OPG Power Ventures plc, the developer and operator of power generation plants, presents a trading update for the three months ended 31 December 2013 (Q3 FY14).

 

Operational Highlights

· Q3 FY14 generation of 518 million units up 8% on Q2 FY14 (Q3 FY13: 301 million units)

· Total year-to-date generation up 129% on nine months ended 31 Dec 2012

· C3 unit fully ramped up; average Plant Load Factor (PLF) achieved across all units of 100% in the quarter (Q2 FY14: 93%)

· Average year-to-date PLF across all units of 96% up from 90% in nine months ended 31 Dec 2012

· Q3 FY14 Underlying Rupee Revenue of Rs 2.67 bn compared with Rs 4.82 bn in full year FY13

· Entered into a 15 year Long Term Variable tariff arrangement with TANGEDCO for C3, providing foreign exchange protection on imported coal

· Full year results expected to meet market expectations

 

Project Highlights

· 300 MW Gujarat (2x150 MW units) - within budget and on track for commissioning by Sep 2014

· 160 MW Chennai IV - within budget and on track for commissioning by Dec 2014

 

Parameter

Quarter ended

31 Dec 13

Quarter ended

30 Sep 13

Quarter ended

31 Dec 12

Nine Months ended

31 Dec 13

Nine Months ended

31 Dec 12

Full year ended

31 Mar 13

Generation (Mn units)

Chennai I

161

164

155

493

448

617

Chennai II

178

172

146

512

146

315

Chennai III

178

143

-

355

-

-

Total (Mn units)

518

479

301

1360

594

932

PLF (%)

Chennai I

95

97

91

97

88

92

Chennai II

105

101

96

101

96

99

Chennai III

101

81

-

88

-

-

Average (%)

100

93

93

96

90

94

Tariff (Rs/kWh)

5.54

5.52

5.53

5.55

5.52

5.58

 

Projects

 

Provided below is a quantified assessment of the progress of the Company's current and most significant projects. This is based purely on management's experience and not verified by any third party and is presented by reference to each of the key stages in a typical project in development. It is a management estimate at the date of this statement only and does not purport to quantify the risk of any project not commissioning.

 

Project stage

Financing

Civil Works and Foundations

Chimney/Boiler related/Rest of plant

Chennai IV

100%

90%

50%

Gujarat

100%

92%

72%

 

At Chennai IV, almost all civil works and foundations have been completed. The boiler drum has been erected and installed and the air cooling condensers are in advanced construction. A team of around 300 are working full time at the site, to be joined by a further 50 when turbine deliveries commence around June 2014. Balance of plant completion and equipment testing, including hydro tests, should follow in the subsequent quarter. Chennai IV shares its storage, power evacuation and water treatment facilities with Chennai II and III. Our leadership team for the delivery of Chennai IV is the same as on the previous three Chennai units and the project continues to be on track for commissioning in the current calendar year.

 

Our 300 (2x150) MW Gujarat project also continues to progress well. The installation and hydro testing of both boilers has been completed successfully. Turbines of both units are now at site and the turbine of one of the units has been installed. Chimney construction is complete. Construction of the balance of plant is ongoing and should finish in June 2014. Thereafter, we expect to commence test firing in the subsequent quarter and the project continues to be on track for commissioning around September 2014.

 

Our website at www.opgpower.com has been updated with recent photographs of all operations and projects.

 

Outlook

 

We remain positive as to the Company's prospects as both expansion projects are progressing well and we continue to expect to commission significant additional capacity in 2014. Due to the strong performance of our operating assets, we remain confident that the results for the current financial year will meet market expectations.

 

About OPG

 

OPG is operating and developing power projects in India under the group captive model with 235 MW in operations and a further 460 MW under development. In the six months ended 30th September 2013, Group revenues were £47.7m, EBITDA was £13.7m and profit before tax was £7.6m.

 

For further information, please visit www.opgpower.com or contact:

 

OPG Power Ventures PLC

+91 (0) 44 429 11 211

Arvind Gupta

 

V Narayan Swami

 

 

 

Cenkos Securities (Nominated Adviser & Broker)

 

Stephen Keys / Camilla Hume

+44 (0) 20 7397 8900

 

 

Tavistock Communications

 

Simon Hudson/James Collins

+44 (0) 20 7920 3150

 

-ends-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTQKQDNOBKDDBD
Date   Source Headline
5th Oct 20157:00 amRNSGujarat Transmission Line Update
14th Sep 20154:30 pmRNSAnnual Report and Annual General Meeting
11th Aug 20157:00 amRNSTrading Statement
16th Jun 20157:17 amRNSStart of Commercial Sales at Chennai IV
2nd Jun 20157:00 amRNSFinal Results
21st May 20157:00 amRNSNotice of Results
14th Apr 20157:00 amRNSOperations Update
27th Feb 20155:25 pmRNSThird Quarter FY2015 Trading Update
22nd Dec 20147:00 amRNSGrant of Options
19th Dec 20142:24 pmRNSResult of AGM
8th Dec 20147:00 amRNSHalf Yearly Report
26th Nov 20147:00 amRNSNotice of AGM and Relationship Agreement
20th Nov 20147:00 amRNSSecond Quarter Trading Update
15th Oct 20147:00 amRNSChennai Sales Contract
15th Sep 20144:35 pmRNSAnnual Financial Report
11th Sep 20147:00 amRNSCoal Supply Update
26th Aug 20147:00 amRNSTrading Statement
6th Aug 20147:00 amRNSLong Term Freight Arrangement
1st Jul 20147:00 amRNSProject Update
18th Jun 20144:17 pmRNSHolding(s) in Company
21st May 20147:00 amRNSFinal Results
16th May 20149:03 amRNSNotice of Results
17th Feb 20147:00 amRNSTrading Update
28th Jan 20147:00 amRNSLong Term Variable Tariff Arrangement Chennai III
21st Nov 20137:00 amRNSHalf Yearly Report
23rd Oct 20137:00 amRNSExtension of Contract
30th Sep 20132:14 pmRNSResult of AGM
10th Sep 201311:01 amRNSAnnual Financial Report
6th Sep 20134:14 pmRNSNotice of AGM
29th Jul 20137:00 amRNSTrading Statement
2nd Jul 20137:00 amRNSExtended coal agreement
20th Jun 20137:00 amRNSFinal Results
11th Jun 20137:00 amRNSCommissioning of Sales and Chennai III
29th May 20137:00 amRNSTrading Statement
3rd May 20137:00 amRNS80MW Chennai III Update
28th Feb 20137:00 amRNSTrading Update
13th Dec 20127:00 amRNSHalf Yearly Report
26th Nov 20127:00 amRNSDate for Interim Results
23rd Oct 20127:00 amRNSTrading Update
18th Sep 20123:35 pmRNSResult of AGM
18th Sep 20127:00 amRNSSuccessful Commissioning of Chennai II 77 MW Plant
15th Aug 20127:00 amRNSFinancial Closure for 80MW Chennai IV
7th Aug 20129:46 amRNSDirector/PDMR Shareholding
6th Aug 20125:05 pmRNSHolding(s) in Company
30th Jul 20127:00 amRNSDirector/PDMR Shareholding
27th Jul 20127:00 amRNSDirector/PDMR Shareholding
25th Jul 20125:59 pmRNSDirector/PDMR Shareholding
25th Jul 20129:35 amRNSAnnual Financial Report
16th Jul 20124:40 pmRNSSecond Price Monitoring Extn
16th Jul 20124:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.