Diablito Project Update

4 Mar 2005 07:00

Vane Minerals PLC04 March 2005 VANE Minerals plc Full Production Expected At Diablito Three Months Ahead Of Schedule Vane Minerals ("VANE" or "the Company") announces that it has signed anagreement with a mining contractor to develop its most advanced project,Diablito, a high grade gold/silver deposit located in west-central Mexico. VANE's wholly owned subsidiary Minerales Vane SA de CV has signed the agreementwith MGA Constratista Minera SA de CV in San Luis Potosi, Mexico, stating thatwork at the Company's Diablito property will commence in 15 days. The contractor had sent the required machinery to the property, ahead of thesigning of the contract, and so work should commence on time and full productionwill be achieved three months ahead of schedule. Following the development plan that VANE has created, Diablito is expected toproduce ore within three weeks of the work commencing. The Company hadoriginally planned to begin at a lower rate and ramp up production to 50 tonsper day over a three month period. However, the new development plan is expectedto allow the mine to start producing at the full production rate of 50 tons perday. At this target rate, VANE has estimated an annual pre tax profit from Diablitoof US$3m, or US$250,000 per month, with a mine life of seven years given thepresent resource calculation. As previously announced on 25th October 2004, thevein is open at depth, and an infill drilling programme is planned in order toextend the resource. Michael Spriggs, Chairman of VANE commented, "We are very pleased with thisprogress at Diablito, and delighted to be achieving full production quicker thanpreviously expected. With the cash flow, we are well on our way to achievingVANE's objective of becoming a self-funding exploration company, thereforelimiting the downside to our shareholders." Enquiries: VANE Minerals plc Seymour Pierce Limited Parkgreen CommunicationsMatthew Idiens Sarah Wharry Justine Howarth / Cathy Malins020 7667 6322 020 7107 8000 020 7493 3713 This information is provided by RNS The company news service from the London Stock Exchange
Date   Source Headline
3rd Aug 202012:51 pmRNSChange of Name to Zephyr Energy plc & website
29th Jul 20203:17 pmRNSResult of AGM
30th Jun 20207:00 amRNSFinal Results and notice of AGM
8th Jun 20204:30 pmRNSHolding(s) in Company
29th May 20207:00 amRNSGrant of options
5th May 20204:20 pmRNSHolding(s) in Company
1st May 20207:00 amRNSOperations and Strategy Update
10th Feb 20207:00 amRNSUpdate on restructuring of the Paradox project
10th Feb 20207:00 amRNSUpdate on McCoy Lease Working Interest Acquisition
31st Dec 20191:00 pmRNSTotal Voting Rights
3rd Dec 201912:27 pmRNSIssue of Equity and change to TVR
29th Nov 20195:00 pmRNSTotal Voting Rights
22nd Nov 20194:52 pmRNSHolding(s) in Company
21st Nov 201912:43 pmRNSResult of General Meeting and change to TVR
14th Nov 20192:10 pmRNSHolding(s) in Company
8th Nov 20194:12 pmRNSHolding(s) in Company
4th Nov 20192:16 pmRNSDirector/PDMR shareholding
4th Nov 20197:05 amRNSIssue of equity and notice of general meeting
4th Nov 20197:00 amRNSProposed Acquisition-McCoy Interest & Fundraising
14th Oct 20197:00 amRNSRestructuring of the Paradox project
30th Sep 20197:00 amRNSHalf-year Report
3rd Sep 20197:00 amRNSDirectorate Changes and Board Restructuring
2nd Sep 201910:59 amRNSHolding(s) in Company
30th Aug 20195:00 pmRNSTotal Voting Rights
22nd Aug 20197:00 amRNSIssue of equity and change to total voting rights
30th Jul 201912:46 pmRNSResult of AGM and update on Board composition
10th Jul 20193:01 pmRNSHolding(s) in Company
28th Jun 20197:00 amRNSBoard appointment and update
28th Jun 20197:00 amRNSFinal Results
27th Jun 20197:00 amRNSNotice of Annual Results
3rd Jun 20197:00 amRNSTotal Voting Rights
24th May 20197:00 amRNSSubscription completion, board appointment & TVR
20th May 20197:00 amRNSIssue of equity and Board Changes
30th Apr 20197:00 amRNSUpdated Corporate Presentation
23rd Apr 20197:00 amRNSDirectorate Change
12th Apr 20193:40 pmRNSHolding(s) in Company
12th Apr 20197:00 amRNSDirector/PDMR Shareholding
11th Apr 20197:00 amRNSIssue of equity and Board Changes
28th Mar 20197:00 amRNSUpdate & Proposed Board Changes
26th Mar 20199:41 amRNSHolding in Company - Correction
12th Mar 20194:17 pmRNSHolding(s) in Company
5th Mar 20196:09 pmRNSHolding(s) in Company
5th Mar 20199:12 amRNSHolding(s) in Company
11th Jan 20197:00 amRNSAcquisition of additional acreage in Paradox Basin
7th Jan 20197:00 amRNSSchlumberger Study Results
6th Dec 20187:00 amRNSOperations Update
27th Nov 20187:00 amRNSDatabase Agreement & North Wash Vanadium update
1st Nov 20187:00 amRNSBLM Approval for Permit to Drill GV 22-1 well
3rd Oct 20187:00 amRNSHolding(s) in Company
25th Sep 20187:00 amRNSHalf-year Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.