Barruecopardo Project Update

26 Feb 2019 07:00

RNS Number : 0650R
Ormonde Mining PLC
26 February 2019
 

26 February 2019

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Ore Mining and Processing Underway at Barruecopardo

 

The Board of Ormonde ("the Board") is pleased to provide an update on the construction and commissioning of the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where the Company holds a 30% interest.

 

Open pit mining of surface tungsten ore zones commenced in January, and the crush and screen plant has been commissioned using ore to produce the fine ore stockpile for feeding into the process plant. The commissioning stages of the process plant have been advancing and the first ore has now been introduced to the process plant. This activity will continue during the following weeks, including producing tungsten concentrates, which will lead on to a progressive transition from the commissioning phase into the gradual ramp-up of production at Barruecopardo.

 

Key recent progress includes:

 

· Crush and screen plant and water treatment plant commissioning completed and handed over to operating team;

· Process plant:

o Installation of equipment and supporting structures materially complete, with some de-snagging ongoing;

o Dry commissioning and water commissioning both complete in most areas;

o Following some slippage in the schedule, commissioning has now progressed to commencement of ore processing and this "hot commissioning" will continue during the remainder of February and into March.

· Initial open pit mining operations underway in the north starter pit, and waste stripping of the east wall of the historic open pit also in progress;

· Installation of pumps ongoing in the water dams;

· Recent site photos can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"Activities at Barruecopardo have been advancing well, with mining of ore for the process plant commencing in early January, and plant dry and wet commissioning mostly complete, with ore now being introduced to the process plant.

 

"These are significant milestones for the Project, and we look forward to seeing ore commissioning progress during the weeks ahead and the successful transition into the Project's production phase."

 

 

 

Enquiries:

 

Ormonde Mining plc

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

Tel: +353 (0)1 8014184

 

Davy (Nomad, Euronext Growth Advisor and Joint Broker)

John Frain / Barry Murphy

Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat 

Tel: +44 (0)20 3 470 0470

 

Capital M Consultants

Simon Rothschild

Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock

Tel: +353 (0)1 4980300

Mob: +353(0)872335923

 

 

Notes:

 

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project during development, commissioning and operation, and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement which provides for certain rights and obligations for each party.

 

 For more information, visit www.ormondemining.com 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLPGUBPPUPBGMA
Date   Source Headline
23rd Jun 20117:00 amRNSDrilling Update
20th Jun 20112:01 pmRNSAnnual Financial Report
24th May 20117:00 amRNSFinal Results
16th May 20117:00 amRNSNotification of Interest
12th May 20117:00 amRNSNotification of Interest
11th May 20112:44 pmRNSIssue of Equity
10th May 20117:00 amRNSEnterprise Securities Market Notice
9th May 201112:50 pmRNSNotification of Interest
9th May 20117:00 amRNSEngineering Firm Appointed
4th May 20117:00 amRNSPlacing
14th Apr 20117:00 amRNSBarruecopardo Drilling Results
4th Apr 20117:00 amRNSAcquisition
14th Mar 20117:00 amRNSSalamanca-Zamora Gold Exploration Update
14th Mar 20117:00 amRNSJoint Venture with Ormonde Mining plc
2nd Mar 20117:00 amRNSTungsten Update
13th Jan 20117:00 amRNSTungsten Permitting
13th Dec 20101:06 pmRNSHolding in Company
13th Dec 201010:36 amRNSHolding in Company
10th Dec 20102:34 pmRNSNotification of Interest
11th Nov 20107:00 amRNSTungsten Progress
13th Oct 20107:00 amRNSOrmonde Presentation
11th Oct 20109:53 amRNSHolding(s) in Company
6th Oct 20107:00 amRNSEnterprise Securities Market Notice
5th Oct 20102:09 pmRNSGranting of Options
30th Sep 20107:00 amRNSIssue of Equity
28th Sep 20107:00 amRNSHalf Yearly Report
27th Sep 20104:41 pmRNSSecond Price Monitoring Extn
27th Sep 20104:35 pmRNSPrice Monitoring Extension
16th Sep 20107:00 amRNSScott Wilson Study
9th Sep 20107:00 amRNSLa Zarza Update
7th Sep 20102:56 pmRNSShareholder Notification
27th Aug 201012:02 pmRNSNotification of Major Interest
26th Aug 20103:17 pmRNSNotification of Major Interest
3rd Aug 20107:01 amRNSSalamanca Gold Report
3rd Aug 20107:00 amRNSAppointment of Joint AIM Broker
28th Jul 20107:00 amRNSTungsten Review
19th Jul 201012:01 pmRNSNotification of Major Interest
16th Jul 20101:40 pmRNSEnterprise Securities Market Notice - Replacement
16th Jul 20101:20 pmRNSEnterprise Securities Market Notice
2nd Jul 20107:00 amRNSResignation of Director
30th Jun 20107:00 amRNSIssue of Equity
28th May 20102:56 pmRNSAGM Result
27th May 20107:00 amRNSMajor Tungsten Upgrade
6th May 201010:14 amRNSAnnual Financial Report
27th Apr 20107:00 amRNSFinal Results
12th Apr 20107:00 amRNSTharsis Option Agreement
19th Feb 20107:00 amRNSLa Zarza Update
27th Oct 20097:00 amRNSAntofagasta Joint Venture
28th Sep 20097:00 amRNSInterim Results
22nd Sep 200911:17 amRNSShareholder Notification

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.