The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksMetals Exploration Regulatory News (MTL)

Share Price Information for Metals Exploration (MTL)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 5.10
Bid: 5.00
Ask: 5.20
Change: -0.15 (-2.86%)
Spread: 0.20 (4.00%)
Open: 5.25
High: 5.25
Low: 5.05
Prev. Close: 5.25
MTL Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Updated Mineral Reserve Estimate

27 Apr 2020 12:01

RNS Number : 9862K
Metals Exploration PLC
27 April 2020
 

27 April 2020

METALS EXPLORATION PLC

 

Updated Mineral Reserve Estimate

 

Metals Exploration plc (AIM: MTL) ("Metals Exploration", the "Company" or the "Group"), the natural resources exploration and development company with assets in the Pacific Rim region, today provides an update to the 2011 estimated gold reserves at its Runruno gold project ("Runruno" or the "Project") in the Philippines.

Summary of Report

In association with the Company's review of its mining plan for the remaining life of mine ("LOM"), the Company commissioned Xenith Consultancy to complete an updated independent JORC compliant reserve estimate (the "Updated Reserve Estimate"). The last independent reserve estimate was compiled in 2011 by Mining Associates, Brisbane.

Since the publication of the 2011 estimate, the Company has completed little additional resource drilling; with the vast majority of drilling being undertaken purely for mining grade control purposes. As a result, the Updated Reserve Estimate was, to a large extent, based upon the existing 2011 resource model.

Set out below are several matters that should be considered in conjunction with the Updated Reserve Estimate. The steps undertaken to evaluate the resource and develop the updated mine plan, and hence a new reserve estimate for this project are outlined below.

· A review of the Company's existing LOM plan was completed by Xenith Consultancy with the following considerations:

o Understanding current mine and dump strategy.

o Identifying critical items constraining the mine plan.

o Updated geotechnical parameters.

o Developed a Malilibeg fault zone model.

o Optimised pit design including reviewing the sensitivity of pit limits to resource category.

· Update the Mine Design:

o Develop ultimate pit limits taking into account the geotechnical criteria, optimiser results and pit access.

o Pit optimisation based on an average 85% recovery and US$1,200 gold price.

o Develop pit stages considering mine access and in-pit dumping requirements.

o Develop both in-pit and ex-pit dumps.

· Following mine design, several production and dump schedules (including truck haulage requirements) were analysed.

· Review of mine economics based on the Company's internal budgets and economic models.

Updated Reserve Estimate

Table 1 - 2020 Ore Reserve estimate

Reserve

Ore

Gold

Category

Mt

g/t

M Oz

Proved

nil

nil

nil

Probable

11.7

1.38

0.50

Total

11.7

1.38

0.50

Inferred included in LOM model pit

Inferred material

2.7

1.21

0.10

 

· The existing Resource model, developed in March 2011, was used for the new Reserve analysis.

· An updated economic cut-off at 0.59 g/t Au has been used.

· 4.76 Mt of Reserves depleted by mining from commencement of production to the end of 2019.

· All Measured and Indicated Resources have been converted to Probable Reserve (reflecting Geotechnical and Hydrogeology uncertainties).

· Mining grade dilution increased to 25% (in-line with reconciled actual performance).

· Mining recovery approximately 85% inclusive of a 5% mining loss.

· Measured Resource - converted to 7.9Mt of Probable Reserve.

· Indicated material - converted to 3.7Mt of Probable Reserve.

· Inferred material - forms only 6% of the planned tonnage in the first 3 years of the updated mine plan.

· Inferred material - 73% of the 2.7Mt is only scheduled for mining in the last 3 years of the updated mine plan.

· LoM pit design remains economic with Inferred material included at zero grade.

 

Reconciliation to 2011 Reserve estimate

 

The 2011 Reserves estimate, prepared by Mining Associates, Brisbane, is shown in table 2 below.

 

Table 2: Ore Reserve Estimate - 2011

Reserve

Ore

Gold

Category

Mt

g/t

M Oz

Proved

10.2

1.90

0.60

Probable

4.8

1.77

0.26

Total

15.0

1.86

0.87

Inferred included in LOM model pit

Inferred material

2.9

1.73

0.16

 

While overall tonnes have been depleted at a rate consistent with the available tonnes as estimated in both the 2011 and 2020 reserve estimates, the grade in the 2011 reserve estimate has proven to be inaccurate. The 2020 Updated Reserve Estimate is reflective of the mining dilutions achieved over the past 3 years.

 

Application of a more accurate resource to reserve recovery has been included with the analysis with approximately 85% of the resource estimated as recoverable, versus a previous assumption of approximately 95% recoverable.

 

Total ounces unaccounted between the two reserve estimates is approximately negative 20Koz, when mining depletion and new mining loss factors are applied. By considering the updated 0.59 g/t cut-off grade (2011: 0.03 g/t) the final difference between the two statements is reconciled.

 

The Company has a planned drilling programme, to be undertaken during the second half of 2020 and during 2021. This will provide the next basis for updating the project's Reserve estimate.

 

 

This Announcement contains inside information as defined in Article 7 of the Market Abuse Regulation No. 596/2014 ("MAR"). Upon the publication of this Announcement, this inside information is now considered to be in the public domain.

- END -

 

 

For further information please visit or contact www.metalsexploration.com

 

METALS EXPLORATION PLC

Darren Bowden (Chief Executive Officer)

+63 908 8500 051

Michael Langoulant (Chief Financial Officer)

+44 (0) 7899 249990 

Nominated & Financial Adviser and Broker: STRAND HANSON LIMITED

James Spinney, James Dance

+44 (0) 207 409 3494

Financial Adviser: HANNAM & PARTNERS

Andrew Chubb

+44 (0) 207 907 8500

Public Relations: TAVISTOCK

Barnaby Hayward, Jos Simson

+44 (0) 207 920 3150

 

 

Competent Persons' Statement

The information contained in this release that relates to the 2020 gold Reserves Estimate is based on information compiled by Mr Iain Ross, who is am a Member of The Australasian Institute of Mining and Metallurgy and the Australian Institute of Geoscientists. Mr Ross is a full-time employee of Xenith Consulting. Mr Ross has sufficient experience that is relevant to the style of mineralisation and type of deposit described in the release to qualify as a Competent Person as defined by the JORC Code, 2012 Edition. Mr Ross consents to the inclusion of this information in the form and context in which it appears in this release.

 

Mr Darren Bowden, a director of the Company, a Member of the Australasian Institute of Mining and Metallurgy and who has been involved in the mining industry for more than 25 years, has compiled, read and approved the technical disclosure in this regulatory announcement in accordance with the AIM Rules - Note for Mining and Oil & Gas Companies.

 

 

Forward Looking Statements

Certain statements relating to the estimated or expected future production, operating results, cash flows and costs and financial condition of Metals Explorations, planned work at the Company's projects and the expected results of such work contained herein are forward-looking statementswhich are based on current expectations, estimates and projections about the potential returns of the Group, industry and markets in which the Group operates in, the Directors' beliefs and assumptions made by the Directors. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by words such as the following: "expects", "plans", "anticipates", "forecasts", "believes", "intends", "estimates", "projects", "assumes", "potential" or variations of such words and similar expressions. Forward-looking statements also include reference to events or conditions that will, would, may, could or should occur. Information concerning exploration results and mineral reserve and resource estimates may also be deemed to be forward-looking statements, as it constitutes a prediction of what might be found to be present when and if a project is actually developed.

 

These statements are not guarantees of future performance or the ability to identify and consummate investments and involve certain risks, uncertainties and assumptions that are difficult to predict, qualify or quantify. Among the factors that could cause actual results or projections to differ materially include, without limitation: uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from logistical, technical or other factors; the possibility that results of work will not fulfil projections/expectations and realize the perceived potential of the Company's projects; uncertainties involved in the interpretation of drilling results and other tests and the estimation of gold reserves and resources; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of environmental issues at the Company's projects; the possibility of cost overruns or unanticipated expenses in work programs; the need to obtain permits and comply with environmental laws and regulations and other government requirements; fluctuations in the price of gold and other risks and uncertainties.

 

The Company expressly disclaims any obligation or undertaking to disseminate any updates or revisions to any forward looking statements contained herein to reflect any change in the Group's expectations with regard thereto or any change in events, conditions or circumstances on which any such statements are based unless required to do so by applicable law or the AIM Rules.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLIRMMTMTATBBM
Date   Source Headline
19th Oct 20177:00 amRNSQuarterly Update To 30 September 2017
2nd Oct 20178:33 amRNSUS$21m Mezzanine Facility Documentation Completed
29th Sep 201711:45 amRNSInterim Results
29th Sep 201711:45 amRNSMezzanine Debt Facility
19th Sep 20177:00 amRNSOperations and Mezzanine Debt Facility Update
26th Jul 20177:00 amRNSQuarterly Update To 30 June 2017
30th Jun 20177:00 amRNSShort Term Funding Secured
15th Jun 201712:36 pmRNSResults of AGM
31st May 20177:00 amRNSFunding Update
24th May 20178:40 amRNSFunding
22nd May 20177:00 amRNSFinal Results For The Year Ended 31 December 2016
18th May 20177:00 amRNSAnnual General Meeting Announcement
24th Apr 201710:15 amRNSQuarterly Update To 31 March 2017
10th Apr 20178:28 amRNSDirector Resignation
15th Mar 20177:00 amRNSRunruno Gold project Update
18th Jan 201710:00 amRNSAppointment of Nominated Adviser and Broker
13th Jan 201711:14 amRNSDirector's Share Dealing
12th Jan 20171:50 pmRNSHolding(s) in Company
10th Jan 20179:50 amRNSDirector/PDMR Shareholding
19th Dec 201610:48 amRNSRescheduled Facility Agreement
8th Dec 20168:12 amRNSHolding(s) in Company
29th Nov 20167:33 amRNSFirst Gold Sale, Debt Rescheduling, Ramp Up
14th Nov 20167:00 amRNSEquity Raising
4th Oct 20163:04 pmRNSResults of General Meeting of Shareholders
30th Sep 20169:03 amRNSInterim Results
15th Sep 20161:52 pmRNSHolding(s) in Company
14th Sep 201611:19 amRNSNotice of General Meeting
8th Sep 20169:54 amRNSEquity Raising
26th Aug 201611:38 amRNSRunruno Gold Project Update
25th Jul 20162:37 pmRNSEquity Raising
15th Jul 20169:53 amRNSRunruno Gold Project Update
13th Jul 201610:10 amRNSRunruno Gold Project Update
30th Jun 201612:44 pmRNSRunruno Gold Project Update
24th Jun 201612:01 pmRNSResult of AGM
24th Jun 201610:32 amRNSRunruno Gold Project Update
13th Jun 20167:46 amRNSFirst Gold Pour
26th May 20162:12 pmRNSFinal Results
25th May 20169:15 amRNSNotice of AGM
11th May 20169:36 amRNSRunruno Gold Project Update
25th Apr 20169:24 amRNSLifting of Partial Suspension Order
22nd Apr 201612:07 pmRNSRESULT OF GENERAL MEETING
4th Apr 20167:00 amRNSNotice of General Meeting
29th Mar 20164:15 pmRNSDirector's Share Dealing
21st Mar 20161:00 pmRNSHolding(s) in Company
21st Mar 201612:55 pmRNSHolding(s) in Company
18th Mar 201611:45 amRNSTotal Voting Rights
11th Mar 201612:49 pmRNSEquity Raising
7th Mar 20168:56 amRNSPartial Suspension Order Update
26th Jan 201610:13 amRNSRunruno Project Update
1st Dec 20157:00 amRNSUpdate on Partial Suspension Order & Permitting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.