Trading Update

28 Feb 2013 07:00

RNS Number : 8438Y
OPG Power Ventures plc
28 February 2013
 



28 February 2013

 

OPG Power Ventures plc

("OPG" or the "Company")

 

Trading update

 

Operating assets performing ahead of expectations and Chennai III on track for Q2 2013

 

OPG Power, the developer and operator of power stations in India, presents the following trading update for the three months ended 31 December 2012.

 

Operations summary - quarter ended

 

Plant

Generation

(Mn Units)

 

Ave tariff realisation

(Rs/kWh)

Plant Load Factor(%)

based on name-plate capacity

 

31/12/12

30/09/12

31/12/11

31/12/12

30/09/12

31/12/11

31/12/12

30/09/12

31/12/11

77MW C I

155

171

158

5.55

5.69

5.09

91

100

93

77MW C II

146

n/a

n/a

5.51

n/a

n/a

96

n/a

n/a

 

77 MW Chennai I performing strongly

The Company's 77 MW Chennai I plant achieved an average Plant Load Factor (PLF)of 91% during the three months ended 31 December 2012.This was in line with expectations and, with load factors in January 2013 being marginally higher than name-plate capacity, we continue to remain confident of this unit achieving a PLF of 90% for FY2013 as a whole.

 

77 MW Chennai II - stronger than expected ramp up to date

In addition 77 MW Chennai II achieved a PLF of 96% during the three months ended 31 December 2012, its commercial operations having commenced in early October. The ramp up of this unit since its commissioning has been stronger than we had anticipated, with load factors in January 2013 being slightly higher than name-plate capacity. Accordingly, we have updated our expectation from this unit to a PLF of just over 90% for FY2013, up from our previous expectation of 85%.

 

Along with the gas and waste heat plants from which the financial contribution remains negligible, the Group's commercial operating capacity remains at 190 MW.

 

Average tariff

In line with our flexible revenue model, our present strategy is to sell most of our power from Chennai I and II to TANGEDCO (Tamil Nadu state utility) at Rs5.50/kWh on a term contract ending May 2013 and accordingly we expect the average tariff for FY2013 to be in the range Rs5.50-5.55/kWh, compared with Rs4.93/kWh actually achieved in the prior year. Transmission charges are not payable on power sold to TANGEDCO.

 

Costs

Landed cost of imported coal declined by approximately 3% compared with the immediately preceding quarter principally on account of the prevailing term contract with our Indonesian coal supplier.

 

80 MW Chennai III - on track to commission in Q2 2013

The Company's 80 MW Chennai III for which equity finance was derived from internal cash flows is approaching completion. Hydro testing has been completed successfully as has boxing up of the turbine. Photographs of the nearly completed unit and the associated coal handling facilities have been uploaded to the Company's website. The unit is expected to enter our rigorous test phase before the end of May beyond which commissioning trials would commence. The plant is on track to commission in the next quarter.

 

160 MW Chennai IV

The 160 MW Chennai IV is in the advanced civil works phase of construction. As the floor plate of the plant is adjoined to the existing plant, infrastructure such as roads and access ways are shared with Chennai I,II and III and are thus already in place. The next key step is for major equipment deliveries to commence. The plant remains on track for commissioning in 2014.

 

2x150 MW Gujarat

The 2x150 MW Gujarat project is progressing well with boiler and chimney foundations complete and boiler erection, and electrical works commenced. One of the boiler drums is expected to be lifted and installed in the next few weeks, a significant milestone for the project as it facilitates the construction of the balance of the plant to commence. Chimney construction has already commenced. The project remains on track for commissioning in the second half of calendar year 2014.

 

Supply and demand fundamentals continue to be supportive

With the financial restructuring of many state utility companies bank lending to the Indian electricity sector is resuming gradually. Although official statistics indicate the pace of national GDP growth has slowed to over 5%, this is considerably in excess of most of the developed world and per capita electricity consumption in India remains comparatively low. In addition, economic reforms continue as part of government policy. Accordingly, we continue to believe that even with a weak rupee and high interest rates, strong supply/demand fundamentals remain in place.

 

About OPG

OPG is operating and developing power projects in India under the group captive model with 190 MW in operations and a further 552 MW under development. In the six months ended 30 September 2012, the Group's revenues were £17.8m and profit before tax was £2.5m.

 

 

For further information, please visit www.opgpower.com or contact:

 

OPG Power Ventures PLC

+91 (0) 44 429 11 211

Arvind Gupta

 

V Narayan Swami

Ajay Paliwal

 

+44 (0) 7760 178 530

 

 

Cenkos Securities (Nominated Adviser & Broker)

 

Stephen Keys / Camilla Hume

+44 (0) 20 7397 8900

 

 

Tavistock Communications

 

Simon Hudson/Kelsey Traynor

+44 (0) 20 7920 3150

 

-ends-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCNKODNFBKDQBB
Date   Source Headline
13th Dec 20174:40 pmRNSSecond Price Monitoring Extn
13th Dec 20174:35 pmRNSPrice Monitoring Extension
13th Dec 20177:00 amRNSHalf-year Report
8th Dec 20177:00 amRNSResult of Scrip Dividend Alternative
5th Dec 20177:00 amRNSNotice of Results
16th Nov 20177:00 amRNSScrip Dividend Reference Price
8th Nov 20177:00 amRNSDirectorate Change
31st Oct 201712:01 pmRNSResult of AGM
13th Oct 20178:50 amRNSNotice of Dividend
3rd Oct 20174:35 pmRNSPrice Monitoring Extension
29th Sep 20173:03 pmRNSPosting of FY2017 Annual report
29th Sep 20177:00 amRNSFinal Results
25th Sep 201712:25 pmRNSNotice of Results
30th Aug 201711:05 amRNSSecond Price Monitoring Extn
30th Aug 201711:00 amRNSPrice Monitoring Extension
30th Aug 20177:00 amRNSTrading Update & Notice of Results
31st May 20177:00 amRNSTrading update
5th Apr 20177:00 amRNSAmendment of Share Capital Rights in OPG Gujarat
28th Feb 201712:59 pmRNSREPLACEMENT: Trading update for Q3 FY17
28th Feb 20177:00 amRNSTrading update for Q3 FY17
22nd Feb 20178:30 amRNSDirectors' Shareholdings
20th Feb 20177:00 amRNSInterim Dividend Paid
17th Feb 20173:59 pmRNSUpdate on Dividend Payment Date
16th Feb 201711:53 amRNSResult of Scrip Dividend and Issue of Equity
26th Jan 20177:00 amRNSTrading Update
25th Jan 20171:09 pmRNSResult of Extraordinary General Meeting
10th Jan 20178:10 amRNSNotice of EGM
6th Jan 20179:22 amRNSScrip Dividend Reference Price
20th Dec 20168:00 amRNSDividend Declaration
6th Dec 20167:00 amRNSHalf-year Report
30th Nov 20163:54 pmRNSNotice of Half Year Results
14th Nov 20162:41 pmRNSResult of AGM and Board Changes
21st Oct 20165:43 pmRNSNotice of AGM
30th Sep 20161:28 pmRNSAnnual Financial Report
15th Sep 20168:30 amRNSCapital Markets Day Presentation
9th Sep 20168:50 amRNSBoard Changes
23rd Aug 20167:00 amRNSNotice of Capital Markets Day
1st Aug 20167:00 amRNSFinal Results
14th Jul 201612:44 pmRNSNotice of Results
5th Jul 20169:33 amRNSRenewable Growth Projects Pursued
24th May 20167:00 amRNSTrading and Dividend Update
26th Feb 20167:37 amRNSQ3 FY2016 Trading Update
1st Feb 20169:23 amRNSGujarat plant second 150 MW unit operational
22nd Dec 20152:26 pmRNSChennai weather update
1st Dec 20157:00 amRNSHalf Yearly Report
25th Nov 20154:28 pmRNSNotice of Half Year Results
5th Nov 20157:00 amRNSTrading Update
30th Oct 201512:09 pmRNSNotice of Trading Update
7th Oct 20151:27 pmRNSResult of AGM
5th Oct 20157:01 amRNSChennai Sales Contracts

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.