India Workover Update

10 Nov 2015 07:00

RNS Number : 1195F
Oilex Ltd
10 November 2015
 



ASX Announcement

 

10 November 2015

 

ASX: OEX

AIM: OEX

India Workover Update

· Cambay-19z workover successfully completed

· Workover rig relocated to Cambay-20 and workover has commenced

· Preparation for workover of Cambay-77H has commenced

· Reviewing other potential workover candidates

Oilex Ltd is pleased to provide the following Workover Update:

Cambay-19z

Oilex successfully completed the Cambay-19z workover on budget. The workover rig was at location for 15 days. Currently 240 bbls of workover brine is being pumped from the well at the rate of 40bbls per day after which oil production should commence. Adjustments to the pumping rate will be made to optimise the oil production after recovery of the workover brine. Cambay-19z is an oil producer from the Eocene (EP IV) formation and located approximately 1.4 km to the west of Cambay-77H.

Cambay-20

The Cambay-20 workover commenced on 5 November after completion of the rig move from Cambay-19z. Cambay-20 is an intermittent oil and gas producer located approximately 200 metres from Cambay-77H. It is connected to Cambay-73 facilities via a temporary flowline to recover gas for sale during intermittent oil production. It is an older legacy well and the workover is to recover, inspect, clean and replace as necessary, the production tubing. In addition, installation of a downhole pump is expected to improve oil production.

Cambay-77H

It is expected workover activities at Cambay 77-H will commence after Cambay-20 following confirmation of delivery times for various components sourced from North America. As such, preparations have commenced to isolate the reservoir section of the well such that the frac tree can be replaced with a production tree and production tubing can be installed. As previously announced, Cambay-77H will be connected to the Cambay-73 facilities via the temporary flowline and gas sold into the low-pressure market in the immediate vicinity of the field.

Other potential workover candidates

· Cambay-70 - located adjacent to Cambay-77H pad, a gas and oil producer from Eocene/MBS formation

· Cambay-60 - located approximately 2.3 km to the south of Cambay-77H, tested gas and condensate from OSII formation but never put into production

· Cambay-15 - located approximately 3.3 km to the south of Cambay-77H, a former gas producer from the OSII formation that may still be capable of servicing the low pressure market

 

 

Managing Director of Oilex, Ron Miller, said;

"The Cambay workover campaign continues with the successful completion of activities at Cambay-19z. The pumping performance to date indicates good well deliverability. We remain vigilant on costs while focusing on increasing cashflow from production. We are excited to build up momentum through the workover campaign and capture the commercial benefit of lower contractor service prices currently prevalent in the market."

For and on behalf of Oilex Ltd

 

Ron Miller

Managing Director

 

For further information, please contact the company or its advisors listed below: 

PAC Partners Pty Ltd

Australian Broker

Andrew Shearer

Email: ashearer@pacpartners.com.au

Tel: +61 3 8633 9862

Australia

Westhouse Securities Limited

AIM Broker

Robert Finlay / Alastair Stratton

Email:  alastair.stratton@westhousesecurities.com

Tel: +44 20 7601 6100

UK

 

Strand Hanson Limited

Nominated Adviser

Rory Murphy / Ritchie Balmer

Email:  

oilex@strandhanson.co.uk

Tel: +44 20 7409 3494

UK

 

Vigo Communications

Public Relations UK

Patrick d'Ancona / Chris McMahon

Email:patrick.dancona@vigocomms.com

chris.mcmahon@vigocomms.com

Tel: +44 20 7016 9570

UK

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLBMBITMBJBMAA
Date   Source Headline
26th Nov 20147:00 amRNSShare Purchase Plan - Notice Under ASIC 09/425
24th Nov 20147:00 amRNSASX Trading Halt
19th Nov 20147:00 amRNSAppendix 3Z
18th Nov 20148:36 amRNSResults of Annual General Meeting 18 November 2014
18th Nov 20147:00 amRNSWithdrawal of AGM Resolution 3
18th Nov 20147:00 amRNSAGM Chairman's Review
18th Nov 20147:00 amRNSAGM Presentation to Shareholders
17th Nov 20147:00 amRNSCambay-77H - Production Test shut-in commenced
11th Nov 20147:00 amRNSAppendix 3B
11th Nov 20147:00 amRNSAppendix 3Y
5th Nov 20147:00 amRNSCambay-77H - Production Test has commenced
4th Nov 20147:00 amRNSSection 708 Notice and Appendix 3B
31st Oct 20148:55 amRNSQuarterly Report 30 September 2014
31st Oct 20147:00 amRNSCambay-77H Delivering proof of concept objectives
27th Oct 20147:00 amRNSCambay-77H - Preparing for Production Test
21st Oct 20147:00 amRNSAppointment of Chief Financial Officer & Co.Sec.
16th Oct 20147:27 amRNS2014 Annual Report to Shareholders
16th Oct 20147:24 amRNSNotice of Annual General Meeting
16th Oct 20147:00 amRNSBoard Composition
8th Oct 20147:00 amRNSCambay-77H - Flowback continues
7th Oct 20147:00 amRNSChange of Nominated Adviser (NOMAD)
17th Sep 20149:22 amRNSCambay-77H - Intervention Complete
16th Sep 20147:00 amRNSS.708 Notice and Appendix 3B - Exercise of Options
12th Sep 201410:05 amRNSFinancial Report for Year Ended 30 June 2014
5th Sep 20147:00 amRNSCanning Basin SPA 17 AO - Work Commitment complete
3rd Sep 20148:32 amRNSAppendix 3B
28th Aug 20149:15 amRNSSection 708 Notice and Appendix 3B
21st Aug 20147:58 amRNSCambay-77H - Interim Flow-back Update
11th Aug 20149:45 amRNSS.708 and Appendix 3B - Exercise of Listed Options
8th Aug 20148:30 amRNSS.708 and Appendix 3B - Exercise of Listed Options
5th Aug 201410:15 amRNSS.708 and Appendix 3B - Exercise of Listed Options
5th Aug 20147:00 amRNSAppendix 3B
4th Aug 20147:00 amRNSCambay-77H - Flow-back Update
1st Aug 20147:00 amRNSSection 708 Notice and Appendix 3B
31st Jul 20147:39 amRNSSection 708 Notice and Appendix 3B
24th Jul 20147:00 amRNSQuarterly Report 30 June 2014
21st Jul 201410:11 amRNSCambay-77H - Flaring Gas and Light Oil Recovered
15th Jul 20147:44 amRNSEquity Financing Facility Drawdown and Appendix 3B
15th Jul 20147:00 amRNSCambay - Gas Sales Agreement Endorsed
14th Jul 20147:00 amRNSCambay-77H Well - Milling Operations Complete
7th Jul 20149:37 amRNSCambay-77H Well Frac Stim Operations Complete
4th Jul 20142:21 pmRNSCambay-77H Well Frac Stim Operations Update
2nd Jul 20147:34 amRNSAppendix 3Y
2nd Jul 20147:00 amRNSCambay-77H Well Frac Stim Operations Update
1st Jul 20149:17 amRNSExpiry of Unlisted Employee Options
24th Jun 20147:00 amRNSCambay-77H Well - Commencement of Frac Stimulation
23rd Jun 20147:14 amRNSChange of interests of substantial holder
9th Jun 20147:00 amRNSCambay-77H Well Fracture Stim Operations Update
2nd Jun 20147:00 amRNSCanning Basin - Prospectivity and Interpretation
21st May 20149:01 amRNSAppendix 3B

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.