade Hydro Limited ("Cascade"). Canchayllo, the first Cascade project, has secured a US$7.2 million financing agreement with IIC, a financing arm of the Inter-American Development Bank. Construction of the project has now begun and the plant size has been increased to just over 5 MW at a total cost of US$11 million. Mechanical completion is now expected at the end of 2013 with an in service date of early 2014.

 

The financing of the Canchayllo project has acted as the catalyst for a substantial private equity capital raising effort for Cascade which is expected to close at the end of Q1 2013. The increase in capital will dilute Rurelec's shareholding below the current 50 per cent interest of Cascade, a company with a strong management team that is expected to build up a substantial portfolio of hydro plants in Peru.

 

 

Argentina

 

The Energia del Sur plant in Commodoro Rivadavia continues to trade as expected. The plant is performing well at the operating level though it continues to suffer the impact of increased costs as a result of inflation.

 

 

Bolivia

 

The Guaracachi arbitration process remains on course and the timetable for the hearing at the Permanent Court of Arbitration ("the PCA") in The Hague is still set to commence in April of this year. The parties' filings may be viewed at the PCA website http://www.pca-cpa.org/, in accordance with the agreement on full transparency reached with Bolivia's Attorney General.

 

 

 

 

Bangladesh

 

While Rurelec is focused on Latin America, the Company has nonetheless sought to capitalise on its track record of building and owning CCGT power plants at a time when other companies put their expansion plans on hold as a result of the difficulties arising from the global banking crisis. Rurelec has successfully used its experience and skills in operating thermal plants in Argentina and Bolivia to sponsor projects outside of the Americas. As a result, a Rurelec sponsored project of 108 MW in Chittagong in partnership with Energypac Confidence Power Ventures (ECVP) has recently achieved financial close with a group of prominent local Bangladeshi banks supported by regional multilaterals. The plant is now under construction and is expected to achieve mechanical completion in August.

 

Rurelec is hoping to develop a follow-on CCGT project of some 400 to 500 MW in Bangladesh operating on LNG as a clone of the two LNG projects which it is now pursuing in Chile based on the original engineering and feasibility work completed by IPC.

 

 

 

Commenting on the trading update, Peter Earl, CEO of Rurelec said:

 

"Our decision to focus on Chile and Peru comes at a time when both countries urgently need new generation capacity and when the regional mining companies are looking for reliable and experienced partners to meet the energy needs of their operations.

 

"These new projects are intended to replace the 540MW of generation capacity lost in May 2010 when Bolivia nationalised our subsidiary, Guaracachi. This expansion, coupled with the conclusion of the Bolivian arbitration process, should make 2013 a memorable year for Rurelec." 

 

For further information please contact:

 

Peter Earl, CEO, Rurelec PLC

 

Ana Ribeiro, Head of Communications

www.rurelec.com

 

Tel: 020 7793 5610

Paul Shackleton, Daniel Stewart & Company Plc

 

Tel: 020 7776 6550

Halimah Hussain/Jon Belliss, XCAP Securities

Tel: 020 77101 7070

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTUGUMAGUPWGBR
Date   Source Headline
31st May 20127:00 amRNSUnaudited Preliminary Results
20th Apr 20127:00 amRNSFurther Hydropower Acquisition in Peru
4th Apr 20127:00 amRNSAdoption of 2012 Employee Share Option Plan
2nd Mar 20127:18 amRNSSubmits Bolivian Claim of US$142 million
5th Jan 20122:10 pmRNSExpansion in to Chile with 38 MW Project in Arica
12th Dec 20117:00 amRNSHydropower Expansion into Peru
28th Nov 20117:00 amRNSUpdate on Guaracachi Arbitration Process
30th Sep 20112:58 pmRNSDirector/PDMR Shareholding
8th Sep 20117:43 amRNSHalf Yearly Report
5th Sep 20117:00 amRNSBangladesh power project
14th Jul 20117:00 amRNSChange of Adviser
30th Jun 201111:52 amRNSResult of AGM
14th Jun 20112:55 pmRNSDirector/PDMR Shareholding
8th Jun 201111:38 amRNSNotice of AGM
8th Jun 20117:00 amRNSFinal Results
10th May 201110:11 amRNSAppointment of Non-Executive Director
5th Apr 20112:38 pmRNSDirector Resignation
5th Apr 201111:30 amRNSHolding(s) in Company
31st Mar 20117:00 amRNSTotal Voting Rights
28th Mar 201111:48 amRNSReplacement General Meeting
28th Mar 201111:27 amRNSGeneral Meeting
11th Mar 20113:10 pmRNSPosting Of Circular
23rd Feb 20112:38 pmRNSDirectorate Change
21st Dec 20105:02 pmRNSHolding(s) in Company
9th Dec 201010:45 amRNSDirector/PDMR Shareholding
1st Dec 20103:04 pmRNSFiling of Arbitration Claim
16th Nov 201010:00 amRNSDirector/PDMR Shareholding
12th Nov 20102:26 pmRNSNotice of Arbitration Claim of Compensation
21st Oct 20102:59 pmRNSNotifiable Interest
21st Oct 20102:59 pmRNSNotifiable Interest
29th Sep 20104:03 pmRNSHalf Yearly Report
28th Sep 20104:52 pmRNSHolding(s) in Company
16th Sep 20109:30 amRNSHolding(s) in Company
14th Sep 20101:06 pmRNSPlacing - Replacement announcement
14th Sep 201010:42 amRNSRurelec Placing of 4.25 Million New Ordinary Share
26th Aug 201010:14 amRNSArgentina of Energia del Sur ("EdS") Contract
13th Aug 20109:16 amRNSVariation to Terms of ?2.5m Convertible Loan Note
10th Aug 201012:06 pmRNSHolding(s) in Company
28th Jul 20101:42 pmRNSHolding(s) in Company
22nd Jul 20104:54 pmRNSHolding(s) in Company
1st Jul 20107:59 amRNSResult of AGM
17th Jun 20103:02 pmRNSDirector/PDMR Shareholding
17th Jun 20102:59 pmRNSTrading Update
14th Jun 20104:02 pmRNSDirectorate Change
8th Jun 201011:33 amRNSNotice of AGM
3rd Jun 20107:00 amRNSFinal Results
18th May 201012:02 pmRNSPlacing of 11 Million New Ordinary Shares
13th May 20103:28 pmRNSInstigation of Arbitration Process
4th May 20107:00 amRNSNationalisation of Controlling Stake in Guaracachi
19th Apr 20107:00 amRNSImportant Developments

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.