Revised CPR and Corporate Update

20 Apr 2012 07:00

RNS Number : 7231B
Rockhopper Exploration plc
20 April 2012
 

Embargoed: 0700hrs 20 April 2012

 

Rockhopper Exploration plc

("Rockhopper" or the "Company")

 

Revised CPR and Corporate Update

 

Rockhopper Exploration, the North Falkland Basin oil and gas company, is pleased to announce the publication of a Competent Person's Report ("CPR") prepared by Gaffney, Cline & Associates ("GCA").

 

CPR highlights

 

·; 355.6 MMbbls net to Rockhopper 2C contingent oil resources attributed to Sea Lion and adjacent discoveries

 

·; Sea Lion and adjacent discoveries estimated to have net to Rockhopper 2C risked NPV10 of US$ 4.1 billion and an unrisked NPV10 of US$ 4.7 billion

Resource and Economic Evaluation

 

The new CPR assigns a 90% chance of the Sea Lion field being progressed to successful development with the discoveries adjacent to Sea Lion assigned a 75% chance of development.

 

The probabilistic 1C, 2C and 3C resource numbers are based on low, best and high estimates of STOIIP of 0.65, 1.07 and 1.56 billion barrels respectively for the Sea Lion field. GCA has also indicated a deterministic best estimate STOIIP for the Sea Lion field of 1.3 billion barrels. The CPR also indicates significant additional prospectivity on licence PL032.

 

The new CPR contains the following table of resources net to Rockhopper. In arriving at the numbers below GCA used a probabilistic analysis with recovery factors ranging from 20 to 40 %.

 

Net Contingent Resources (MMbbls)

1C

2C

3C

Sea Lion

194.7

307.4

446.3

Casper

13.6

20.4

28.4

Casper South

15.1

24.3

36.0

B15

0.5

0.7

1.0

SL05

1.7

2.8

4.2

Total

225.6

355.6

515.9

 

The table below, extracted from the CPR, shows the Sea Lion risked and unrisked post tax net present value net to Rockhopper using a US$ 3/bbl discount to GCA's internal Brent oil pricing scenario and a 10 per cent discount rate.

 

Risked

Unrisked

1C

US$ 1,471 MM

US$ 1,635 MM

2C

US$ 3,512 MM

US$ 3,902 MM

3C

US$ 6,240 MM

US$ 6,993 MM

 

Using the same assumptions the discoveries adjacent to Sea Lion are deemed to have risked and unrisked post tax net present value net to Rockhopper of:

 

Risked

Unrisked

2C

US$ 615 MM

US$ 827 MM

 

Accordingly, Sea Lion and adjacent discoveries are estimated to have net to Rockhopper 2C risked NPV10 of US$ 4.1 billion and an unrisked NPV10 of US$ 4.7 billion

 

Field Development

 

The CPR also reports on a development concept for the Sea Lion field using a Floating Production Storage and Offloading vessel ("FPSO"). The principal assumptions of the development conceptinclude first oil being achieved at the start of 2016, with a plateau production rate 70,000 barrels per day for the first three years (based on the 2C scenario) and life-of-field development costs of $4.8 billion, based on a purchased new-build FPSO and inclusion of contingency. A breakdown of GCA's Capex is set out in the table below:

 

Component

Gross CapitalCosts US$ MM

Comment

Drilling

2,369

34 wells

FPSO Vessel

294

Market driven, subject to variation

Topside Facilities

522

Subsea Facilities

320

Flowlines

481

Mobilisation

100

Project Management, Insurance, Owners Costs

246

Contingency

493

(on Facilities and Subsea costs)

Total CAPEX

4,825

 

GCA has not provided an estimate of capital cost to achieve first oil production, however the Company's internal calculation of cost to first oil remains at approximately US$2 billion. This estimate is based on the Company's planned development of Sea Lion via a leased FPSO scenario, rather than the purchased new-build scenario assumed in GCA's costing, and a phased drilling programme.

 

The full CPR is available on the Company's website at www.rockhopperexploration.co.uk

 

Corporate Update

 

As previously announced the Company has prepared a data room to enable potential industry partners and debt providers access to the Sea Lion data. Collection and analysis of the field data is now complete and interested parties are actively reviewing the available information.

 

The Falkland Islands Government has recently clarified the position around the submission date for the Final Development Plan ("FDP") for the Sea Lion development. Whilst the licence issued to the Company states that a plan is to be submitted within three years of spudding the discovery well, the 2000 Model Clauses allow for five years if appraisal work has been undertaken. The Falkland Islands Government has therefore recently confirmed the final submission date for an FDP on Sea Lion is 15 April 2015. This does not change the Company's plans to develop Sea Lion as soon as practically possible.

 

Sam Moody, Chief Executive of Rockhopper, commented:

 

"We are delighted by the progression that the publication of today's CPR demonstrates as we continue to move forward our development for Sea Lion and nearby discoveries. We are particularly pleased by the results of the CPR due to the standing of consultants Gaffney, Cline & Associates Ltd and its reputation for thoroughness in the analysis of reservoir data and field development planning. The study has strongly reinforced our view of the potential of Sea Lion for commercial development."

 

Enquiries:

 

Rockhopper Exploration plc

Sam Moody - Chief Executive

Tel. +44 (0)20 7920 2340 (via M: Communications)

 

M: Communications

Patrick d'Ancona or Ben Simons

Tel. +44 (0)20 7920 2340

 

Canaccord Genuity Limited

Robert Finlay / Henry Fitzgerald-O'Connor

Tel. +44 (0) 20 7050 6500

 

Glossary of technical terms

 

Contingent Resources

those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations, but the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies. Contingent Resources are further categorised as 1C, 2C and 3C in accordance with the level of certainly associated with the estimates and may be sub-classified based on project maturity and/or characterised by their economic status.

 

Deterministic Method

The deterministic approach, which is the one most commonly employed worldwide, involves the selection of a single value for each parameter in the reserves calculation.

The discrete value for each parameter is selected based on the estimator's

determination of the value that is most appropriate for the corresponding reserves category.

 

MM

 

millions

MMbbls

 

million barrels

NPV10

net present value at a 10 per cent discount rate

 

Probabilistic Method

Probabilistic analysis involves describing the full range of possible values for each unknown parameter. This approach typically consists of employing computer

software to perform repetitive calculations to generate the full range of possible outcomes and their associated probability of occurrence.

 

STOIIP

 

Stock tank oil initially in place

 

Notes to Editors

 

Rockhopper was established in February 2004 with a strategy to invest in and carry out an offshore oil exploration programme to the north of the Falkland Islands. The Company floated on AIM in August 2005 and holds a 100 per cent. interest in four offshore production licences: PL023, PL024, PL032 and PL033 which cover approximately 3,800 sq. km. Rockhopper also farmed in (7.5% working interest) to licences PL003 and PL004, which are operated by Desire Petroleum. In addition to the original farm-in, and in consideration for drilling one well on the north-western acreage of licence PL004, known as Area 1, which contains the extension to the Sea Lion field as well as the Beverley, Casper and Casper South features, Rockhopper farmed-in with operatorship and an aggregate 60% interest in Area 1.

 

An extensive work programme has been carried out over a number of years on the licences operated by Rockhopper. This has included 2D and 3D Seismic and Controlled Source Electromagnetic Mapping (CSEM). In February 2010, the Ocean Guardian drilling rig arrived in Falkland waters to carry out a multi-well drilling campaign. Rockhopper drilled an exploration well on its Sea Lion prospect during April and May 2010, the result of which was the first oil discovery and Contingent Oil Resource in the North Falkland Basin. The Sea Lion discovery was successfully tested during September 2010 and June 2011 and was the first oil to flow to surface in Falkland Islands waters. Rockhopper's drilling campaign lasted from 16 April 2010 to 8 January 2012 and resulted in seven successful wells of the ten drilled, with three oil discoveries, three gas discoveries, multiple successful Sea Lion appraisal wells and a successful appraisal well on Casper.

 

Rockhopper Exploration plc www.rockhopperexploration.co.uk

 

NB: This statement has been approved by the Company's geological staff who include David Bodecott (Exploration Director), who is a Member of Petroleum Exploration Society of Great Britain (PESGB) and the American Association of Petroleum Geologists (AAPG) with over 30 years of experience in petroleum exploration and management, for the purpose of the Guidance Note for Mining, Oil and Gas Companies issued by the London Stock Exchange in respect of AIM companies, which outline standards of disclosure for mineral projects.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLILMTTMBMBTJT
Date   Source Headline
29th May 20154:20 pmRNSTotal Voting Rights
28th May 20157:00 amRNSIsobel Deep Oil Discovery
20th May 20157:00 amRNSResult of AGM
19th May 20157:00 amRNSOperations Update - Isobel Deep & Mediterranean
12th May 20157:00 amRNSOperations Update
6th May 20152:52 pmRNSTotal Voting Rights
28th Apr 20153:30 pmRNSHolding(s) in Company
24th Apr 20154:30 pmRNSNotice of AGM
24th Apr 201512:00 pmRNS14/20-1 Operational Update
21st Apr 20155:13 pmRNSHolding(s) in Company
21st Apr 20155:12 pmRNSHolding(s) in Company
13th Apr 20154:15 pmRNSDirector/PDMR Shareholding
10th Apr 20153:15 pmRNSAnnual Financial Report
9th Apr 20157:00 amRNS14/20-1 Well Spud 'Isobel Deep'
9th Apr 20157:00 amRNSFalkland Island CGT liability deferment
9th Apr 20157:00 amRNSFinal Results
8th Apr 20154:10 pmRNSHolding(s) in Company
2nd Apr 20157:00 amRNS14/15b-5 Well Update
31st Mar 20155:28 pmRNSBlocklisting Interim Update
31st Mar 20155:27 pmRNSDirector Dealing and Total Voting Rights
10th Mar 20159:51 amRNSHolding(s) in Company
6th Mar 20157:45 amRNS14/15-5 Well Spud and Drilling Order Update
3rd Mar 20151:24 pmRNSHolding(s) in Company
3rd Mar 20157:00 amRNSUpdate on Drilling Rig and Analyst Presentation
3rd Mar 20157:00 amRNSUpdate on Drilling Rig and Analyst Presentation
27th Feb 20154:50 pmRNSTotal Voting Rights
24th Feb 20155:41 pmRNSHolding(s) in Company
24th Feb 20155:39 pmRNSHolding(s) in Company
6th Feb 20153:56 pmRNSHolding(s) in Company
3rd Feb 20153:29 pmRNSBlocklisting Interim Review
3rd Feb 20152:42 pmRNSHolding(s) in Company
2nd Feb 20157:00 amRNSMobilisation of drilling rig
29th Jan 20157:00 amRNSDirectors Dealing and Total Voting Rights
27th Jan 20154:27 pmRNSHolding(s) in Company
19th Jan 20156:27 pmRNSHolding(s) in Company
19th Jan 20155:27 pmRNSHolding(s) in Company
16th Jan 201511:14 amRNSHolding(s) in Company
9th Jan 20158:45 amRNSHolding(s) in Company
5th Jan 20157:00 amRNSCroatian Licence Award
2nd Jan 20156:11 pmRNSDirectors Dealing and Total Voting Rights
23rd Dec 20141:47 pmRNSHolding(s) in Company
22nd Dec 20144:27 pmRNSHolding(s) in Company
22nd Dec 20144:26 pmRNSHolding(s) in Company
19th Dec 201411:35 amRNSDirector Dealings
18th Dec 20142:21 pmRNSHolding(s) in Company
16th Dec 20147:00 amRNSHalf Yearly Report
12th Dec 20147:00 amRNSMediterranean Operations Update
10th Dec 20142:15 pmRNSHolding(s) in Company
3rd Dec 20143:23 pmRNSHolding(s) in Company
1st Dec 20141:07 pmRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.