DRILLING UPDATE

27 Jan 2011 07:00

RNS Number : 1590A
Nyota Minerals Limited
26 January 2011
 



 

 

 

27 January 2011

 

Nyota Minerals Limited ('Nyota' or the 'Company')

 

Drilling Update

 

Highlights

·; Further definition drilling of recently discovered high-grade feeder zone at the Tulu Kapi Project in Ethiopia ("Feeder Zone");

·; Drilling has commenced aimed at increasing the size of the high-grade Feeder Zone;

·; Further intersections made in Lode 3;

·; Drill results for UNDP Prospect have returned encouraging results and a potential opportunity to increase the global resource.

 

High-grade Feeder Zone

 

The high grades announced on 9 December for intersections in the Feeder Zone were exceptional and warranted additional investigation to establish the full extent of this mineralised structure. The Feeder Zone discovery has required a review of the development strategy for Tulu Kapi as the Feeder Zone may provide scope for future production from an underground mining operation in parallel to the planned open pit. Previously drilled reverse circulation drill holes have been re-opened and extended with a diamond drill which has continued to extend the Feeder Zone. The three holes reported have intersected Feeder Zone style mineralisation some distance away from the discovery hole and represent mineralisation that has been deposited in a similar fashion to the Lodes 1, 2 and 3. Grades achieved include peak intersections of 6.15g/t Au over 8.67m and 3.08g/t Au over 19.31m.

 

 

Borehole

Depth From

(m)

Depth To

(m)

Length

(m)

Grade

(g/t Au)

TKBH-067

415.00

422.22

7.22

1.49

TKBH-067

419.70

422.22

2.52

3.67

TKBH-070

352.84

372.15

19.31

3.08

TKBH-070

358.62

367.29

8.67

6.15

TKBH-075

391.75

393.55

1.80

12.93

TKBH-075

413.50

421.58

8.08

2.67

 

Further deep drilling has commenced to target the Feeder Zone beneath the previous intersection achieved on TKBH074 previously returning a peak average grade of 37.04g/t Au over 15.07m. Three diamond drill rigs have been assigned to the Feeder Zone exploration programme.

 

Lode 3

 

Four additional diamond drill holes have intersected mineralisation through Lode 3. The encouraging results (tabulated below) are expected to add mineable gold ounces to an open pit mine plan and will be included in the PEA scheduled for release later in this quarter.

 

Borehole

Depth From

(m)

Depth To

(m)

Length

(m)

Grade

(g/t Au)

TKBH-067

224.70

238.76

14.06

1.15

TKBH-067

247.72

253.00

5.28

1.39

TKBH-070

233.50

242.85

9.35

3.48

TKBH-073

223.93

233.87

9.94

2.37

TKBH-075

204.60

204.95

0.35

6.41

TKBH-075

216.85

225.00

8.15

1.74

TKBH-075

229.70

239.83

10.13

5.03

TKBH-075

252.55

257.00

4.45

2.12

TKBH-075

262.70

266.63

3.93

2.64

 

UNDP Prospect 

 

Borehole TKBH-063 drilled into the UNDP Prospect intersected low-grade gold mineralisation between the depths of 11.60m and 107.79m down the hole. Whilst the grades recorded may be low, the Company believes that confirmation of gold mineralisation in the UNDP Prospect is significant. The UNDP Prospect is composed of a Tulu Kapi style syenite and is located immediately north of the current limit of the main Tulu Kapi orebody. The presence of gold mineralisation in another syenite indicates further evidence of a structural corridor extending from Tulu Kapi, north through the UNDP Prospect and for a further estimated 10 km within which lies a number of other discrete Tulu Kapi style syenites that remain to be explored (the "Tulu Kapi Trend"). Further drilling is required over the UNDP Prospect before the true potential for a resource can be confirmed.

 

Borehole

Depth From

(m)

Depth To

(m)

Length

(m)

Grade

(g/t Au)

TKBH-063

11.60

12.15

0.55

2.33

TKBH-063

49.20

56.00

6.80

1.01

TKBH-063

62.70

63.10

0.40

2.58

TKBH-063

100.90

107.79

6.89

1.11

 

Terry Tucker, Chief Executive Officer commented "The ability to extend old reverse circulation holes with a diamond drill to further define the Feeder Zone has provided information quickly and enabled the Company to redirect three diamond drill rigs to focus on drilling extensions of the high-grade zone. The mineralised intersections on the UNDP Prospect are very encouraging. Nyota has, based on recent geophysical surveys, mapping and historical soil geochemistry identified the Tulu Kapi Trend. The presence of gold mineralisation in a separate syenite body north of Tulu Kapi, potentially with additional Tulu Kapi style syenites continuing further northwards along the Tulu Kapi Trend, encourages our view that there may be a developing gold province".

 

For further information please contact:

 

Terry Tucker

Nyota Minerals Limited

info@nyotaminerals.com

 

NOMAD

Richard Brown / Jennifer Boorer

Ambrian Partners Limited

+44 (0)20 7634 4700

 

BROKER

Guy Wilkes / Will Slack

Ocean Equities Limited

(+44) (0) 20 7786 4370

 

BROKER

Rory Scott

Mirabaud Securities LLP

(+44) (0)20 7878 3360

 

Or visit: http://www.nyotaminerals.com

 

The technical exploration and mining information contained in this Announcement has been reviewed and approved by Mr Terry Tucker (P.Geo). Mr Tucker has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves and as a qualified person under the AIM Note for Mining, Oil and Gas Companies. Mr Tucker is a registered Professional Geoscientist with the Association of Professional Engineers and Geoscientists of British Columbia, Canada.

 

Mr Tucker consents to the inclusion in this Announcement of such information in the form and context in which it appears.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSEIEDMFFSEDF
Date   Source Headline
1st May 20137:00 amRNSNew Presentation and Strategic Review Update
29th Apr 20137:30 amRNSQuarterly Report
25th Apr 20137:01 amRNSPresenting at Master Investor investment show
23rd Apr 20134:40 pmRNSSecond Price Monitoring Extn
23rd Apr 20134:35 pmRNSPrice Monitoring Extension
9th Apr 20134:40 pmRNSSecond Price Monitoring Extn
9th Apr 20134:35 pmRNSPrice Monitoring Extension
8th Apr 201310:45 amRNSCompletion of Tranche 2 Placement
4th Apr 20133:45 pmRNSHolding in Company
4th Apr 201311:31 amRNSCLOSING OF SHARE PURCHASE PLAN
4th Apr 201311:30 amRNSResults of GM
28th Mar 20137:02 amRNSPresentation at Proactive Investors Forum
27th Mar 20138:45 amRNSChange of Director Interest
19th Mar 20138:45 amRNSRetirement of Directors
14th Mar 201311:45 amRNSHalf Year Results
6th Mar 20139:10 amRNSSPP Documentation
6th Mar 20139:02 amRNSHolding(s) in Company (Replacement)
5th Mar 20139:31 amRNSNOTICE OF MEETING OF SHAREHOLDERS
1st Mar 20139:00 amRNSHolding(s) in Company
28th Feb 20139:35 amRNSCompletion of Tranche 1 Placement
28th Feb 20139:30 amRNSHolding in Company
21st Feb 20138:16 amRNSPlacing of £4.0 million and Share Purchase Plan
31st Jan 201311:30 amRNSDecember Quarterly Report
21st Jan 20137:00 amRNSPositive Feeder Zone Drill Update & Trading Update
17th Jan 20137:00 amRNSEthiopian Ministry Confirms DFS Compliance
6th Dec 20127:00 amRNSDFS Demonstrates Potential for 105,000oz pa
3rd Dec 20127:00 amRNSFurther high-grade gold mineralisation identified
16th Nov 20127:00 amRNSResults of Annual General Meeting
31st Oct 201212:35 pmRNSQuarterly Report to 30/09/12 (Replacement)
31st Oct 201210:20 amRNSQuarterly Report period ended 30 September 2012
24th Oct 20124:35 pmRNSPrice Monitoring Extension
15th Oct 20127:00 amRNSNotice of AGM
9th Oct 20127:00 amRNSMineral Resource Update
28th Sep 20123:45 pmRNSFinal Results
28th Aug 20127:00 amRNSTulu Kapi Project Update
2nd Aug 201211:03 amRNSHolding(s) in Company
31st Jul 201211:40 amRNSQuarterly Report for the period ended 30 June 2012
27th Jul 20127:00 amRNSHolding in Company
12th Jul 20128:41 amRNSIFC Subscription Completed - Section 708A Notice
6th Jul 20121:44 pmRNSSubmission to the Ministry of Mines
25th Jun 20127:00 amRNSExploration Drilling Update
21st Jun 20127:00 amRNSAppointment of Non-Executive Director
21st Jun 20127:00 amRNSIFC Subscription to raise GBP1.3m
11th Jun 20127:06 amRNSDFS and Exploration Update
6th Jun 20129:12 amRNSHoldings in Company
16th May 20124:40 pmRNSSecond Price Monitoring Extn
16th May 20124:36 pmRNSPrice Monitoring Extension
8th May 20128:59 amRNSHoldings in Company
4th May 20122:48 pmRNSHoldings in Company
30th Apr 20127:00 amRNSQuarterly Report 31 March 2012

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.