India Operations Update

21 Dec 2015 07:00

RNS Number : 6587J
Oilex Ltd
21 December 2015
 



ASX Announcement

 

21 December 2015

 

ASX: OEX

AIM: OEX

 

India Operations Update

 

l Cambay-77H produced ~715 boe during first 10 days, ~2.7MMscf gas and 252 bbls of condensate

l Cambay-77H gas sales averaged ~0.267MMscfd with a maximum peak rate of 0.572MMscfd

l The Bhandut-3 well and the associated gas production facilities are ready for start-up

Oilex Ltd is pleased to provide the following update:

Cambay-77H

Since restarting production, the Cambay-77H initial average production rate for 10 days (IP10) was ~71.5boepd. Although demand for gas fluctuates on a regular basis, as anticipated, production from Cambay-77H has gradually increased from 51boepd as previously announced on 7 December 2015. The well continues producing through a 1/64 inch choke and the average tubing head pressure for the same period was ~2,400psig. The condensate gas ratio (CGR) increased to an average of ~92.5bbls/MMscf from the previously reported 55bbls/MMscf. It is expected that with further production, the CGR may decrease to the anticipated 40-50bbls/MMscf as the tubing head pressure decreases.

Gas is sold into the low-pressure market in the immediate vicinity of the field. The well continues to meet the local low pressure market including a peak demand rate of ~0.500MMscfd for ~1 hour that occurs twice daily. Further increases in the overall market will be dependent on successful marketing efforts that are currently underway.

Ongoing production from Cambay-77H will allow a fuller understanding of its deliverability potential from the Y zone and the longer term CGR. This production data will be used to update the numerical simulation model created as part of the Independent Resource Assessment completed by RISC in April 2015 (refer ASX announcement dated 16 April 2015).

Cambay 73

Cambay-73 remains shut in, as Cambay 77H can meet current demand from the low-pressure market.

Bhandut Field

The Bhandut-3 well and the associated gas production facilities are ready for start-up (see attached photographs). The gas buyer is responsible for construction of a flowline to deliver the gas for further processing. This work has commenced and is estimated to be complete in early January 2016 at which time Bhandut-3 will commence commercial production. It is planned that Bhandut-3 will start-up at 0.7MMscfd and its performance will be closely monitored.

Joint Venture Matters

Oilex is continuing to work closely with our joint venture partner via regular meetings to resolve the outstanding receivable amount owed to the joint venture, and rescheduling the drilling of Cambay-78H and Cambay-80H wells.

   

Managing Director of Oilex, Ron Miller, said;

"Cambay continues to deliver positive results with Cambay-77H gas production gradually increasing as the low pressure gas market demand permits. While the higher than anticipated CGR at present is positive, ongoing production data is necessary to determine its sustainability. Another major milestone for 2015 has been achieved with Bhandut-3 and the gas production facilities ready for start-up. Oilex continues to focus on growing production and cashflow in India underpinned by a significant independently assessed Reserve and Resource base."

 

For and on behalf of Oilex Ltd

 

Ron Miller

Managing Director

For further information, please contact:

 

Investor Enquiries

Oilex Ltd

Ron Miller

Managing Director

Email: oilex@oilex.com.au

Tel: +61 8 9485 3200

Australia

Nominated Adviser

Strand Hanson Limited

Nominated Adviser

Rory Murphy /Ritchie Balmer

Email: oilex@strandhanson.co.uk

Tel: +44 20 7409 3494

UK

 

Media Enquires

Vigo Communications

Public Relations UK

Patrick d'Ancona / Chris McMahon

Email: patrick.dancona@vigocomms.com

chris.mcmahon@vigocomms.com

Tel: +44 20 7016 9570

UK

 

 

http://www.rns-pdf.londonstockexchange.com/rns/6587J_-2015-12-21.pdf 

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLPKDDPBBDKNBB
Date   Source Headline
1st Jul 20157:27 amRNSTrading Halt
29th Jun 20157:00 amRNSCambay Field - Gas Sales Commence
10th Jun 20157:00 amRNSPAC Partners Broker Research
8th Jun 20157:00 amRNSCambay-73 : Pipeline & pre-commissioning completed
8th Jun 20157:00 amRNSChange of Registered Office
20th May 20158:33 amRNSAppendix 3B - Cancellation of Unlisted Options
18th May 20157:00 amRNSPESA Deal Day Presentation
14th May 201510:16 amRNSJPDA 06-103 Joint Venture
13th May 20157:00 amRNSJPDA 06-103 Joint Venture
11th May 20158:51 amRNSInterview with Oilex Managing Director
11th May 20157:00 amRNSOILEX Investor Presentation May 2015
30th Apr 20157:00 amRNSQuarterly Report 31 March 2015
29th Apr 20157:00 amRNSInterview with Oilex Managing Director
28th Apr 20157:00 amRNSCambay-73 : Production Facilities Completed
20th Apr 20157:03 amRNSOILEX Investor Presentation April 2015
16th Apr 20157:06 amRNSCambay Field - Reserves and Contingent Resources
14th Apr 20159:51 amRNSAppointment of Australian Broker
26th Mar 20157:00 amRNSCambay-73 - Construction of Oil & Gas Facilities
20th Mar 20158:37 amRNSInterview with Managing Director
19th Mar 20157:00 amRNSAppointment of UK Broker
18th Mar 20157:00 amRNSAppendix 3B - Exercise of Listed Options
16th Mar 201512:31 pmRNSOilex Investor Presentation March 2015
9th Mar 20157:46 amRNSIndia Operations Update with Addendum
9th Mar 20157:00 amRNSIndia Operations Update
19th Feb 20157:00 amRNSAppendix 3B - Issue of Employee Options
12th Feb 20159:28 amRNSInterview with Oilex Managing Director
11th Feb 20157:00 amRNSInterim Financial Report half-year 31 Dec 2014
5th Feb 20157:00 amRNSOilex Investor Presentation - February 2015
3rd Feb 20157:00 amRNSAppendix 3X J Auld
30th Jan 20157:00 amRNSQuarterly Report 31 December 2014
28th Jan 20157:00 amRNSAppointment of UK Based Non-Executive Director
27th Jan 20157:00 amRNSAppendix 3B - Cancellation of Unlisted Options
21st Jan 20157:00 amRNSInterview with Oilex Vice Chairman
20th Jan 20157:00 amRNSChange of Share Registry
19th Jan 20157:00 amRNSCambay-77H - Gas Sales Agreement Endorsed
30th Dec 20147:00 amRNSAdmission of Shares and Total Voting Rights
24th Dec 20147:00 amRNSNotice of Change in Substantial Holding
23rd Dec 20149:16 amRNSAppendix 3Y R Miller
23rd Dec 20149:14 amRNSAppendix 3Y M Cozijn
22nd Dec 20148:50 amRNSCleansing Notice and Appendix 3B
19th Dec 20149:10 amRNSCompletion of SPP Raising A$2.5 Million
12th Dec 20147:00 amRNSCambay Basin demonstrates strong economics
11th Dec 20147:00 amRNSCanning Basin SPA 17 AO
8th Dec 20147:00 amRNSCambay-77H - Successful Well Test
5th Dec 20149:18 amRNSShare Purchase Plan - Extension to ClosingDate
5th Dec 20148:31 amRNSBhandut-3 - Gas Sales Agreement Endorsed
1st Dec 20147:00 amRNSCambay-77H - Production Test Complete
28th Nov 20148:52 amRNSUK Shareholders Access to Share Purchase Plan
28th Nov 20147:00 amRNSInterview with Oilex Ltd Managing Director
26th Nov 20147:00 amRNSShare Purchase Plan Offer Document

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.