Immediate Release 7 November 2011

 

 

GLOBAL ENERGY DEVELOPMENT PLC

(the "Company")

PROGRESS ON TORCAZ CHOPS RECOMPLETION

AND TILODIRAN OPERATIONS

 

Global Energy Development PLC, the Latin America focused petroleum exploration and production company (AIM: GED), with operations in Colombia and Peru is pleased to announce the following update regarding the cold heavy oil production with sand ("CHOPS") recompletion of the Torcaz #5 well and the Tilodiran field operations.

 

REGIONAL STRATEGY REFOCUS - Middle Magdalena Valley

 

In light of recent technology advances in heavy oil production and fractured reservoir development, Global Energy Development is refocusing reserve exploitation to the Middle Magdalena valley. Over 88% of the Company's 2P oil reserves are located in the Bocachico and Bolivar Contract areas within the Middle Magdalena valley, and positive results are anticipated with the ongoing CHOPS project on the Torcaz #5 well within the Bocachico Contract area.

 

In previous years, the Company has accelerated the development of its oil reserves in the Llanos Basin of Colombia (Alcaravan, Rio Verde and the Canacabare / Los Hatos Contract areas) which has been the primary focus for the Company and its capital investment. Over 70% of Colombia's oil production comes from the Llanos Basin as Colombia's largest producing field (Rubiales) is located in the eastern Llanos Basin. This success has lead to pipeline access constraints in the area and consequently increased truck transportation costs. As such the Company will continue to maximise production in the Llanos Basin whilst optimising cost margins, which is evident at the Tilodiran field. Currently, approximately 95% of the Company's daily oil production comes out of the Llanos Basin, but only 6% of the Company's 2P oil reserves are located within these contract areas.

 

Steve Voss, Managing Director, commented "Colombia is enjoying the continued success and increase of its country-wide oil development and production. The strategic decision to refocus on the Middle Magdelena valley will help to optimise cost margins and exploit a larger proportion of the Company's 2P oil reserves."

 

BOCACHICO CONTRACT - Torcaz Field, Middle Magdalena Valley

 

CHOPS (Cold Heavy Oil Production with Sand) Project - Torcaz #5 well

 

The Company is moving forward with its plans to utilise one of the existing Torcaz wellbores, the Torcaz #5, for the initial CHOPS workover operation which targets the Lower Mugrosa formation. The Directors hope this plan will increase the Company's incremental production and allow for the further development of the Torcaz reserves at lower overall costs. Global engaged with skilled service and equipment providers with CHOPS experience and completed the planning and design of the operation, and a workover rig was mobilised in late October.

 

Operations have begun to remove the existing sand screens and clean out the well casing which could take approximately 14 to 20 days. The Torcaz #5 was originally drilled in 1999 and previously tested at sustained rates of 300+ barrels of oil per day through unscreened perforations before sanding up using conventional pumps. Sand screens were subsequently installed to control the sand influx. The previous unscreened flow behavior of Torcaz #5 has encouraged the company to use this wellbore as the first test of the CHOPS process in the Torcaz field.

 

Following completion of the well clean-out, the Company plans to utilise a total perforated section of 175 feet in the Lower Mugrosa formation and to install the abrasives tolerant PCP pump. Following installation of the pump (expected to be completed in December), the Company will test the well to analyse sand production to determine the final separation facility design. Expected capital costs of the recompletion project are approximately $1.5 million and will be funded out of cash from existing operations.

 

RIO VERDE CONTRACT - Tilodiran Wells, Llanos Basin

 

In order to minimise overall water production and improve cost margins at the Tilodiran field, the Company initiated a procedure on the Tilodiran 2 well to isolate and thereby reduce water production from the water-prone Ubaque formation and stimulate the Gacheta formation. Following the successful stimulation of the Gacheta formation in late October, the Tilodiran 2 well was placed on pump and is in the process of producing back imbibed Ubaque formation fluids and stimulation load fluids prior to the production of the Gacheta formation fluids. Following further testing and clean up, and when production resumes from the Gacheta formation only, the Company expects to recommence production from the Tilodiran 2 well with lower water levels and a targeted oil cut of approximately 350 gross bopd.

 

Secondly, the Company has its necessary environmental permits to convert the abandoned Rio Verde 2 well into water disposal service for the Tilodiran field and expects to proceed with the conversion in January 2012 pending certain final regulatory approvals. This project is expected to reduce water disposal costs per barrel of water from approximately $5.00 to approximately $1.00.

 

UPDATED INVESTOR PRESENTATION AVAILABLE ON WEBSITE

 

The Company is also pleased to announce it has updated its presentation to its investors regarding the Company and its operations. The shareholder presentation is now available to view on the Company's website at www.globalenergyplc.com.

 

For further information please contact

 

Global Energy Development PLC

Anna Williams, Director of Business Development

+001 817 310 0240

awilliams@globalenergyplc.com

www.globalenergyplc.com

 

 

Buchanan (Financial PR)

Tim Thompson

+44 (0)20 7466 5000

Ben Romney

Helen Chan

 

 

Notes to Editors:

 

About CHOPS

CHOPS is a proven technique used by the Canadian oil industry of extracting heavy crude oil where sand production is encouraged as a means of enhancing well productivity using abrasives tolerant pumps. Using abrasives tolerant pumps, substantial production rate improvements over non-CHOPS techniques have been reported. The Company has 2P oil reserves of 75 million BOE (60% of Global's 2P reserve base) within the Bocachico Contract area as at 31 December 2010.

 

About Global Energy Development

The Company's shares have been traded on AIM, a market operated by the London Stock Exchange, since March 2002 (AIM: GED). The Company's balanced portfolio includes the countries of Colombia and Peru and comprises a base of production, developmental drilling and workover opportunities and several exploration projects. The Company currently holds six contracts: five in Colombia and one in Peru.

 

The information contained within this announcement has been reviewed by Mr. Stephen Voss, a Director of the Company, for the purpose of the Guidance Note for Mining, Oil and Gas Companies issued by the London Stock Exchange in respect of AIM companies which outlines standards of disclosure for natural resource projects. Mr. Voss is a Registered Professional Engineer in Texas and has been a Member of SPE for 27 years.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDKADKCBDDDDK
Date   Source Headline
15th Dec 20067:58 amRNSDirector Shareholding
12th Dec 20067:01 amRNSConvertible Notes
16th Nov 20067:00 amRNSOperations Update
28th Sep 20067:01 amRNSHolding(s) in Company
14th Sep 20062:41 pmRNSShare Option Grant
11th Sep 20067:02 amRNSInterim Results
6th Sep 20064:04 pmRNSHolding(s) in Company
4th Sep 20067:00 amRNSResources Study
29th Aug 20067:01 amRNSAppointment
22nd Aug 20067:00 amRNSRig Contract
25th May 20067:04 amRNSActivity Update
24th May 20063:34 pmRNSHolding(s) in Company
24th May 20063:32 pmRNSResult of AGM
10th May 200610:09 amRNSForm 10-Q
5th May 20063:58 pmRNSExercise of Options
4th May 20067:01 amRNSResults of Well Test
2nd May 20062:37 pmRNSAdmission to CREST
27th Apr 20067:00 amRNSAnnual Report and Accounts
20th Apr 20067:01 amRNSHolding(s) in Company
6th Apr 20067:00 amRNSNew Contract
28th Mar 20067:02 amRNSOperations Update
16th Mar 20067:01 amRNSHolding in company
15th Mar 20063:54 pmRNSExercise of Options
22nd Feb 20067:02 amRNSFinal Results
13th Feb 20067:00 amRNSDrilling Update
13th Jan 20067:01 amRNSNew Subsidiary Office
4th Jan 20067:00 amRNSNew Contract
7th Dec 20057:01 amRNSDrilling Update
23rd Nov 20057:02 amRNSNew Contract Approval
22nd Nov 20059:00 amRNSExercise of Options
11th Nov 20057:29 amRNSOperations Update
1st Nov 20057:01 amRNSConvertible Note
27th Oct 20051:59 pmRNSHolding(s) in Company
27th Oct 20057:00 amRNSDrilling Update
17th Oct 20057:00 amRNSOperations Update
3rd Oct 20053:37 pmRNSSAR 5-Global Energy Develop.
29th Sep 20053:35 pmRNSExercise of Options
15th Sep 20055:00 pmRNSSAR 3 - Global Energy Dev.
15th Sep 20054:42 pmRNSHolding(s) in Company
12th Sep 200512:43 pmRNSSAR 3 - Global Energy Dev.
9th Sep 20053:30 pmRNSHolding(s) in Company
8th Sep 20053:30 pmRNSHolding(s) in Company
2nd Sep 20057:00 amRNSHolding(s) in Company
1st Sep 20057:01 amRNSInterim Results
18th Aug 20059:00 amRNSChange of Registered Office
16th Aug 20055:51 pmRNSNotice of Results
16th Aug 20055:51 pmRNSExercise of Warrants
16th Aug 20055:51 pmRNSDrilling Update
16th Aug 200510:00 amRNSNotice of Results
16th Aug 20057:00 amRNSExercise of Warrants

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.